§ 10-169 — Performance standards for construction sites under one acre
Code of General Ordinances of the City of Janesville, Wisconsin (Codified through Ordinance No. 2026-935, enacted May 26, 2026. (Supp. No. 20)) · Janesville Code of General Ordinances § 10-169
Corpus is an independent public-information project, not the official City of Janesville website. Stable reference: corpuslaw.us/code/09b16802-9208-4e39-891c-1d4e13e30c0b
Sec. 10-169. - Performance standards for construction sites under one acre.
(a) Responsible party. The responsible party shall comply with this section. (b) Erosion and sediment control practices. Erosion and sediment control practices at each site where land disturbing construction activity is to occur shall be used to prevent or reduce all of the following: (1) The deposition of soil from being tracked onto streets by vehicles. (2) The discharge of sediment from disturbed areas into on-site stormwater inlets. (3) The discharge of sediment from disturbed areas into adjacent waters of the state. (4) The discharge of sediment from drainage ways that flow off the site. (5) The discharge of sediment by dewatering activities. (6) The discharge of sediment eroding from soil stockpiles existing for more than seven days. (7) The transport by runoff into waters of the state of chemicals, cement, and other building compounds and materials on the construction site during the construction period; however, projects that require the placement of these materials in waters of the state, such as constructing bridge footings or BMP installations, are not prohibited by this subdivision. (c) Location. The BMPs shall be located so that treatment occurs before runoff enters waters of the state. (d) Implementation. The BMPs used to comply with this section shall be implemented as follows: (1) Erosion and sediment control practices shall be constructed or installed before land disturbing construction activities begin. (2) Erosion and sediment control practices shall be maintained until final stabilization. (3) Final stabilization activity shall commence when land disturbing activities cease and final grade has been reached on any portion of the site. (4) Temporary stabilization activity shall commence when land disturbing activities have temporarily ceased and will not resume for a period exceeding 14 calendar days. (5) BMPs that are no longer necessary for erosion and sediment control shall be removed by the responsible party. (e) Inspection and maintenance records. The responsible party shall inspect and maintain records as follows: (1) Inspect the BMPs within 24 hours after each rainfall of 0.5 inches or more which results in runoff during active construction periods, and at least once each week and document these inspections in a log that also includes the date of inspection, the name of the person conducting the inspection, and a description of the present phase of the construction at the site. (2) Provide written notification to the Director of any failures in existing BMPs allowing sediment transport off site, make needed repairs, and install additional BMPs as necessary.
(Code 1976, § 15.05.070)