Permit required to erect, construct, alter, repair, or demolish structure — Commission quorum and voting.
R.I. Gen. Laws § 45-24.4-10
in effect45-24.4-10. Permit required to erect, construct, alter, repair, or demolish structure — Commission quorum and voting.
(a) Before any structure may be erected, constructed, altered, repaired, or demolished
within a special development district, the person proposing the construction or other
alteration shall file with the commission an application for permission to erect,
construct, alter, repair, or demolish the structure, together with plans and specifications,
all that may be required by regulations adopted by the commission. It is the duty
of the commission to review the application, plans, and specifications, and no building
permit shall be granted until the commission has acted on it. No construction or other
alteration of a structure may be undertaken within a special development district
without a permit.
(b) At all meetings of the commission, a majority of the commissioners is necessary and
sufficient to constitute a quorum for the transaction of business, and the act of
a majority of the commissioners present at any meeting at which there is a quorum
is the act of the commission, except as otherwise provided by law.
P.L. 1981, ch. 332, § 1.