Section 3.3.7. - Site development and subdivision construction plans.
A. Applicability. The procedures contained in this Section are applicable to all projects involving land development, including Site Development Plans (SDP) for individual sites, Subdivision Construction Plans (SCP), and sites without structures such as parking lots. Also included are projects which involve the construction of any facility, the expansion of a site through acquisition or lease, alteration or conversion of an existing site or structures, or the change of use of a site or structure where the site or structure does not meet the current standards or criteria of these regulations. The provisions of this Section, where appropriate, are to be applied to on-site and off-site development activity. No land development activity (including land clearing, excavation, or placement of fill) shall commence without obtaining the appropriate approvals and permits required by this code.
B. Exceptions. The requirements of this section do not apply to:
1. Single-family dwellings; or
2. Duplex dwellings on existing platted lots or parcels.
C. Plan Preparation. A professional engineer registered in the state of Florida shall design all required improvements such as streets, drainage systems, water and sewage facilities, etc. All plans, drawings, reports, and calculations shall be prepared, signed, and sealed by the appropriate licensed professional, such as engineers, architects, landscape architects, professional surveyors and mappers, or attorneys, registered in the state of Florida. Other specialized consultants, such as environmental consultants, structural engineers, archaeologists, etc., may be required to assist in the preparation of the plans, drawings, reports, or other documents required for application submittals.
D. Review Process. The application review and approval process follows the administrative review procedure as established in Sections 3.1.4 through 3.1.8 of this Article.
E. Criteria. The Development Services Manager may approve, approve with conditions, or deny the application, after consideration and review of the following:
1. The development, as proposed, conforms to the comprehensive plan and is consistent with the recommendations of any applicable PUD Master Concept Plan, Preliminary Subdivision Plan, or master plans which have been approved or accepted by the City Council;
2. The proposed development plans, landscape plans, engineering plans, lighting plans, and other required plans conform or will conform with all applicable City codes, the Engineering Design Standards, and design standards as set forth in this code;
3. The development will efficiently use or not unduly burden drainage, water, sewer, solid waste disposal, education, recreation, or other necessary public facilities which have been constructed or planned and budgeted for construction in the area;
4. The development provides sufficient on-site storm water management improvements to meet state water quality and flood protection standards;
5. The development will efficiently use or not unduly burden or affect public transportation facilities, including mass transit, public streets, roads, and highways which have been planned and budgeted for construction in the area, and if the development is or will be accessible by private or public roads, streets, or highways; and
6. The development provides necessary and adequate vehicular circulation, pedestrian access, ingress and egress, and is configured in a manner to minimize hazards and impacts on adjacent properties and adjacent rights-of-way.
7. Projects subject to SDP review comprised of 2 or more parcels with unique strap numbers must be combined into a single parcel with one strap number prior to approval of the Site Development Plan.
8. Projects subject to SDP review required to provide easements shall provide executed copies of staff approved easements to the City prior to approval of the Site Development Plan. The City may require such easements be accepted by City Council and recorded in the public records prior to approval of the Site Development Plan.
9. Projects that involve a vacation of plat or release of easement may have review or approval withheld until such vacation or release of easement has been approved or recorded, as determined by the Director.
10. The City may attach any reasonable conditions, safeguards, limitations, or requirements to the approval of a plan which are found necessary and consistent with the review to effectuate the purpose of this section and to carry out the purpose of this Code and the Comprehensive Plan.
F. Plats. If the development is a subdivision, a plat meeting the requirements of F.S. Ch. 177, Part 1 and the City of Cape Coral Technical Requirements for Plat Approval, which are hereby incorporated by reference, must be submitted prior to approval of Subdivision Construction Plans. The preliminary plat submittal is not required until after the first round of SCP sufficiency comments, though it may be submitted earlier. Refer to Article 10 Subdivisions.
G. Plan Approval. Upon successfully addressing departmental comments, the Development Services Manger shall approve the application provided all departmental reviewers have accepted the plans or accepted the plans with conditions. Upon receiving plan approval and meeting any applicable conditions, written construction authorization shall be provided for the applicant to begin those construction activities specifically covered by the plan approval.
H. Effect of Plan Approval. Site Development Plans and Subdivision Construction Plans are valid for two years from the date of approval. If written construction authorization to construct the improvements has not been obtained prior to the expiration date, the approval expires and becomes null and void. An applicant may apply for a one-year extension for good cause. Such an extension may be granted for any plan approved after the effective date of this ordinance and two years prior to adoption. The extension request must be filed prior to the expiration date of plan approval. If the project is within a PDP, a PUD, or a phased development, the expiration of plan approvals may differ, as established in the original approval. See Phased Projects Section 3.3.7.T for addition information regarding expiration of permits and plan approvals in phased projects.
I. Engineer's Opinions of Probable Construction Costs. The City shall review and approve all cost opinions prior to acceptance of same.
1. Inspection fees applied to development permits are based on a percentage of the estimated construction cost, of Developer installed improvement, to be turned over to the City for ownership and maintenance.
2. Opinions of Probable Construction Costs shall be prepared, signed, and sealed by the professional engineer of record.
3. Cost opinions shall be a unit quantity itemized estimate of the required improvements including: mobilization, material and other testing, survey stake out, and a 10% contingency. Lump sums are only to be used for items typically not contracted as unit price items.
4. Subdivisions. Cost opinions for subdivision improvements are to be provided as required in Article 10 of this code. The cost of improvements required to support a subdivision that will be turned over to the City for ownership and maintenance will be utilized in determining inspection fees for the subdivision infrastructure permit. Cost opinions for assuring the completion of subdivision improvements shall include, in addition to the items listed above, the cost of providing electrical service for lift stations, pump stations, or other components that may require electric service to function and setting PCP's. upon completion of construction.
J. Amendments. Plan amendments include changes to projects which impact multiple aspects of the development, may affect multiple plans, and will require multiple departmental reviews to evaluate the proposed amendment to the plan(s).
1. The amendment process may not be used to substantively modify the scheme of development as originally approved under an approved SDP or SCP.
2. Proposed amendments that impact a PDP or PUD approval criteria or conditions must receive approval of an amendment to the PDP or PUD prior to receiving SDP or SCP approval.
3. Amendments may apply to projects that are currently under review, projects under construction or phased projects that have yet to be completed.
4. The applicant shall submit a letter of intent, the applicable fee, the amended plan(s) and any other documentation required to review the proposed amendment.
5. The Development Services Manger shall determine if the proposed changes to the plan can be processed as an amendment, qualify for a lesser review process or requires a greater review process.
K. Revisions. Revisions to an approved plan while under construction which do not increase the gross square footage of a building or adversely impact compliance with the approved plan, and would not alter the required infrastructure and improvements necessary to serve the project, may be approved in writing by the Development Services Manager provided such revisions fully conform to all existing City regulations. The Development Services Manager will determine if the revision requires an approved plan revision or if the revision can be shown on the Record Drawings.
L. Limited Review. A Limited SDP Review for a new improvement or alteration of existing improvements to an approved project may be requested. Limited Reviews are for proposed improvements which do not substantially affect projects minimum technical requirements of this Code or do not require a review by three or more of the following review disciplines: zoning, planning transportation, drainage, fire, utilities, and landscaping. Changes that exceed the criteria for the scope of a Limited SDP review as specified in this subsection or, as determined by the Development Services Manager, may be processed as an amendment or a full SDP review in accordance with this section. Applications reviewed under this process will be reviewed for compliance with the following general criteria:
1. The development must have no significant adverse effect upon surrounding land uses;
2. The development must have no significant adverse effect upon public facilities in the area;
3. The development must not adversely affect the environmental quality of the area; and
4. The development proposal must be consistent with the City Comprehensive Plan.
M. Site Improvement Permit for minor changes. A permit review of minor changes to an existing development which does not require a separate Site Development Plan review. This approval process may be utilized when the existing project is in full compliance with an approved plan or the site proposed for a minor change meets the following criteria: Any changes to an approved Site Development Plan or project will not increase density, parking requirements, water or sewer usage, or enlarge a structure for human occupancy or assembly by more than 5% of the existing approved plan. For sites lawfully developed without Site Plan review, the 5% exception may be applied if the applicant submits all of the information required under SDP review. Determination of the 5% shall be cumulative based on the originally approved development.
1. All infrastructure exists on the site to service the site;
2. Engineering is not required for the proposed change;
3. Parking meets all parking code requirements;
4. The improvement does not significantly alter the traffic circulation system or significantly change the use of property;
5. The existing project is in compliance with an approved landscape plan or the code in effect at the time of the original construction; and
6. The existing project meets all storm water management requirements.