27.28.200 - Pass-through claims.
A. Public Works Contracts will prohibit a Person furnishing labor, materials and/or equipment under contract to the Contractor from submitting a Claim directly to the City.
B. The Public Works Contract will allow the Contractor to pass through a Claim from a Person furnishing labor, materials and/or equipment under contract to the Contractor only if the Contractor certifies in the Notice of Potential Claim that the Contractor reviewed the Claim and reasonably concluded the Claim has merit.
(Ord. 30540.)