QUALITY ASSURANCE AND DAMAGE MITIGATION PLAN.
Austin City Code § 14-11-174
in effect§ 14-11-174 - QUALITY ASSURANCE AND DAMAGE MITIGATION PLAN.
(A) This section applies to an excavation project of 2,500 linear feet or more.
(B) An applicant must prepare and obtain the director's approval of a quality assurance and damage mitigation plan.
(C) A quality assurance and damage mitigation plan must include:
(1) a description of the applicant's procedures for:
(a) inspecting the project;
(b) locating and safeguarding utility facilities adjacent to the excavation site; and
(c) repairing damage to infrastructure and right-of-way.
(2) the names of and contact numbers for employees authorized to make decisions over construction activity at the excavation site who may be contacted at any time during the day or night;
(3) for an excavation within five feet of a utility, a description of the procedures for avoiding damage to the utility;
(4) procedures for responding to damage to an existing utility, including emergency traffic control and the name and contact number of the engineer and contractor who will repair the damage; and
(5) other information related to applicant use of the rights-of-way requested by the director.
(D) A single quality assurance and damage mitigation plan is required for a project. A copy of the plan must be submitted with each excavation project description.
(E) A permit holder shall update the quality assurance and damage mitigation plan not less than once each year for excavation projects that are not completed within one year of the initial permit application date.
Source: Ord. No. 20170817-045, Pt. 2, 8-17-17.
Source: City of Austin, City Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/tx/austin/codes/code_of_ordinances?nodeId=TIT14USSTPUPR_CH14-11USRI-W_ART2USRI-WCOEXFAINTEUS_SPBEXFAINPE_S14-11-174QUASDAMIPLFetched: 10/27/2026