8-5-13. - Construction and Restoration Standards for Newly Constructed or Overlayed Streets.
(a) Prohibition of Excavation in Newly Constructed Streets: No person shall excavate an area in the pavement of any public street for a period of three years from the completion of construction or resurfacing except in compliance with the provisions of this section. (b) Application: Any application for a permit to excavate in a public street with surface paving less than three years old shall contain the following materials: (1) All permit application requirements set forth in section 8-5-4, "Permit Application," B.R.C. 1981; (2) Detailed and dimensioned engineering plans that identify and accurately represent the paved surface areas that will be impacted by the proposed excavation, including: (A) The city blocks affected, including the side streets at the ends of the city blocks; (B) The street width or alley width, including curb and gutter, over the total length of each city block affected; (C) The location, width, length and depth of the proposed excavation; (D) The total area of existing street or alley pavement in each individual city block that will be impacted; (E) The total area of proposed street excavation in each individual city block that will be impacted by the proposed excavation; and (3) A written statement addressing the criteria for approval. (c) Criteria for Approval: No permit for excavation in the right-of-way shall be approved unless the city manager finds that: (1) Boring or jacking under the pavement is not practical due to physical characteristics of the street or alley or other utility conflicts; (2) Alternative utility alignments that do not involve excavating the street or alley are found to be impracticable; (3) The proposed excavation cannot reasonably be delayed until after the three-year deferment period has lapsed; and (4) The proposed excavation is necessary to remedy an immediate threat to the public safety or the restoration of a utility service. (d) Exemptions for Emergency Operations: Emergency maintenance operations shall be limited to circumstances involving the preservation of life, property or the restoration of customer utility service. City and non-city-owned utility companies with prior authorization from the city manager to perform emergency maintenance operations within the public right-of-way shall be exempted from obtaining the above specified prior written approval from the city manager. The utility company shall submit, as required by subsection (b) of this section, detailed engineering plans no later than five working days after initiating the emergency maintenance operation. (e) Construction and Restoration Standards for Newly Constructed or Overlayed Streets: For any excavation or opening in a public street or alley in the three-year period following new construction or overlay, trenches shall be filled with flowable fill backfill material, and the streets shall be repaired so as to not reduce the useful life of the pavement in accordance with design and construction standards adopted by the city. (f) Remediation Requirement: If the total area of the proposed excavation exceeds fifteen percent of the total area of pavement within a block or involves a trench in excess of one hundred fifty feet in length, the applicant shall remediate the damage caused to the pavement. City and non-city-owned utility companies with prior authorization to perform emergency maintenance operations within the public right-of-way, as set forth in subsection (d) of this section, shall submit an engineering plan that complies with the standards set forth in subsection (b) of this section to the city no later than five working days after initiating the emergency maintenance operation. The city manager will review the remediation plan to determine if remediation will be required. Remediation will consist of a curb to curb grading profile and overlay, a centerline to curb grading profile and overlay, or a lane-line to curb grading profile and overlay, whichever is necessary in order not to decrease the average life expectancy of the street or alley surface. (g) Impact Fee for Loss of Useful Pavement Life: An applicant for a permit to excavate an area in the pavement of any public street with surface paving less than three years old shall pay an additional impact fee for loss of useful pavement life as set forth in section 4-20-6, "Public Right-of-Way Permit and Contractor License Fees," B.R.C. 1981, prior to the issuance of a permit for work in the public right-of-way unless the applicant will be required to remediate pursuant to subsection (f) of this section.
Ask a question about Boulder law
Corpus searches the Boulder sections it holds and shows the ones that match, with their citations. Free, no sign-in.