Additional construction defects; additional notice of claim required.
AS 09.45.894
in effect09.45.894. Additional construction defects; additional notice of claim required.
A court action for a defect that is discovered after a claimant has provided a construction professional with a notice of claim required in AS 09.45.881 — 09.45.899 may not be commenced until the claimant has complied with the provisions of AS 09.45.881 — 09.45.899.
Source: Alaska State Legislature (akleg.gov)URL: https://www.akleg.gov/basis/statutes.asp?media=print&secStart=09.45.894&secEnd=09.45.894#09.45.894Fetched: 10/20/2026