§ 12.01.040 — Review process
Municipal Code, City of Yakima, Washington (includes legislation through 10-06-2026) · Yakima Municipal Code § 12.01.040
Corpus is an independent public-information project, not the official City of Yakima website. Stable reference: corpuslaw.us/code/3a968dfe-847d-4e2f-b0f1-8a50f3809414
§ 12.01.040: Review process.
(1) The city engineer shall review design documents for public works improvements. No public works improvements may be constructed before appropriate fees are paid and the city engineer has provided written approval of the pertinent design documents. If the city engineer determines that proposed public works improvements and the related design documents conform to applicable requirements including this chapter, then the city engineer shall mark the original design documents “Approved” and affix his/her signature thereto, and these actions shall constitute written approval. (2) Proposals will ordinarily be reviewed and inspected in the order they are submitted to the city engineer. An. applicant may request expedited review or inspection; however, an applicant shall have no right to such expedited review or inspection. The city engineer may determine the terms and conditions of such expedited review or inspection, including, without limitation, compensation for city employee overtime work. (3) Public works improvements described by approved design documents must be constructed in conformity with the approved design documents and may not be changed, modified or altered without written approval of the city engineer. (4) The applicant shall, during construction, maintain a neatly marked, full-sized set of record drawings showing the layout and final location of all public works improvements involved in new construction. Prior to final acceptance by the city of Yakima of public works improvements, reproducible record drawings prepared by the civil engineer of record and clearly identified as record drawings shall be delivered to the city engineer for acceptance. (5) The applicant shall submit for written approval by the city engineer a detailed summary of the construction cost of approved public works improvements, which may include the contractor’s bid, the engineer’s estimate, or other items which may assist the city engineer to determine the cost of construction. (6) The applicant shall, upon the city engineer’s written approval of completed public works improvements, transfer ownership of such public works improvements to the city of Yakima. (7) Final acceptance by the city of Yakima of the actual public works improvements shall not occur before the applicant has satisfied all applicable requirements, including, without limitation, those of this chapter.
( Ord. 95-6 § 5, 1995 ; Ord. 2001-13 § 3, 2001 )
Ask a question about Yakima law
Corpus searches the Yakima sections it holds and shows the ones that match, with their citations. Free, no sign-in.