Progress payments.
San José Municipal Code § 27.26.040
in effect27.26.040 - Progress payments.
Public Works Contracts will include standard provisions for progress payments consistent with this Section 27.26.040.
A. The City will review and act on progress payment requests submitted by a Contractor as soon as is practicable.
B. The City will endeavor to notify a Contractor on or before seven (7) Calendar Days after receiving a progress payment request if the request is not proper or otherwise does not comply with the requirements of the Public Works Contract. The City's notification will be in writing and will identify any deficiencies in the progress payment request.
C. The City will endeavor to make progress payments of undisputed amounts within thirty (30) Calendar Days of the Contractor's submission of a properly completed progress payment request that complies with the requirements of the Public Works Contract.
D. The City will not be liable for interest or other charges or costs if it fails to meet any of the times set forth in this Section 27.26.040.
E. There is no requirement to include in Public Works Contracts a copy or summary of California Contract Code Section 20104.60.
(Ord. 30540.)