Sec. 14-61. - Conditions for the construction, disinfection, protection and testing of a public water well.
The construction, disinfection, protection, and testing of a well to be used as a water supply source must meet the rules and regulations of the Texas Commission on Environmental Quality (TCEQ) under the Texas Administrative Code, Title 30, chapter 290, subchapter D, as amended, and the following conditions. In case of conflict between the TCEQ rules and regulations and the conditions set forth in this section, the more restrictive shall apply.
(1) Drilling records and well completion data shall be maintained accurately and copies made available to the owner, as well as the city engineer or other city departments. Before placing the well into service, the city engineer shall be furnished a copy of the well completion data, which includes the following items:
a. The driller's log (geological log and material setting report);
b. A cementing certificate;
c. The results of a 36-hour pump test;
d. The results of the microbiological and chemical analyses required by subsections (7) and (12) of this section; and
e. An original or legible copy of a United States Geological Survey 7.5 Minute Topographic Quadrangle showing the accurate well location to the city engineer.
All the documents listed in this section must be approved by the city engineer before final approval is granted.
(2) The casing material used in the construction of wells shall be new carbon steel, high-strength, low-alloy steel, stainless steel or plastic and the material shall conform to the American Waterworks Association Standards. The casing shall extend a minimum of 18 inches above the elevation of the finished floor of the pump room or natural ground surface and a minimum of one inch above the sealing block or pump motor foundation block, when provided. The casing shall extend at least to the depth of the shallowest water formation to be developed and deeper, if necessary, in order to eliminate all undesirable water-bearing strata. Well construction materials containing more than eight percent lead are prohibited.
(3) The space between the casing and drill hole shall be sealed by using sufficient cement under pressure to provide for completely filling and sealing of the annular space between the casing and the drill hole. The well casing shall be cemented in this manner from the top of the shallowest formation to be developed to the earth's surface. The driller shall utilize a pressure cementation method in accordance with the American Waterworks Association Standard for Water Wells (A100-97), appendix C; section C.3 (positive displacement exterior method); section C.4 (interior method without plug); section C.5 (positive placement, interior method, drillable plug); section C.6 (placement through float attached to bottom of casing). Cementation methods other than those listed in this subsection may be used on a site-specific basis with the prior written approval of the city engineer. A cement bonding log, as well as any other documentation deemed necessary, may be required by the city engineer to assure complete sealing of the annular space.
(4) In all cases, a concrete sealing block extending at least three feet from the well casing in all directions, with a minimum thickness of six inches, and sloped to drain away at not less than one-fourth or three inches per foot, shall be provided around the well head.
(5) Well heads and pump bases shall be sealed by gaskets or sealing compounds and properly vented to prevent the possibility of contaminating the well water. A well casing vent shall be provided with an opening that is covered with 16-mesh or finer corrosion-resistant screen, and facing downward, elevated and located so as to minimize the drawing of contaminants into the well. Wellheads and well vents shall be at least two feet above the highest known watermark or 100-year flood elevation, if available, or adequately protected from possible flood damage by levees.
(6) Safeguards shall be taken to prevent possible contamination of the water or damage by trespassers following the completion of the well and prior to installation of permanent pumping equipment.
(7) Upon well completion, or after an existing well has been reworked, the well shall be disinfected in accordance with current American Waterworks Association Standards for well disinfection except that the disinfectant shall remain in the well for at least six hours.
a. Before placing the well in service, the water containing the disinfectant shall be flushed from the well, and the samples of water shall be collected and submitted for microbiological analysis until three successive daily raw water samples are free of coliform organisms. The analysis of these samples must be conducted by a laboratory approved by the state department of health.
b. Appropriate facilities for treatment of the water shall be provided where a satisfactory microbiological record cannot be established after repeated disinfection. The extent of water treatment required will be determined on the basis of geological data, well construction features, nearby sources of contamination and, if necessary, on the basis of quantitative microbiological analyses.
(8) A suitable sampling cock shall be provided on the discharge pipe of each well pump prior to any treatment.
(9) If a well blowoff line is provided, its discharge shall terminate in a downward direction and at a point which will not be submerged by floodwaters.
(10) The well site shall be fine graded so that the site is free from depressions, reverse grades, or areas too rough for proper ground maintenance so as to ensure that surface water will drain away from the well. In all cases, arrangements shall be made to convey well pump drainage, packing gland leakage, and floor drainage away from the wellhead. Suitable drain pipes located at the outer edge of the concrete floor shall be provided to collect this water and prevent its ponding or collecting around the wellhead. This wastewater shall be disposed of in a manner that will not cause any mosquito breeding or stagnation. Drains shall not be directly connected to storm or sanitary sewers.
(11) When a gravel packed well is constructed, all gravel shall be of selected and graded quality and shall be thoroughly disinfected with a 50 mg/l chlorine solution as it is added to the well cavity.
(12) A complete physical and chemical analysis of the water produced from a new well shall be made after 36 hours of continuous pumping at the design withdrawal rate. Shorter pump test periods can be accepted for large capacity wells producing from areas of known groundwater production and quality so as to prevent wasting of water. Samples must be submitted to a certified laboratory for chemical analyses. Tentative approval may be given on the basis of tests performed by in-plant or private laboratories but final acceptance by the city engineer shall be on the basis of results from the certified laboratory. Appropriate treatment shall be provided if the analyses reveal that the water from the well fails to meet the water quality criteria as prescribed by the drinking water standards. These criteria include turbidity, color and threshold odor limitations, and excessive hydrogen sulfide, carbon dioxide or other constituents or mineral which make the water undesirable or unsuited for domestic use. Additional chemical and microbiological tests may be required after the city engineer conducts a vulnerability assessment of the well.
(13) Below ground level pump rooms and pump pits will not be allowed in connection with water supply installations.
(14) Flow measuring devices shall be provided for each well to measure production yields and provide for the accumulation of water production data. These devices shall be located to facilitate daily readings.
(15) All completed well units shall be protected by intruder-resistant fences, the gates of which are provided with locks or shall be enclosed in locked, ventilated well houses to exclude possible contamination or damage to the facilities by trespassers. The gates or wellhouses shall be locked during periods of darkness and when the plant is unattended.
(16) An all-weather access road shall be provided to each well site.
(17) If an air release device is provided on the discharge piping, it shall be installed in such a manner as to preclude the possibility of submergence or possible entrance of contaminants. In this respect, all openings to the atmosphere shall be covered with 16-mesh or finer, corrosion-resistant screening material or an acceptable equivalent.
(18) Upon completion of the water well, the following reports shall be required:
a. The water well driller shall submit a copy of the drilling log, the size of the pump, and the pump setting.
b. The casing contractor shall submit a report detailing the size, depth, material used, and wall thickness of the casing.
c. The cementing contractor shall submit a report of the specification of the cementing.
(Code 1995, § 6.307; Ord. No. G-03-11-25-11E1, 11-25-2003)