Sec. 82-113. - Encasement for carrier pipe protection.
The city's responsibility pertains primarily to the safety and convenience of the traveling public. The utility is responsible for the quality and safety of the installation, including non-encased construction, when permitted. The following provisions shall govern:
(a) Encased pipe for road crossings:
(1) Encasement is recommended for all pipe installations across paved or hard-surfaced roads, where feasible, as a means of avoiding open trench construction and as a protection of carrier pipe from external loads or shocks.
(2) All coated carrier pipes are to be encased.
(3) All lines carrying gasses or liquids shall be encased.
(4) Lines with less than minimum bury, near footings of bridges and structures, across unstable or subsiding ground, or near other hazards must be encased. All encasements shall be of such design as will support the loads to which they are subjected and shall be of such materials as will be durable under conditions to which they may be exposed.
(5) Encasement pipe shall be of sufficient thicknesses as to withstand both external and internal pressures, with minimum as follows:
4—10" ..... 0.083 to 0.164"
wall thickness
12—18" ..... 0.104 to 0.188"
wall thickness
24—36" ..... 0.164 to 0.250"
wall thickness
(6) Encasement pipe should extend seven feet from the normal shoulder line of the roadway or a minimum of five feet from the toe of the embankment slope. In curb and gutter sections, the encasement shall extend at least to the back of the curbs.
(7) Encasements shall be sealed at the ends to prevent debris, soil, and moisture from entering the space between the carrier pipe and the casing.
(b) Unencased pipeline crossings. Under certain conditions, proposed pipeline crossings may be installed, or existing installations may remain in place, without encasement. The following conditions shall govern in such instances:
(1) The carrier pipe should conform to the material design requirements of the utility facility and to all governmental codes, specifications, and regulations.
(2) Carrier pipes shall provide for a higher factor of safety than would normally be required outside of the highway area.
(3) Existing unencased lines may remain in place without further protection if they were installed at such depth that will not conflict with future highway construction and maintenance and provided that both the city and the utility are satisfied that the lines are structurally sound.
(4) In the event it is necessary to replace unencased lines under the roadway, new lines will be installed by jacking and boring since the cutting of the pavement and base will not be permitted.
(5) When encasement under a road crossing is not provided or when an existing installation is to remain in place without encasement, the utility shall furnish the City of Clinton with a certificate as follows:
CERTIFICATE OF _________________________ UTILITY COMPANY FOR THE
UNENCASED PIPELINE CROSSING
PROJECT NO. ___________________________
NAME OF ROAD ________________________
CITY OF ________________________________
STATION NO. ___________________________
_______________________________________________ do hereby certify that
(Applicant)
the line at the location noted above carrying ________________________
(gas, oil, or fuels)
shown in this application will not need encasement and that the operating
Pressure will be _____________ pounds per square inch. This line will be
regularly inspected and adequately maintained. Extra yield strength (will be or was)
used in this installation as shown on the sketch or plans for this pipe crossing.
Adequate cover for the pipe is provided.
Certified Correct ____________________
Title _______________________________
Date ______________________________
(Ord. of 05-15-2007(2) )