§ 18-250 — Permit

Code of General Ordinances of the City of Janesville, Wisconsin (Codified through Ordinance No. 2026-935, enacted May 26, 2026. (Supp. No. 20)) · Janesville Code of General Ordinances § 18-250

Corpus is an independent public-information project, not the official City of Janesville website. Stable reference: corpuslaw.us/code/a93a4078-d7d8-4701-ac56-52492303d92e

Sec. 18-250. - Permit.

(a) Permit required. No person, firm, or corporation shall raze or cause to be razed any building, structure, or part thereof without first obtaining a permit from the Building Official. (b) Permit application. The owner of the building to be razed shall sign the permit application. In the alternative, an agent for the owner may sign the permit application upon providing written authorization verifying the permission of the owner to apply for the permit. The Building Official may require additional information and other state or local permits as required by law, rule, or regulation. (c) Fees. Permit fees shall be established from time to time by the City Council. (d) Permit conditions. All permits shall be subject to the following conditions: (1) A Notice of Demolition DNR form #4500-113 must be completed and provided to the Building Official for all commercial buildings or residential buildings of five or more dwelling units if asbestos is being removed prior to demolition. An asbestos containing material (ACM) inspection will be completed by a certified asbestos inspector separate from and prior to work under a demolition permit. All asbestos containing materials which require removal prior to razing will be removed from the building by a certified asbestos abatement contractor separate from and prior to the start of work under a demolition permit. Proof of DNR approval must be submitted prior to issuance of a demolition permit. (2) Every person filing an application for a permit for the demolition of a major building or structure shall file with the Building Official such application a detailed plan indicating the manner in which the building or structure is to be demolished, the time schedule for all phases of the demolition work, a disposal plan for debris. The plan shall also address noise, dust, debris transport, hours of work, and protection of excavated or hazardous areas and disposal areas. (3) The razing of a building shall be completed within 60 days after the date the permit was issued. The Building Official may, at his or her discretion, extend the permit for cause. Cause shall mean the inability of the permittee to act due to circumstances beyond permittee's reasonable control upon the exercise of due diligence. (4) Work done under a demolition permit is subject to inspection by the Building Official who shall have the authority to order corrective work. Failure to follow the orders of the Building Official, or to complete the raze in accordance with this Code, shall give the Building Official authority to seek restitution from any required bond. If no bond, the cost thereof shall be assessed against the property as a special charge and added to the next tax roll against such property. (5) Whenever a building or structure has been razed, the foundation thereof, if any, shall be leveled to at least one foot below grade. The basement and other openings shall be filled to grade with sand, limestone, or other fill approved by the Building Official. No combustible material may be used for the fill material. The excavation must be filled to grade within a period of 60 days from the date the permit to raze had been issued, unless within that time actual new construction has been commenced on the site. If such excavation has not been filled, construction commenced, or an extension granted by the Building Official within the 60-day period of time, it shall be the duty of the Building Official to have the excavation filled and the cost thereof shall be assessed against the property as a special charge and added to the next tax roll against such property. (6) Remaining slabs and private sidewalks shall be removed from the site by the permittee prior to final approval. (7) Whenever a building or structure has been razed, the site shall be graded with a minimum of six inches of topsoil, with seed and mulch or sod applied to cover the entire disturbed area. (e) Major buildings. Additional condition of issuance by the Building Official of the permit for major buildings: (1) The applicant/permittee shall post with the City Clerk-Treasurer a surety bond payable to the City of Janesville in a form approved by the City Attorney in the amount of the actual cost of the permitted work. Such bond shall guarantee that all work is performed in accordance with this Code and other state and local laws, rules, and regulations, hold the City harmless from any costs and expenses arising from the permitted work, and secure timely performance of the work. The City may reasonably require a bond of a greater amount, on a case-by-case basis, where deemed necessary, to protect the City. In extraordinary circumstances, the City Council may allow for an alternate form of security in an amount deemed reasonably necessary and sufficient. The bond shall be made payable to the City of Janesville upon demand unless all work is timely completed by the permittee. (2) The permittee shall have the responsibility at all times to obtain, pay for, and maintain policies of insurance in the following minimum amounts, naming the City of Janesville as an additional and/or co-insured for all entities or natural persons doing work upon the property, building, and/or structure, or associated with the work under the permit, and shall maintain on file with the City Clerk-Treasurer current certificate of insurance for same: a. Commercial general liability: 1. General aggregate: $2,000,000.00. 2. Each occurrence $1,000,000.00. b. Automobile liability (owned, non-owned, leased): 1. Bodily injury: $1,000,000.00 each occurrence. 2. Property damage: $1,000,000.00 each occurrence. c. Pollution legal liability: $5,000,000.00 each loss where asbestos removal, environmental process, abatement, remediation, or dumping/disposal in a federal or state regulated facility is required. d. Workers' compensation: Statutory limits. e. Umbrella liability: $2,000,000.00 over the primary Commercial General Liability and Automobile Liability insurance coverages listed above. (3) Every person filing an application for a permit for the demolition of a major building or structure shall file with the Building Official such application a detailed plan indicating the manner in which the building or structure is to be demolished, the time schedule for all phases of the demolition work, a disposal plan for debris. The plan shall also address noise, dust, debris transport, hours of work, and protection of excavated or hazardous areas and disposal areas.

(Code 1976, § 16.08.020)