Atlanta City Code § 138-65 Permits for construction or excavation.
Sec. 138-65. - Permits for construction or excavation.
(a) Permit required. Any person desiring to conduct construction activities within the public right-of-way or to have an excavation or opening made within a public street, sidewalk, or right-of-way shall make application for a permit to the commissioner of transportation. The commissioner of transportation shall have the authority to impose such permit terms and conditions necessary to protect the public health and safety, and the permittee shall comply with all terms and conditions imposed by the commissioner of transportation including the right to maintain a register of authorized contractors. Only authorized contractors shall engage in permitted activities in the rights-of-way. Applications for all permits for construction and excavation pursuant to this section shall be reviewed, and if the application is complete and the permittee is in compliance with all requirements of this article, to the extent practicable, the city shall issue a permit within 60 days of receipt of the last application and notice to all parties; provided that all joint application permits for excavation by two or more persons shall be expedited and if in compliance with all requirements of this article shall, if practicable, be approved by the commissioner of within 30 days of receipt of such applications.
(1) Scheduled maintenance permits—There shall be a standing permit for the routine maintenance and repair by the franchisees to existing facilities in the public rights-of-way.
(2) Construction permits:
a. Persons desiring to conduct excavation work in the streets or public rights-of-way for the purpose of sewer installation, water line installation, and water meter installation shall apply for a construction permit. Such permits shall be issued for a fee of $85.00 per permit.
b. Persons desiring to conduct excavation work in the streets or public rights-of-way including, but not limited to, any street cuts boring activity and the placement or removal of conduits, manholes, cable, shall apply for a construction permit. Such permits shall be issued for a fee of $200.00 per permit.
The permit fees set out above shall include one hour of inspection by a department of transportation inspector upon the completion construction activity. In addition, the city may charge an inspection fee of $50.00 per hour. However, where the Georgia Department of Transportation has primary permitting authority over a particular construction activity, the permittee may show a copy of the GDOT permit upon application for a city permit and the city permit fee and inspection fees shall be waived for that permit. With respect to subsection (2)b. immediately above, to the extent that a person pays or remits payment to the city pursuant to section 138-127(h)(1). Such payment shall be in lieu of permit fees and inspection fees.
(3) Emergency repair permit—Persons conducting excavation work in the public rights-of-way pursuant to an emergency shall comply with the provisions set forth in section 138-74.
(b) Permit maintained on site. The permit granted by the commissioner of transportation to conduct construction activities within the public right-of-way, maintenance activities, or to open any street or sidewalk shall be maintained on site and displayed to any official of the department of transportation, police, or other city official upon request. A scheduled maintenance permit shall be exhibited for scheduled maintenance. A construction permit shall be exhibited for excavation activities. Emergency repair permits shall be exhibited for emergency repairs. Failure to exhibit the appropriate permit shall not only be a violation of this article but shall also be cause for revocation of the permit by the commissioner of transportation.
(c) Working without a permit. It shall be unlawful, and a violation of the City Code to perform any regulated activity within the public right-of-way without complying with the permit requirements of the department of transportation in this chapter. Any person deemed guilty of such violation, upon conviction thereof, shall be punished with a fine of $1,000.00. An additional fine of $100.00 per day will be assessed for each day of the violation.
(d) Denial of a permit. The commissioner of transportation shall grant no permit where the applicant has failed to comply with the terms of a prior permit. It shall be within the reasonable discretion of the commissioner of transportation to decline a permit to any person who shall have failed to carry out any prior order or instruction of the commissioner of transportation in connection with the opening of a street or sidewalk at any time. The commissioner of transportation may in the commissioner's discretion decline to grant a permit if the commissioner determines that the permit will not be in the public interest. A person may appeal the denial of a permit to the commissioner of transportation. The responsibility shall be upon the commissioner of transportation to see that no permit is granted to any person to open any street or sidewalk where the results to be accomplished under the permit will unreasonably interfere with the use of the street or sidewalk. Time length for allowing excavations to remain shall be determined by the commissioner of transportation.
(e) Signed petition required. The commissioner of transportation shall not grant any permit to conduct construction activities within the public right-of-way or for an excavation underneath sidewalks or streets for any purpose, unless the petition for that use in each instance is signed by the owner of the proposed facility, who shall enter into an agreement with the city binding the owner and the owner's successor in title. The owner shall agree to indemnify the city against any and all damages to either persons or property caused by the construction or maintenance of the excavation or opening and agree that the commissioner of transportation shall have the right to have said excavations closed and filled at any time the commissioner of transportation determines and the owner shall vacate the area beneath the sidewalk when requested to do so by the city without cost to the city. The work in each instance shall be done under the supervision and to the satisfaction of the commissioner of transportation. Any person violating this section shall be required to close the excavation and remove any obstructions upon the direction of the commissioner of transportation. If such notice is not complied with, such encroachment shall be removed by the commissioner of transportation at the owner's expense.
(f) Supervision of work. All such openings, except as provided in this subsection, shall be made and refilled and permanent improvements removed shall be replaced by or under the supervision of the commissioner of transportation.
(g) Cost of work. The cost of conducting construction activities within the public right-of-way or making and refilling any opening and of replacing any permanent improvement removed shall be paid by the person at whose request such opening is made. If work is performed by the city on behalf of or at the request of an applicant, charges therefore shall be in such amounts as may be fixed by the commissioner of transportation, subject to the approval of the council. The commissioner of transportation shall likewise in each case estimate the cost of replacing permanent improvements and shall have authority to replace or require the replacement of all of a sidewalk or street when it is necessary to put the sidewalk in as good condition using materials of equal or better quality as before the opening. All such cost, whether computed from a schedule fixed by the commissioner of transportation or embodied in an estimate made under this subsection by the commissioner of transportation, shall be paid before the work is done by the city or the permit is granted.
(h) Conditions of maintaining a permit.
(1) The commissioner of transportation is authorized to establish and publish a list of conditions and requirements for all construction, repair, maintenance, and other activities within the public right-of-way including, among other things, the power to establish reasonable fees and fines not inconsistent with this chapter. Said conditions shall contain, but shall not be limited to, requirements pertaining to:
a. Notice of proposed construction activities and projected impediment to the abutting commercial and residential land five business days prior to construction activity. Notice shall be visibly displayed in a conspicuous manner on the door of the residence or commercial establishment;
b. Traffic protection;
c. Emergencies;
d. Clear identification of all construction and maintenance sites, vehicles, metal plates and other obstacles with the name and phone number of the utility owner and the person performing the work;
e. Construction plans to show length of cut, construction activity to install the equipment, size, type and location of utilities in the rights-of-way and technical specifications for street rehabilitation;
f. Placement of warning signs identifying construction and excavation-site;
g. Replacement of decorative sidewalk style and material;
h. Coordination of excavation and paving activities between and among any persons;
i. Placement and removal of paint markings for utility locations;
j. Bonds, insurance and other financial protection for the city;
k. As-built plans. As-built plans and drawings in a form specified by the department of transportation. Plans submitted to the department of transportation for permit approval, which have been updated and certified to reflect actual construction and field changes, shall satisfy this section. Permittee shall not be required to supply privileged information. Any such plans submitted to the city, to the extent permitted by applicable law, shall remain proprietary. No person shall artificially under-estimate the size of their proposed system to evade the purpose of this article.
l. Permittee shall provide to the department of transportation a list identifying all subcontractors used by a permittee on a construction or excavation project. List shall include the name and telephone number of the subcontractor, location and the anticipated duration of the project; and
m. Any other requirements, limitations, or conditions that may be necessary and proper.
(2) Restoration of the right-of-way. Upon the determination by the department of transportation that all construction and excavation activity in the right-of-way, has ceased, within 14 business days of such determination, all persons shall begin to restore the right-of-way to its pre-construction condition. The restoration of the right-of-way shall include; the repaving of all streets and sidewalks, removal of temporary utility markings, and replacement of all disturbed pavement markings, the removal of all barricades, obstructions, surplus excavation material and the restoration of the appropriate vegetation. However, trees and shrubs should be planted during the appropriate season. All restoration shall be completed within 21 days after the end of construction activity. Failure to comply with this section will subject all persons to the maximum penalties as set forth in section 138-4 of this chapter.
(i) Safety barriers. It shall be the duty of all persons doing any kind of non-emergency work in the streets of the city, such as paving, laying sewers, sidewalks and curbing, moving buildings or any other work that in any way obstructs free passage thereon to notify the commissioner of transportation at least 96 hours before the work is commenced and on its completion. It shall be the duty of the commissioner of transportation to see that this subsection is enforced, both as to the erection of barriers or enclosures and as to travel on the street by vehicles or otherwise during the time prohibited. It shall also be the duty of the commissioner of transportation to notify the fire chief and police chief, Grady Memorial Hospital, the Metropolitan Atlanta Rapid Transit Authority and persons named by the mayor or the mayor's designee of the date and time the street will be closed.
(j) Performance bond. Persons performing construction or excavation work in the right-of-way shall maintain a performance and completion bond in the amount of $500,000.00 or in an amount determined by the city's risk manager to be adequate to either complete the proposed work impacting the public right-of-way in its entirety or to restore the public right-of-way to its condition prior to the commencement of the work if the person fails to complete the work to the satisfaction of the commissioner of transportation.
(k) Insurance. The city's risk manager shall require the person conducting construction activities within the public right-of-way to obtain a policy of public liability and property damage insurance naming the city as an additional insured and affording coverage for personal injury, including death in an amount not less than $3,000,000.00, or such amounts established by the city's risk manager, to protect the city from liability claims arising out of the permitted construction activities. These insurance requirements may be met by evidence of self-insurance acceptable to the city.
(l) Cash deposit and irrevocable letter of credit. The permittee conducting construction activities within the public right-of-way shall maintain either an irrevocable letter of credit from a qualified financial institution or a cash deposit securing the compliance of the terms of this chapter and the faithful performance of the obligations of the party conducting construction activities within the public right-of-way. The permittee is not required to obtain an irrevocable letter of credit or cash deposit for each individual construction activity for the year beginning January 1. The irrevocable letter of credit or cash deposit shall cover all construction activities conducted by the permittee from January to January of the next year.
(1) Amount. The irrevocable letter of credit or cash deposit shall be in the sum of $10,000.00 for work up to 500 feet in the public right-of-way. A $25,000.00 irrevocable letter of credit or cash deposit shall be required for work performed in the public right-of-way in excess of 500 feet. The deposit shall be placed in an interest bearing account.
(2) Demand on the irrevocable letter of credit or from cash deposit. The commissioner of transportation may demand payment from the institution that issued the letter of credit for a violating party or make deductions from the cash deposit, as applicable to offset the costs of, among other things, the repair, excavations or work performed by the department of transportation, or to pay any assessed penalties or costs associated with violations of this chapter. Where practicable, the city shall provide the permittee with ten days advance written notice of a deduction from the deposit.
(3) Release of the letter of credit or cash deposit. The letter of credit or cash deposit shall be maintained for a period of one year after the satisfactory completion of work performed in the public right-of-way to secure the obligations in the permit and this ordinance. Upon expiration of one year of the satisfactory completion of the latest activity conducted in the public right-of-way, the department of transportation shall either release the letter of credit or cash deposit securing satisfactory completion of the work performed in the public right-of-way. If the department determines that the work is unsatisfactory, the department of transportation shall provide written notice of the reasons why the work is unsatisfactory to the person conducting the construction activities. If no notice of unsatisfactory work is provided by the department of transportation within 30 days after a request for release pursuant to this section, any letter of credit or cash deposit plus accrued interest will be refunded.
(4) Notwithstanding the foregoing, the requirement for an irrevocable letter of credit or cash deposit may be waived, or the amount may be decreased at the discretion of the city's risk manager.
(m) Notification to abutting property owners or occupants. The commissioner of transportation shall require the person conducting activities pursuant to the permit and construction activities within the public right-of-way to provide each abutting property owner or occupant with reasonable and timely notification of any impending construction work that would unreasonably interfere with either egress or ingress onto said owner's property.
(n) Indemnity of the city. The commissioner of transportation shall require the person conducting activities pursuant to the permit and construction activities within the public right-of-way to indemnify and hold harmless the city, its officers, agents and employees, from any and all claims or litigation arising from any construction activities which interfere with the ability of the abutting property owner to conduct his business and/or personal activities in a manner to which he is accustomed.
(o) Consequential damages. The commissioner of transportation shall require the person conducting activities pursuant to the permit and construction activities within the public right-of-way to indemnify and hold harmless the city, its officers, agents and employees, from any and all claims or litigation arising from any consequential damages arising from any construction activities within the public right-of-way, including but not limited to vehicular damage caused by such disruption to the right-of-way.
(p) Guarding of temporary excavations. All persons making an excavation in any street, sidewalk or public place for any purpose shall erect around the excavation a fence or barrier adequate to protect the public from the excavation. When the excavation is made across the sidewalk or at a place used by pedestrians, a bridge shall be erected over the excavation sufficient for the safe passage of the public. All excavations shall be properly lighted at night as determined by the commissioner of transportation. The guarding and protection of excavations shall be in accordance with state law and with specifications promulgated by the commissioner of transportation and on file in the office of the commissioner of transportation. Appropriate signage shall be erected by all persons making an excavation in the street to provide notice of the excavation to the public.
(q) Reservation of rights. The city reserves the right, upon the review of its franchise application, to waive, modify or amend the various bonding, letter of credit, cash deposits and insurance requirements as set forth in section 138-65, taking into account, among other factors, the financial stability of the franchisee or revocable licensee and the past performance of the franchisee or revocable licensee in the city's right-of-way.