18.68.020: DEFINITIONS:
For purposes of this chapter the following terms mean:
AREA OF SHALLOW FLOODING: A designated AO, AH or VO zone on the flood insurance rate map (FIRM) with a one percent (1%) or greater annual chance of flooding to an average depth of one to three feet (3') where a clearly defined channel does not exist, where the path of flooding is unpredictable and where velocity flow may be evident. Such flooding is characterized by ponding or sheet flow.
AREA OF SPECIAL FLOOD HAZARD: The land in the floodplain within a community subject to a one percent (1%) or greater chance of flooding in any given year. The area is shown on the flood insurance rate map (FIRM) as zone A, AE, AH, AO, A1-99, VO, V1-30, VE or V.
BASE FLOOD: A flood having a one percent (1%) chance of being equaled or exceeded in any given year.
BASE FLOOD ELEVATION: The probable water surface elevation (in relation to mean sea level) of the base flood as determined by or approved by the city floodplain administrator.
CERTIFY OR CERTIFICATION: The specific reports, inspections and tests that are required have been performed in an appropriate manner, and such reports, inspections, tests and results comply with the applicable requirements of this chapter.
CITY FLOODPLAIN ADMINISTRATOR: The person designated by the director of the department of public utilities to direct the decision making process that aims to achieve the wise use of the city's floodplains. "Wise use" means both reduced flood losses and protection of the natural resources and function of floodplains.
CONSTRUCTION: Any manmade change to improved real property including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations located within the floodplain hazard area, whether or not the same requires building or other permits under this code.
DEVELOPMENT: Any manmade change to improved or unimproved real property including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials.
DRAINWAY: A natural or artificial land depression, with or without perceptible bed and banks, to which surface runoff gravitates to form a continuous or intermittent flow of water in a definite direction.
FLOOD INSURANCE RATE MAP (FIRM): The official, currently effective flood insurance rate map for Salt Lake City, Utah, as issued by the federal emergency management agency "FEMA" and any officially approved amendments (LOMCs) thereto, on which the floodplain hazard areas and the risk premium zones have been delineated.
FLOOD INSURANCE STUDY: The official report provided by the federal emergency management agency that includes flood profiles, the flood boundary floodway map, and the water surface elevation of the base flood.
FLOOD OR FLOODING: A general and temporary condition of partial or complete inundation of normally dry land area from the overflow of inland or tidal waters or the unusual and rapid accumulation or runoff of surface waters from any source.
FLOODPLAIN: Generally, a floodplain(s) is/are a relatively flat area or lowland(s) adjoining a river, stream, watercourse, ocean or lake which has been or may be covered by floodwater. Specifically, for purposes of this title, "floodplain(s)" shall be that area of the city designated within the boundaries of the official flood insurance rate map or amendments, which may be subject to periodic inundation in the event of the base flood.
FLOODPLAIN HAZARD AREA: The area containing the floodplain for a base flood in the city, as designated on the flood insurance rate map and approved amendments.
FLOODPROOFING: Any combination of structural or nonstructural additions, changes or adjustments to structures or property which reduce or eliminate flood damage to improved or unimproved real property, water and sanitary facilities, structures and their contents.
FLOODWAY: The channel of the river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood, without cumulatively increasing the water surface elevation more than a designated height.
HIGHEST ADJACENT GRADE: The highest natural elevation of the ground surface prior to construction or development next to the proposed wall of a structure.
LETTER OF MAP CHANGE (LOMC): A letter which reflects an official revision to an effective national flood insurance program map.
LEVEE SYSTEM: A flood protection system which consists of a levee, or levees, and associated structures, such as closure and drainage devices, which are constructed and operated in accordance with sound engineering practices.
LICENSED ARCHITECT: An architect who is registered with the department of registration of the state of Utah.
LOWEST FLOOR: The lowest floor of the lowest enclosed area (including basement). An unfinished or flood resistant enclosure, usable solely for parking of vehicles, building access or storage in an area other than a basement area is not considered a building's lowest floor; provided, that such enclosure is not built so as to render the structure in violation of the applicable nonelevation design requirements of section 60.3 of the national flood insurance program regulations.
MANUFACTURED HOME: A structure transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when connected to the required utilities. For floodplain management purposes the term "manufactured home" also includes park trailers, travel trailers, and other similar vehicles placed on a site for greater than one hundred eighty (180) consecutive days. For insurance purposes the term "manufactured home" does not include park trailers, travel trailers, and other similar vehicles.
MANUFACTURED HOME PARK OR MANUFACTURED HOME SUBDIVISION: A parcel (or contiguous parcels) of land divided into two (2) or more manufactured home lots for rent or sale.
MEAN SEA LEVEL: For purposes of the national flood insurance program, the North American vertical datum of 1988 (NAVD 88) or other datum to which base flood elevations shown on a community's flood insurance rate map are referenced.
NEW CONSTRUCTION: Structures or substantial improvement thereto for which the "start of construction" as defined in this section is commenced on or after the effective date of the ordinance codified herein.
NEW DEVELOPMENT: Any development proposal(s) and/or plan(s) submitted for approval, for which the development activities as defined in this section will commence on or after the effective date of the ordinance codified herein.
REGISTERED LAND SURVEYOR: A land surveyor who is registered with the department of registration of the state of Utah.
REGISTERED PROFESSIONAL ENGINEER: A civil engineer who is registered with the department of registration of the state of Utah.
REMEDY A VIOLATION: To bring the structure or other development into compliance with state or local floodplain management regulations, or, if this is not possible, to reduce the impacts of its noncompliance. Ways that impacts may be reduced include protecting the structure or other affected development from flood damages, implementing the enforcement provisions of this chapter or otherwise deterring future similar violations, or reducing federal financial exposure with regard to the structure or other development.
SPECIAL FLOOD HAZARD AREA (SFHA): The land in the floodplain within the community subject to a one percent (1%) or greater chance of flooding in any given year, which area may be designated as zone A, AO, AH, A1-30, AE, A99 on the FIRM.
START OF CONSTRUCTION: Applies to both new construction and substantial improvements and means:
A. Date Of Issuance: The date the building permit was issued, provided the actual start of construction, repair, reconstruction, placement or other improvement was within one hundred eighty (180) days of the permit date. The "actual start" means either the first placement of permanent construction of a structure or on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure.
B. Relocatable Office Or Structure: Start of construction for a "relocatable office building" (defined in section 18.84.010 of this title, or its successor) or other temporary structure shall be the date on which the relocatable office building is placed upon an approved site.
STRUCTURE: A walled and roofed building, temporary structure, or manufactured home that is in whole or in part aboveground.
SUBSTANTIAL IMPROVEMENTS: Any development and/or construction of a structure, the cost of which equals or exceeds either fifty percent (50%) of the market value of the structure before the development is started, or, if the development or construction is undertaken for repair of damage caused by accident or acts of God, fifty percent (50%) of the same market value of the structure before the damage occurred.
VIOLATION: The failure of a structure or other development to fully comply with these floodplain management regulations. A structure or other development without the elevation certificate, other certifications, or other evidence of compliance required in CFR section 60.3(b)(5), (c)(4), (c)(10), (d)(3), (e)(2), (e)(4), or (e)(5) is presumed to be in violation until such time as that documentation is provided.
WATER SURFACE ELEVATION: The height, in relation to the NAVD 88 (or other datum, where specified), of floods of various magnitudes and frequencies in the floodplains of coastal or riverine areas. (Ord. 50-09 § 1, 2009)