Stormwater pollution prevention plan (SWPPP).
Oxford Code of Ordinances § 98-95
in effectSec. 98-95. - Stormwater pollution prevention plan (SWPPP).
(a) Applicable for all developments requiring site plan approval including, multifamily, subdivisions, commercial and industrial construction, and single-family residences over one acre, and/or those in critical areas.
(b) The stormwater pollution prevention plan shall be prepared by a certified erosion and sediment control specialist, such as a qualified credentialed professional (QCP), a certified professional of erosion and sediment control (CPESC) and/or a professional engineer.
(c) The plan shall at a minimum include the following:
(1) The name of the project;
(2) Intended use of the property;
(3) Map identifying topography, natural features such as watercourses, waterways, and wetlands, buffers, and proposed construction areas.
(4) The building site with corresponding dimensions scaled at no more than one inch equals 100 feet;
(5) The name, address and telephone number of the owner or lessee of the property;
(6) Construction phasing details describing the intended sequences of construction activities, including clearing and grubbing, excavation and grading, utility and infrastructure installation, final grading and landscaping, and any other activity at the site that results in soil disturbance. Sequencing shall identify the estimated duration of exposure of cleared areas.
(7) The specific erosion control plans proposed, as specified herein below;
a. The name, address and telephone number of the entity performing such work;
b. Total area to be cleared, graded, excavated or filled;
c. General description of work to be performed.
d. Erosion and sediment controls used throughout all phases of construction and details of permanent stabilization methods to be used at completion.
e. Provisions for maintenance of erosion and sediment controls.
f. Contact information for person responsible for inspecting the site each week and following rain events.
(d) Submittal, review, and approval procedures.
(1) The stormwater pollution prevention plan shall be submitted in conjunction with the land disturbance permit application.
(2) For sites requiring a stormwater permit from the state department of environmental quality (MDEQ), a copy of such approved permit shall also be submitted as part of the application for the permit. Any work to be performed within any 100-year floodplain area shall also be identified on maps or plats showing the existing elevations of the property, the 100-year floodplain and floodway areas, and the location and elevation of proposed fill material. No permit shall be required prior to beginning work in an emergency situation to repair or restore utility service. An application shall be made for a permit for all emergency cuts, digging, or excavations within 48 hours after the cuts, digging, or excavations have been made. However, a prospective applicant shall give verbal notice immediately to the building official or his or her designee upon determination that "emergency" work or construction is needed.
(3) Review of each stormwater pollution prevention plan shall be within 30 days of submittal to determine the plan's conformance with these provisions.
(4) The city shall:
a. Review the plan with reasonable, justifiable conditions to accomplish objectives and ensure that the plan meets or exceeds the provisions of the city BMP minimum requirements and the Field Manual.
b. City may elect to require a third party review for sites in or near critical areas.
(e) Modifications to the plan.
(1) Major modifications to the stormwater pollution prevention plan, such as the redesign of BMPs or removal of BMPs, shall be submitted to the city building department and shall be processed and approved, or disapproved, in the same manner as the original plan.
(2) Minor modifications to the stormwater pollution prevention plan, such as the use of additional temporary BMPS, may be addressed on site as needed to ensure compliance with the provisions.
(3) If a BMP failure occurs, as deemed by the city inspector, the city may require that the stormwater pollution prevention plan be modified and resubmitted.
(f) All sites, including single-family residential, shall comply with the city BMP minimum requirements specifications, as well as the stormwater pollution prevention plan (if any).
(Ord. No. 2014-26, § I, 7-1-2014)
Source: City of Oxford, Mississippi, Code of Ordinances (Municode Library, library.municode.com)URL: https://library.municode.com/ms/oxford/codes/code_of_ordinances?nodeId=COOR_CH98STSIROBR_ARTIVERCO_S98-95STPOPRPLSWFetched: 11/1/2026