Certificate of approval or rejection of plans.
R.I. Gen. Laws § 45-24.4-11
in effect45-24.4-11. Certificate of approval or rejection of plans.
The commission shall file with the inspector of buildings or other duly delegated
authority its certificate of approval or rejection of all plans submitted to it for
review. No work shall begin until the certificate has been filed, but, in the case
of rejection, the certificate is binding upon the inspector of buildings or other
duly delegated authority, and no permit shall be issued in that case. The failure
of the commission to act within forty-five (45) days from the date of application
filed with it, unless an extension is mutually agreed upon by the applicant and the
commission or unless the commission makes a finding of fact that circumstances require
additional time for study up to a maximum of ninety (90) days, is deemed to constitute
approval.
P.L. 1981, ch. 332, § 1.
Source: State of Rhode Island General Assembly (rilegislature.gov)URL: https://webserver.rilegislature.gov/Statutes/TITLE45/45-24.4/45-24.4-11.htmFetched: 10/20/2026