§ 138-75 — Fees charged for permits which allow blocking or closing sidewalks or streets; etc

Atlanta City Code (Code of Ordinances, Part II) (Supp. No. 108, Update 1: codified through Ordinance No. 2026-37 (26-O-1511), enacted September 30, 2026) · Atlanta City Code § 138-75

Corpus is an independent public-information project, not the official City of Atlanta website. Stable reference: corpuslaw.us/code/e469df1d-3f50-4cef-bae6-66a6159deb8a

Sec. 138-75. - Fees charged for permits which allow blocking or closing sidewalks or streets; etc.

(a) The applicant for any permit issued by the department of transportation for closing, occupying, blocking or otherwise using sidewalks or streets for building construction, building repairs, material or equipment storage, movement of oversize vehicles or loads and other special purposes shall pay to the city an application fee of $35.00 and, upon receipt of such permit, pay to the city a permit fee as provided in this section. (b) There shall be a $35.00 fixed fee for all permits issued as provided in this section, unless otherwise provided herein. (c) A variable permit cost for use of up to 100 linear feet of sidewalk and any portion of the adjacent curb lane shall be $15.00 per calendar day for the duration of the permit. (d) A variable permit cost for use of 101 to 200 linear feet of a sidewalk and any portion of the adjacent curb lane shall be $30.00 per calendar day for the duration of the permit. (e) A variable permit cost for use of 201 to 300 linear feet of a sidewalk and any portion of the adjacent curb lane shall be $45.00 per calendar day for the duration of the permit. (f) A variable permit cost for use of over 300 linear feet of a sidewalk and any portion of the adjacent curb lane shall be $60.00 per calendar day for the duration of the permit. (g) The variable permit cost for use of sidewalk space only shall be 40 percent of the variable permit cost as determined for paragraphs (c), (d), (e) and (f) of this section, based on the linear feet of sidewalk used. (h) The variable permit cost for use of multiple lanes or full street closure shall be the cost of a single lane permit as established in paragraphs (c), (d), (e) and (f), multiplied by the number of marked traffic lanes encroached upon by the permitted use. Where no lane markings are used, a lane width of ten feet shall be assumed for determining the permit cost. (i) The variable permit cost for trenching or excavating within rights-of-way shall be $25.00 per calendar day per lane for the duration of the permit. (j) Each truck, trailer, crane, tractor, structure or similar device parked or placed within public rights-of-way contrary to established parking regulation and not within an area permitted, as provided by other portions of this section, shall be required to have from the department of transportation a permit for such storage or parking. The cost of such permit shall be $20.00 per day; however, the fixed fee of $20.00 shall not be applied. (k) A single trip permit for moving vehicles over city streets which exceed the legal length, width, height, or weight shall be $20.00 for exceeding one of the limitations and $30.00 for exceeding more than one of the limitation. If the department of transportation determines that such vehicles or load, because of its size, must be moved at night or will require a special police escort, the variable permit cost shall be $200.00. Permit charges required in this subsection may be waived if such oversized vehicle or load thereon is being used as part of or in preparation for a parade, festival or other such event. (l) An annual multiple trip permit cost for moving vehicles which exceed the legal length, width, height or weight shall be $200.00. (m) Minor routine maintenance of buildings, walls, signs, fences, trees or similar facilities which requires use of a sidewalk, shall require a permit and permit fee. (n) The commissioner of the department of transportation shall make a determination on any question concerning conditions which require a permit and shall approve waivers of permit fees as provided for herein. (o) The fee for a haul route permit shall be $80.00.

(Ord. No. 2008-43(08-O-0881), § 1, 6-24-08; Ord. No. 2015-32(15-O-1131), § 2, 6-24-15; Ord. No. 2020-32(20-O-1379), § 35, 6-23-20)