18.07.050 - Required inspections.
A. Building. The Building Official, upon notification as specified in Section 18.07.030, shall make the inspections set forth in subsection, if applicable.
1. Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. For concrete foundations, any required forms shall be in place prior to inspection. Materials for the foundation shall be on the job, except where concrete is ready mixed in accordance with ASTM C94, the concrete need not be on the job.
2. Concrete slab and under-floor inspection. Concrete slab and under-floor inspections shall be made after all in-slab or under-floor reinforcing steel and building service equipment, conduit, piping accessories and other ancillary equipment items are in place, but before any concrete is placed or floor sheathing installed, including the subfloor.
3. Methane gas mitigation system inspection. Vent collector and sub-slab pipe routing shall be inspected prior to placement of the methane barrier. The methane barrier shall be inspected after installation is complete and a certificate of installation is provided by the installer. Exterior wall vent risers shall be inspected prior to concealment within the wall.
4. Lowest floor elevation. In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required in Chapter 16 and Appendix G of the California Building Code adopted in Chapter 18.40 or Chapter 3 of the California Residential Code adopted in Chapter 18.41, as applicable, shall be submitted to the Building Official.
5. Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fire blocking and bracing are in place and all pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved.
6. Types IV-A, IV-B and IV-C construction protection inspection. In buildings of Types IV-A, IV-B and IV-C construction, where connection fire-resistance ratings are provided by wood cover calculated to meet the requirements of Section 2304.10.1 of the California Building Code adopted in Chapter 18.40, inspection of the wood cover shall be made after the cover is installed, but before any other coverings or finishes are installed.
7. Lath, gypsum board and gypsum panel product inspection. Lath, gypsum board and gypsum panel product inspections shall be made after lathing, gypsum board and gypsum panel products, interior and exterior, are in place, but before any plastering is applied or gypsum board and gypsum panel product joints and fasteners are taped and finished.
8. Fire- and smoke-resistant penetrations. Protection of joints and penetrations in fire resistance-rated assemblies, smoke barriers and smoke partitions shall not be concealed from view until inspected and approved.
9. Energy efficiency inspections. Inspections shall be made to determine compliance with the California Energy Code adopted in Chapter 18.46 and shall include, but not be limited to, inspection for: envelope insulation R- and U-values, fenestration U-value, duct system R-value, and HVAC and water-heating equipment efficiency.
10. Reinforced concrete. When forms and reinforcing steel are in place ready for concrete.
11. Reinforced masonry. In grouted masonry when vertical reinforcing steel is in place and other reinforcing steel distributed and ready for placing, but before any units are laid up.
12. Structural steel. When structural steel members are in place and required connections are complete, but before concealing any members or connection.
13. Other inspections. In addition to the inspections specified in this subsection, the Building Official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this title and other laws that are enforced by the Building Official.
14. Special inspections. When special inspections are required by Chapter 17 of the California Building Code adopted in Chapter 18.40.
15. Final inspection. Final inspection shall be made after all work required by the permit is completed and prior to occupancy. If located in a flood hazard area, flood hazard documentation required in Chapter 16 and Appendix G of the California Building Code adopted in Chapter 18.40 or Chapter 3 of the California Residential Code adopted in Chapter 18.41, as applicable, shall be submitted to the Building Official prior to final inspection.
B. Electrical. The Building Official, upon notification as specified in Section 18.07.030, shall make the inspection and approval of electrical installation as set forth in subsection, if applicable.
1. Inspection required. All electric wiring or installation in or on any building or structure of any nature, or tent, or premises, except as otherwise exempted in this title, for which a permit is required must be inspected and approved by the Building Official before being energized or used.
2. Prohibited use, operation or maintenance. No person shall use, operate or maintain, or cause or permit to be used, operated or maintained, any such electric wiring until such inspection and approval. No serving agency shall furnish or supply or cause or permit to be furnished or supplied, electric energy to any such electric wiring until such inspection and approval.
3. Prohibited concealment or enclosure of electrical wiring. No person shall conceal, enclose or cover, or cause or permit to be concealed, enclosed or covered, any portion of any electric wiring in any manner that will interfere with or prevent the inspection and approval thereof.
4. Prohibited obstruction to inspection. Any portion of any floor, ceiling, wall, partitions, roof, finish or other obstruction whatsoever which renders impracticable the making of a complete and thorough inspection of electric wiring shall be removed upon notice to do so, and shall be kept removed until such electric wiring has been inspected and approved.
5. Removal of foreign material in junction boxes and wire enclosures. Before a final inspection of any electric wiring, all plaster, concrete or other foreign material shall be thoroughly removed from every junction box and wiring enclosure, and not less than six (6) inches of jointless conductors shall extend out of each lighting outlet box for future connection thereto, except when conductors are intended to loop through the lamp holder.
6. Fixture connection. Fixtures or appliances shall not be connected to electric wiring until the rough wiring has been inspected and approved by the Building Official.
7. Free of defects. All such wiring shall be free from grounds, shorts, or other defects, before approval thereof.
8. Exemption. The provisions of this subsection shall not apply to finished work or to conductors inserted in conduit or other wiring enclosures. Nothing contained in this subsection shall be construed to prohibit the temporary use of electric energy when and as specifically provided in this title. Nothing contained in this subsection shall be construed to prohibit the inspection of any electric wiring even though no permit is required therefore.
9. Final inspection. Final inspection shall be made after all work required by the permit is completed and found to be in compliance with the provisions of this title, the Building Official shall leave a notice at the service switch or other suitable place so stating, and shall issue a certificate of inspection or approval tag when requested, or service permit, authorizing the connection to the electrical service and the energizing of the installation.
C. Plumbing. The Building Official, upon notification as specified in Section 18.07.030, shall make the inspection and approval of plumbing installation as set forth in subsection, if applicable.
1. Inspection required. All plumbing installation in or on any building or structure of any nature, or tent, or premises, except as otherwise exempted in this title, for which a permit is required must be inspected and approved by the Building Official.
2. Gas supply or meter. No person shall furnish or supply gas to any gas piping or install any meter therefore until all plumbing as regulated by this title has been installed and approved by the Building Official and a certificate of final inspection has been issued.
EXCEPTION: Notwithstanding anything in this chapter to the contrary, gas service may be supplied to gas piping for construction purposes only and a gas meter may be installed therefore under the following conditions:
a. The owner of the building or a duly authorized representative shall apply to the Building Official for such gas service and shall pay a fee as set forth in the schedule of fees and charges established by City Council resolution in connection with such application to the Building Official. The application for such gas service shall not be granted until all gas piping in the structure affected has been tested and approved pursuant to the California Plumbing Code adopted in Chapter 18.43.
b. Such service shall not be permitted for an initial period in excess of thirty (30) days. The Building Official may impose such reasonable requirements and regulations in connection therewith as he or she may deem necessary. For good cause, the Building Official may extend such period of time in his or her reasonable discretion.
3. Prohibited concealment of installation. No person shall fail, neglect or refuse to leave and keep any plumbing, as regulated by this title, open, uncovered and convenient for inspection until such plumbing has been inspected and approved by the Building Official, and any obstruction whatsoever, which interfered with a complete and thorough inspection of any plumbing, shall be removed upon notice so to do, and shall be left and kept removed until such plumbing has been inspected and approved.
4. Location of installation. Piping, fixtures or equipment shall not be located in such manner as to interfere with the normal operation of windows, doors or other required means of access.
5. Services to be capped when building removed. Where a building is demolished or removed from its site, the building sewer, water and gas service shall be properly capped to the satisfaction of the Building Official.
6. Final inspection. Final inspection shall be made after all work required by the permit is completed and found to be in compliance with the provisions of this title, the Building Official shall leave a notice at a suitable place so stating, and when requested shall authorize the furnishing or supplying of gas to any gas piping or the installation of any meter.
D. Mechanical. The Building Official, upon notification as specified in Section 18.07.030, shall make the inspection and approval of mechanical installation as set forth in subsection, if applicable.
1. Inspection required. All mechanical installation in or on any building or structure of any nature, or tent, or premises, except as otherwise exempted in this title, for which a permit is required must be inspected and approved by the Building Official.
2. Prohibited concealment of installation. That portion of any equipment intended to be concealed by any permanent portion of the building shall not be concealed until inspected and approved by the Building Official.
3. Connection to fuel or power supply. Equipment regulated by this title shall not be connected to the fuel or power supply until authorized by the Building Official.
4. Failure to comply. A final inspection approval may, upon notice, be revoked by the Building Official if he or she finds that the heating, ventilating, cooling, or refrigeration equipment fails in any respect to comply with the requirements of this title, or that the installation is unsafe, dangerous, or a hazard to life or property.
5. Final inspection. Final inspection shall be made after all work required by the permit is completed and found to be in compliance with the provisions of this title, the Building Official shall leave a notice at a suitable place so stating, and shall authorize the connection to the fuel or power supply for the installation.
E. Grading. The Building Official, upon notification as specified in Section 18.07.030, shall make the inspection and approval of grading, excavations or fills operation as set forth in subsection, if applicable:
1. Initial meeting/inspection. When the permit holder or their duly authorized agent is ready to begin work, but before any grading operation or brushing is started, a meeting shall be held at the project site with the contractor and the inspectors to discuss the approved construction documents, soil reports and the sequence of the grading operations.
2. Toe inspection. After the natural ground is exposed and prepared to receive fill, but before any fill is placed.
3. Excavation inspection. After the excavation is started, but before the vertical depth of the excavation exceeds ten (10) feet.
4. Fill inspection. After the fill placement is started, but before the vertical height of the lifts exceeds ten (10) feet.
5. Drainage device inspection. After forms and pipes are in place, but before any concrete is placed.
6. Rough grading. When all rough grading has been completed. This inspection may be called for at the completion of the rough grading without the necessity of the Building Official having previously reviewed and approved reports.
7. Final. When all work, including installation of all drainage structures or other protective devices, has been completed and the as-graded construction document and required reports have been submitted.
(ORD-25-0019 § 1(Exh. A), 2025; ORD-22-0033 § 1(Exh. A), 2022; ORD-19-0031 § 1(Exh. A), 2019; ORD-16-0026 § 1(Exh. A), 2016)