Extra compensation.
San José Municipal Code § 27.26.050
in effect27.26.050 - Extra compensation.
A. A Public Works Contract may include standard provisions for the payment of extra compensation to the Contractor for cost reduction changes in the plans and specifications made pursuant to a proposal submitted by the Contractor.
B. Any provisions included pursuant to Subsection A of this Section 27.26.050 must provide for the Contractor and City to negotiate the amount of extra compensation, provided that the extra compensation cannot exceed fifty percent (50%) of the net savings in construction.
(Ord. 30540.)
Source: City of San José, Municipal Code (Municode Library, library.municode.com)URL: https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT27PRPUWO_CH27.26CO_27.26.050EXCOFetched: 11/1/2026