Sec. 16-81. - Stormwater management performance standards.

(a) Responsible party. The landowner of the post-construction site, or any other person obligated by agreement with the landowner to implement and maintain post-construction stormwater management measures, is deemed the responsible party and shall comply with this article. (b) Stormwater management plan. The responsible party shall develop and implement a written post-construction stormwater management plan that incorporates the requirements of this section. (c) Development districts. All land development activities shall conform to stormwater management standards established for the development district within which the development occurs. (d) Maintenance of effort. For redevelopment sites where the redevelopment will be replacing older development that was subject to post-construction performance standards of Wis. Admin. Code Ch. NR 151 in effect on or after October 1, 2004, the responsible party shall meet the total suspended solids reduction, peak flow control, infiltration, and protective areas standards applicable to the older development or meet the redevelopment standards of Wis. Admin. Code §§ NR 151.122 through 151.125, or the City of Green Bay stormwater standards, whichever is more stringent. (e) Stormwater discharge quantity. Unless otherwise provided for in this article, all land development activities subject to this article shall establish on-site management practices to control the peak flow rates of stormwater discharged from the site as described in this article. The amount of peak discharge control previously required for the site shall not be reduced as a result of the proposed development or land disturbance. Infiltration of stormwater runoff shall be in accordance with Wis. Admin. Code Ch. NR 151 and WDNR Technical and Guidance Standards. (1) On-site management practices shall be used to meet the minimum performance standards for each development district as described in the applicable subsection below. a. All developments smaller than five acres in size in the Urban Service District shall not increase peak flow rates of stormwater runoff from that which would have resulted from the same storm occurring over the site with the land in its existing land use conditions for design rainfall events with recurrence intervals of two, ten, and 100 years. The Director of Public Works may require more stringent or less stringent criteria if it has been determined that the downstream storm sewers can or cannot handle the runoff from the site. b. All developments five acres in size or larger in the Urban Service District shall be subject to the criteria described in subsection (e)(1)c. of this section. The Director may require more stringent or less stringent criteria if it has been determined that the downstream storm sewers can or cannot handle the runoff from the site. c. All proposed land developments in the Urban Reserve and Urban Expansion Districts shall not increase peak flow rates of stormwater runoff from that which would have resulted from the same storm occurring over the site with the land in its pre-development land use conditions for design rainfall events with recurrence intervals of two, ten, and 100 years. The Director may require more stringent or less stringent criteria if it has been determined that the downstream storm sewers can or cannot handle the runoff from the site. (2) All stormwater conveyance systems within the proposed development of all development districts and receiving surface runoff from the proposed development shall be designed to completely contain peak storm flows as described in subsections (b)(2)a and b of this section. Calculations for determining peak flows for conveyance system sizing shall be based on the existing or future proposed land use conditions for off-site areas (whichever results in the highest peak flows), and the future proposed land use conditions for the on-site areas. a. For publicly-owned or maintained open channel conveyance systems, the peak flow from the 25-year storm shall be completely contained within the channel bottom and banks. b. For publicly-owned or maintained storm sewer pipes, the peak flow from the ten-year storm shall be completely contained within the pipes with no surcharging or pressurized flow. c. Private storm sewer pipes shall be constructed to contain the peak flow from the five-year storm with no surcharging or pressurized flow. (3) Determination of peak flow rates and volume of runoff for purposes of meeting the requirements of subsections (e)(1) and (2) of this section shall be computed by procedures based on the principles and procedures approved by the Director of Public Works. (4) The amount of peak discharge control previously required for the site shall not be reduced as a result of the proposed development or disturbance. (5) An adequate outfall shall be provided for each point of concentrated discharge from the post-construction site. An adequate outfall consists of non-erosive discharge velocities and reasonable downstream conveyance. (6) All discharges will be restricted to public drainage systems (including storm sewers and ditches) or to waters of the state or the U.S. It shall be the responsibility of the applicant to obtain from adjacent property owners any easements or other necessary property interests concerning flowage of water from the proposed development onto private lands. (7) Increases or decreases in the hydrology of natural wetlands shall be minimized to the extent practical. Where such changes are proposed, the impact of the proposal on wetland shall be assessed and meet the requirements of Wis. Admin. Code Ch. NR 103. (8) Emergency overland flow for all stormwater facilities shall be provided to prevent exceeding the safe capacity of downstream drainage facilities and prevent endangerment of downstream property or public safety. (f) Stormwater discharge quality. Unless otherwise provided for in this article, all land development activities subject to this article shall establish on-site management practices to control the quality of stormwater discharged from the site. On-site management practices shall be used to meet the following minimum standards established for each development district: (1) Stormwater management measures in the Urban Expansion District and Urban Reserve District shall be designed to remove, on an average annual basis, a minimum of 80 percent of the total suspended solids load from the proposed on-site development when compared to the proposed on-site development without stormwater management measures. The effectiveness of the stormwater management measures shall be evaluated using criteria provided by the Director. (2) Stormwater management measures for developments in the Urban Service District smaller than five acres shall be designed to remove, on an average annual basis, a minimum total suspended solids load of 40 percent for redevelopment sites and a minimum of 80 percent for new development from the proposed on-site development when compared to the proposed on-site development without stormwater management measures. The effectiveness of the stormwater management measures shall be evaluated using criteria provided by the Director. (3) The Director may require stormwater management measures in the Urban Service District for developments five acres or larger to be designed to remove, on an average annual basis, a minimum of 80 percent of the total suspended solids load from the proposed on-site development when compared to the proposed on-site development without stormwater management measures. The effectiveness of the stormwater management measures shall be evaluated using criteria provided by the Director. (4) Discharge of urban stormwater pollutants to natural wetlands shall have pretreatment and vegetative buffers, unless otherwise exempted by the Director. (5) Infiltration of stormwater runoff shall be in accordance with Wis. Admin. Code Ch. NR 151 and WDNR Technical and Guidance Standards. When an applicant proposes infiltration basins, bio-filtration or bio-infiltration basins, or other such practices as BMPs for the site, the stormwater management plan required under Section 16-82 shall contain a soils investigation following WDNR Technical Standard 1002. (6) Stormwater discharges shall have pretreatment prior to infiltration to prolong maintenance of the infiltration practice and to prevent discharge of stormwater pollutants at concentrations that will result in exceedance of groundwater preventive action limits or enforcement standards established by the Department of Natural Resources in Wis. Admin. Code Ch. NR 140. Stormwater infiltration is prohibited under the following circumstances: a. Stormwater generated from highly contaminated source areas at manufacturing industrial sites. b. Stormwater carried in a conveyance system that also carries contaminated, non-stormwater discharges. c. Stormwater generated from active construction sites. (7) Petroleum products in runoff from gas pump areas and vehicle maintenance areas shall be controlled with a properly designed and maintained oil and grease separator or other equivalent practice. The structure or practice shall remove all visible sheen from the runoff prior to discharge to waters of the state, the U.S., or the City's storm sewer system. With appropriate documentation, a combination of the following BMPs or others may be used and maintained to prevent or treat petroleum in runoff: canopies, oil and grease separators, petroleum spill cleanup materials, or any other structural or nonstructural methods. (8) Stormwater ponds and infiltration devices shall not be located closer to water supply wells than indicated below without first notifying the Director. a. 100 feet from a private or transient non-public water supply well; b. 1,200 feet from a municipal water supply well; or c. The boundary of a recharge area to a well identified in a well head area protection plan. (9) The amount of total suspended solids control previously required for the site shall not be reduced as a result of the proposed land development, land disturbance, or land-disturbing construction activities. (10) Pollutant loading models such as SLAMM, P8, or equivalent methodology shall be used to evaluate the efficiency of the design in reducing total suspended solids. (11) If the design cannot achieve the applicable total suspended solids reduction requirement , the stormwater management plan shall include a written and site-specific explanation why that level of reduction cannot be attained, and the total suspended solids load shall be reduced to the maximum extent practicable. (12) More or less stringent treatment limits may be required at the discretion of the Director. (13) Maximum extent practicable applies when a person who is subject to a performance standard under this article demonstrates to the Director's satisfaction that a performance standard is not achievable and that a lower level of performance is appropriate. In making the assertion that a performance standard is not achievable, the responsible party shall consider the best available technology, cost effectiveness, geographic features, and other competing interests such as protection of public safety and welfare, protection of endangered and threatened resources, and preservation of historic properties. (g) Technical standards. The following methods shall be used in designing and maintaining the water quality, peak discharges and infiltration, protective area, and fueling/vehicle maintenance components of stormwater practices needed to meet the water quality standards of this article: (1) Consistent with the Technical and Guidance identified, developed, or disseminated by the Wisconsin Department of Natural Resources under Subch. V of Wis. Admin. Code Ch. NR 151 (Wis. Admin. Code §§ NR 151.30—151.32) and as modified herein: a. Interior pond slopes shall be 4:1. b. The top of all berms for stormwater facilities shall be ten feet wide unless analysis is shown that a lesser width is acceptable to withstand saturated soil pressure. (2) Where technical standards have not been identified or developed by the Wisconsin Department of Natural Resources, other technical standards may be used provided that the methods are generally consistent with standards adopted by other Wisconsin jurisdictions and have been submitted to and approved by the Director. (h) Protective areas. Stormwater runoff through and around protective areas shall be in conformance with Wis. Admin. Code Ch. NR 151. (1) In this section, protective area does not include any area of land adjacent to any stream enclosed within a pipe or culvert, so that runoff cannot enter the enclosure at this location. a. For outstanding resource waters and exceptional resource waters: 75 feet. b. For perennial and intermittent streams identified on a United States Geological Survey 7.5-minute series topographic map, or a county soil survey map, whichever is more current: 50 feet. c. For lakes: 50 feet. d. For highly susceptible wetlands: 75 feet. Highly susceptible wetlands include the following types: fens, sedge meadows, bogs, low prairies, conifer swamps, shrub swamps, other forested wetlands, fresh wet meadows, shallow marshes, deep marshes and seasonally flooded basins. e. For less susceptible wetlands: ten percent of the average wetland width, but no less than ten feet nor more than 30 feet. Less susceptible wetlands include degraded wetlands dominated by invasive species such as reed canary grass, cultivated hydric soils; and any gravel pits, or dredged materials or fill material disposal sites that take on the attributes of a wetland. f. For wetlands not subject to subsections (h)(1)d or e of this section: 50 feet. g. In subsections (h)(1)a, d and e of this section, determinations of the extent of the protective area adjacent to wetlands shall be made on the basis of the sensitivity and runoff susceptibility of the wetland in accordance with the standards and criteria in Wis. Admin. Code § NR 103.03. h. For concentrated flow channels with drainage areas greater than 130 acres: ten feet. (2) Wetland boundary delineation shall be made in accordance with current Wisconsin Department of Natural Resources procedures. This subsection does not apply to wetlands that have been completely filled in compliance with all applicable state and federal regulations. The protective area for wetlands that have been partially filled in compliance with all applicable state and federal regulations shall be measured from the wetland boundary delineation after a fill has been placed. Where there is a legally authorized wetland fill, the protective area standard need not be met in that location. (3) Subsection (f) of this section applies to post-construction sites located within a protective area, except those areas exempted pursuant to subsection (h)(6) of this section. (4) The following requirements shall be met: a. Impervious surfaces shall be kept out of the protective area entirely or to the maximum extent practicable. If there is no practical alternative to locating an impervious surface in the protective area, the stormwater management plan shall contain a written, site-specific explanation. b. Where land disturbing construction activity occurs within a protective area, and where no impervious surface is present, adequate sod or self-sustaining vegetative cover of 70 percent or greater shall be established and maintained where no impervious surface is present. The adequate sod or self-sustaining vegetative cover shall be sufficient to provide for bank stability, maintenance of fish habitat and filtering of pollutants from upslope overland flow areas under sheet flow conditions. Non-vegetative materials, such as rock riprap, may be employed on the bank as necessary to prevent erosion, such as on steep slopes or where high velocity flows occur. c. Best management practices such as filter strips, swales, or wet detention basins that are designed to control pollutants from non-point sources may be located in the protective area. (5) A protective area established or created after the adoption date (July 19, 2016) of the ordinance from which this article is derived shall not be eliminated or reduced, except as allowed in subsection (h)(6)c, d, or e of this section. (6) Exemptions. The following areas are not required to meet the protective area requirements of subsection (f) of this section: a. Redevelopment and routine maintenance areas, provided the minimum requirements within in subsection (h)(5) of this section are satisfied. b. In-fill development areas less than five acres. c. Structures that cross or access surface waters such as boat landings, bridges and culverts. d. Structures constructed in accordance with Wis. Stats. § 59.692. e. Areas of post-construction sites from which runoff does not enter the surface water, except to the extent that vegetative groundcover is necessary to maintain bank stability. (i) General considerations for stormwater management measures. The following considerations shall be observed in on-site and off-site runoff management: (1) Natural topography and land cover features such as natural swales, natural depressions, native soil infiltrating capacity, and natural groundwater recharge areas shall be preserved and used, to the extent possible, to meet the requirements of this section. (2) Emergency overland flow for all stormwater facilities shall be provided to prevent exceeding the safe capacity of downstream drainage facilities and prevent endangerment of downstream property or public safety. (j) BMP location. (1) To comply with the performance standards required under this section, BMPs and stormwater management measures may be located on-site or off-site as part of a regional stormwater device, practice, or system, but shall be installed in accordance with Wis. Admin. Code § NR 151.003. (2) In addition to compliance with Wis. Admin. Code. § NR 151.003, additional requirements apply to certain onsite BMPs, as described in this section. a. Cisterns. An above-ground cistern shall be limited to a maximum of 5,050 gallons. The cistern shall be installed with proper mosquito/vector control and shall comply with applicable setback requirements. b. Planter boxes. Planter boxes shall not be used in areas where their operation may create a risk for basement flooding, interfere with subsurface sewage disposal systems, or affect other underground structures. Stormwater planter boxes shall be designed so that overflow drains away from buildings to prevent negative impacts to structures. (3) The Administering Authority may approve off-site management measures, provided that all of the following conditions are met: a. The administrating authority determines that the post-construction runoff is covered by a stormwater management system plan that is approved by the Director and that contains management requirements consistent with the purpose and intent of this article. b. The off-site facility meets all of the following conditions: 1. The facility has already been constructed and is currently serving a stormwater management function. 2. The facility is designed and adequately sized to provide a level of stormwater control equal to or greater than that which would be afforded by on-site practices meeting the performance standards of this article. 3. The facility has entered into a valid maintenance agreement in accordance with Section 16-84. (k) Exceptions. The Director of Public Works may waive the minimum requirements for on-site stormwater management practices established in subsections (e) and (f) of this section upon written request of the applicant, in which a site-specific explanation as to why that level of reduction is not attained and the total solids load shall be reduced to the maximum extent practicable, and provided that at least one of the following conditions applies: (1) Alternative minimum requirements for on-site management of stormwater discharges have been established in a stormwater management plan that has been approved by the Director of Public Works and that is required to be implemented by local ordinance. (2) Provisions are made to manage stormwater by an off-site facility. This requires that the off-site facility is in place, is designed and adequately sized to provide a level of stormwater control that is equal to or greater than that which would be afforded by on-site practices meeting the requirements of this article, and has a legally obligated entity responsible for long-term operation and maintenance of the stormwater practice. (3) The Director of Public Works finds that meeting the minimum on-site management requirements is not technically feasible due to site restrictions. (4) This article does not apply to redevelopment projects that result in no net increase in impervious area and does not have exposed parking lots or roads. (l) Additional requirements. The Administering Authority may establish stormwater management requirements more stringent than those set forth in this article if the Administering Authority determines that the requirements are needed to control stormwater quantity or control flooding, due to, but not limited to, insufficient downstream system capacity, potential erosion of stream channels, or impacts on flood stages, and to comply with federally approved total maximum daily load requirements, or control pollutants associated with existing development or redevelopment. (m) Fee in lieu of on-site stormwater management practices. Where the Director of Public Works waives all or part of the minimum on-site stormwater management requirements under subsection (k)(3) of this section, or where the waiver is based on the provision of adequate stormwater facilities provided by the City downstream of the proposed development, as provided for under subsection (k)(2) of this section, the applicant shall be required to pay a fee as provided in the City Fee Schedule. In setting the fee for land development projects, the City shall consider an equitable distribution of the cost of land, engineering design, and construction.

(Code 1984, § 30.06; Ord. No. 21-21, § 1, 10-5-2021; Ord. No. 17-22, §§ 6—11, 6-7-2022)