§ 25-77 — Permit required for use of right-of-way

Code of Ordinances, City of Denton, Texas (Supp. No. 37, Update 1: codified through Ordinance No. 26-296 adopted March 24, 2026) · Denton City Code § 25-77

Corpus is an independent public-information project, not the official City of Denton website. Stable reference: corpuslaw.us/code/747a683d-c1a4-4292-aa64-81bacda7fd4d

Sec. 25-77. - Permit required for use of right-of-way.

(a) Permit required. Any right-of-way user seeking to place facilities on, in or over a right-of-way or to engage in construction, excavation, and occupy a work area within or upon any right-of-way shall first file an application for a right-of-way permit with the city and shall abide by the terms and provisions of the right-of-way permit and this division pertaining to the use of the rights-of-way. (b) Exemptions. (1) No application, permit or fee is required of a right-of-way user for: a. Routine maintenance of existing facilities that does not require excavation or closing of sidewalks or vehicular lanes in streets of a right-of-way; b. A network provider replacing or upgrading a network node or pole with a node or pole that is substantially similar in size or smaller and that does not require excavation or closing of sidewalks or vehicular lanes in a right-of-way; 1. Substantially similar shall mean the replacement or upgrade does not include replacement of an existing pole; and 2. The determination of whether a replacement or upgrade is substantially similar may include the location, size, material, quantity, capacity, or other similar characteristic of the existing facilities as approved by the city engineer. (c) Permits generally. (1) Permits will be issued in the name of the right-of-way user that will own the facilities. Permits for public infrastructure will be issued in the name of the public infrastructure contractor. (2) Any right-of-way user with a current, unexpired consent, franchise, agreement, or other authorization from the city (grant) to use the rights-of-way that is in effect at the time this division takes effect shall continue to operate under and comply with that grant, unless prohibited by law, until the grant expires or until it is terminated by mutual agreement of the city and the right-of-way user or as otherwise provided for by law. (3) Construction, excavation, or work area. No right-of-way user shall perform construction, excavation, or occupy a work area larger or at a location different, or for a longer period than that specified in the permit or permit application. If, after construction, excavation, or occupying the work area is commenced under an approved permit, it becomes necessary to perform construction, excavation, or occupy a work area larger or different area than originally requested under the application or for a longer period of time, the right-of-way user shall notify the city engineer immediately and, within twenty-four (24) hours, shall file a supplementary application for the additional construction, excavation, or occupation of a work area. (4) Permit transferability or assignability. The right-of-way user may subcontract the work to be performed under a permit if the right-of-way user is responsible for the performance of the work under the permit and all insurance and financial security as required in this division. Permits are transferable and assignable upon written notice to the city engineer that the transferee or assignee has posted all required security pursuant to this division. Any transferee or assignee shall be bound by all requirements of the permit and this division. (5) The construction of public infrastructure, excluding franchise utility infrastructure, in new developments is the responsibility of the developer of the land. Ownership of that infrastructure remains with the developer of the land until accepted by the city. (6) Any franchise utility, utility, or public infrastructure contractor performing work on infrastructure that is within a right-of-way, but prior to infrastructure acceptance by the city, shall obtain a permit from the city and permission from the owner of all the infrastructure in the right-of-way. The agency or public infrastructure contractor shall be financially responsible to the owner of the infrastructure to carry out all remedial work necessary to receive acceptance by the city of that infrastructure. This financial obligation shall apply only to the work in the right-of-way done by the franchise utility, utility, or public infrastructure contractor. The city will not accept for dedication public infrastructure if the work performed on that infrastructure is not in accordance with applicable city construction standards. (7) Any right-of-way user found to be conducting any excavation activity within the right-of-way without having first obtained the required permit(s) shall immediately cease all activity (exclusive of actions required to stabilize the area) and be required to obtain a permit before work may be restarted. (8) The city may institute all appropriate legal action to prohibit any right-of-way user from knowingly using the rights-of-way unless the agency or public infrastructure contractor has complied with the terms of this division.

(Ord. No. 2019-2439, § I, 11-19-19)