§ 9-7-5 — Building Height

Boulder Revised Code 1981 (Supplement167; ordinances effective through July30,2026; five publisher-pending ordinances held); partial · Boulder Revised Code 1981 § 9-7-5

Corpus is an independent public-information project, not the official City of Boulder website. Stable reference: corpuslaw.us/code/8475cf91-1359-45da-9b98-9908d0e338e2

9-7-5. - Building Height.

(a) Permitted Height: The height permitted without review within the City is set forth in Section 9-7-1, "Schedule of Form and Bulk Standards," B.R.C. 1981, except as provided in Paragraph (b)(2) of this section and except under a form-based code review. Buildings greater than the permitted height may be approved under Section 9-2-14, "Site Review," B.R.C. 1981. Buildings developed under a form-based code review are subject to the minimum and maximum height standards established in Chapter 9-14, "Form-Based Code," B.R.C. 1981, and shall not exceed the height limit of Charter Section 84, "Height limit." (b) Measurement of Height: Height shall be measured as the vertical distance from the lowest point within twenty-five horizontal feet of the tallest side of the structure to the uppermost point of the roof or structure. The lowest point shall be calculated using the natural grade. The tallest side shall be that side whose lowest exposed exterior point is lower in elevation than the lowest exposed exterior point of any other side of the building (see Figure 7-4 Measurement of Height). (1) Modifications to Natural Grade: If there is evidence that a modification to the natural grade has occurred since the adoption of Charter section 84, "Height limit." B.R.C. 1981, on November 2, 1971, the city manager can consider the best available information to determine the natural grade. This may include, without limitation, interpolating what the existing grade may have been using the grade along property lines, topographic information on file with the City, or other information that may be presented to the city manager.

![Figure 7-4: Measurement of Height](https://figures.74-208-44-221.nip.io/boulder/496676/6c2f2724ec5f0edce97578d63a3af586d106d65305c7380b5f8b0567651dfd94.png)

Figure 7-4: Measurement of Height (2) Slopes Greater Than Twenty Degrees: On a slope measured within the building envelope created by the required setbacks from property lines that is greater than twenty degrees (36.4 percent slope), the building height may not exceed twenty-five feet measured perpendicular from the natural grade below. (See Figure 7-5 of this section.) However, under no circumstances shall a structure exceed fifty-five feet as measured under charter section 84 except as provided for poles in Section 9-2-14, "Site Review," B.R.C. 1981. The slope percentage shall be calculated by measuring the difference between the high point and the low point within the building envelope and dividing it by the distance between the high and low points.

![Figure 7-5: Building Height on a Slope Greater than Twenty Degrees](https://figures.74-208-44-221.nip.io/boulder/496676/dbfad6245770950b0d794c2cf5e2fed42e33696fb25a95e600c881e15e10eb99.png)

Figure 7-5: Building Height on a Slope Greater than Twenty Degrees (c) Nonconformity to Fifty-Five-Foot Limit: No addition to that portion of the building exceeding the current fifty-five foot height limitation is allowed for structures erected at a height conforming to the height limitations applicable at the time of their erection which are now nonconforming as to height. Appurtenances which meet the requirements of Section 9-7-7, "Building Height, Appurtenances," B.R.C. 1981, may exceed the fifty-five-foot height limit. (d) Nonconformity to Permitted Height: For existing buildings that exceed the height permitted in Section 9-7-1, "Schedule of Form and Bulk Standards," or Section 9-7-6, "Building Height, Conditional," B.R.C. 1981, the following changes require approval under Section 9-2-14, "Site Review," B.R.C. 1981: (1) Increasing the building's highest point as established by Subsection 9-7-5(b), "Measurement of Height," B.R.C. 1981; (2) Adding building elements or massing above the permitted or conditional height unless permitted by Section 9-7-7, "Building Height, Appurtenances," B.R.C. 1981; or (3) Adding floor area of buildings above the permitted or conditional height. (e) Height Calculations for Attached Buildings: (1) The following shall be considered separate buildings for the purposes of calculating building height: (A) Buildings that are connected only below grade (see Figure 7-6 of this section). (B) Separate abutting buildings that may have an internal connection (see Figure 7-7 of this section). (C) Buildings built to the common property line that may have an internal connection (see Figure 7-7 of this section). (D) Buildings attached by an at-grade open or enclosed connection not more than fifteen feet high and twelve feet deep (see Figure 7-8 of this section). (2) Separate buildings in compliance with Paragraph (e)(1) of this section, and which exceed the maximum permitted height allowed by Section 9-7-1, "Schedule of Form and Bulk Standards," B.R.C. 1981, may be considered by the planning board pursuant to Section 9-2-14, "Site Review," B.R.C. 1981.

![Figure 7-6: Below Grade Connection](https://figures.74-208-44-221.nip.io/boulder/496676/ffc15426eb217aed75f2b50daeaafc12c196c5b8edf96970f3100a93bda4ada8.png)

Figure 7-6: Below Grade Connection

![Figure 7-7: Internal Connection](https://figures.74-208-44-221.nip.io/boulder/496676/d71dcebf65e4f289cc212fb7e22358e6d4e1e61f15b1a743a10646992bc7fa83.png)

Figure 7-7: Internal Connection

![Figure 7-8: At-Grade Open or Enclosed Connection](https://figures.74-208-44-221.nip.io/boulder/496676/a1eb76dee0407666f7b90e15539b683f65aa7492df2f1be9c73dcf7d6b95e596.png)

Figure 7-8: At-Grade Open or Enclosed Connection Ordinance Nos. 7535 (2007); 7699 (2009); 8409 (2020); 8620 (2024); 8622 (2024); 8669 (2025); 8697 (2025)