§ 14-327 — Stormwater pollution prevention plan; contents of plans

Code of the City of Richmond, Virginia, 2026 (Recodification codified through Ordinance No. 2025-207, adopted October 14, 2025) · Richmond, Va., City Code § 14-327

Corpus is an independent public-information project, not the official City of Richmond website. Stable reference: corpuslaw.us/code/9a911872-28a2-4564-9c14-1ece6aec881e

Sec. 14-327. - Stormwater pollution prevention plan; contents of plans.

(a) The operator shall maintain a stormwater pollution prevention plan throughout the period of permit coverage that is consistent with the requirements of 9VAC875-500 and 9VAC25-880-70. The stormwater pollution prevention plan shall include, but not be limited to, an approved erosion and sediment control plan, an approved stormwater management plan (as approved by the City, or by the State pursuant to the general permit issued July 1, 2009) or an agreement in lieu of a stormwater management plan as provided in Section 14-326, a pollution prevention plan, and a description of any additional control measures necessary to address a total maximum daily load if a specific wasteload allocation for a pollutant has been established in a total maximum daily load and is assigned to stormwater discharges from construction. In addition, the stormwater pollution prevention plan shall include any information required by Section II (stormwater pollution prevention plan) of the general permit. (b) The stormwater pollution prevention plan shall meet the following requirements: (1) Control stormwater volume and velocity within the site to minimize soil erosion; (2) Control stormwater discharges, including both peak flow rates and total stormwater volume, to minimize erosion at outlets and to minimize downstream channel and stream bank erosion; (3) Minimize the amount of soil exposed during construction; (4) Minimize the disturbance of steep slopes; (5) Minimize sediment discharges from the site. The design, installation, and maintenance of erosion and sediment controls must address factors such as the amount, frequency, intensity and duration of precipitation, the nature of resulting stormwater runoff, and soil characteristics, including the range of soil particle sizes expected to be present on the site; (6) Provide and maintain natural buffers around surface waters, direct stormwater to vegetated areas to increase sediment removal and maximize stormwater infiltration, unless infeasible; (7) Minimize soil compaction and, unless infeasible, preserve topsoil; (8) Stabilization of disturbed areas must, at a minimum, be initiated immediately whenever any clearing, grading, excavating, or other earth disturbing activities have ceased permanently on any portion of the site, or have ceased temporarily on any portion of the site and will not resume for a period exceeding 14 calendar days. The stormwater pollution prevention plan shall require that stabilization be completed within a period of time determined by the City. In arid, semi-arid, and drought-stricken areas where immediately initiating vegetative stabilization measures is infeasible, the stormwater pollution prevention plan shall require that alternative stabilization measures be employed as specified by the City; and (9) Utilize outlet structures that withdraw water from the surface, unless infeasible, when discharging from basins and impoundments. (c) The permittee shall maintain the stormwater pollution prevention plan at a central location on the site of the land disturbing activity for as long as land disturbing activities are occurring on the site. If an on-site location is unavailable, the operator shall post notice of the stormwater pollution prevention plan's location near the main entrance to the site. The permittee shall make the stormwater pollution prevention plan available for public review in accordance with the terms of the general permit, either electronically or in hard copy. (d) The permittee's stormwater pollution prevention plan shall be written in compliance with the regulations, the terms of the general permit, and this article. The permittee shall amend the stormwater pollution prevention plan in a timely fashion to incorporate any change in design, construction, operation, or maintenance that has a significant effect on the discharge of pollutants to State waters.

(Code 2004, § 50-405; Code 2015, § 14-326; Code 2020, § 14-326; Ord. No. 2014-116-89, § 3, 5-27-2014; Ord. No. 2024-176, § 3, 7-22-2024)

Ask a question about Richmond law