Sec. 46-106. - Processing of permit applications.
A producer that wishes to perform filming must submit to the CAOE a completed application and the application fee set forth in code section 46-110 below. Where the producer is an organization, corporation or other entity, the application must be signed and submitted by an individual authorized to bind the producer. The CAOE will process the applications and the director will make permit determinations in accordance with this article IV.
(1) The application shall include, but not be limited to, the following:
a. The filming project name;
b. The name and contact information of the applicant, including postal address, email address, and telephone number;
c. A valid photo identification of the applicant;
d. The name and contact information of the producer (if the applicant is not the producer);
e. The dates, times and locations of the filming for which a permit is being requested, and a general description of the filming activity that will occur at each location;
f. A description of any elements that may be performed during the filming, including the dates, times and locations of each;
g. A description of any aspects of the filming, other than the elements, that may require city services;
h. A description of any assistance the producer may need from the CAOE, and/or concerns that the producer wants the CAOE to be aware of; and
i. Where the producer is a student, an official letter or document from her/his school confirming that s/he is currently enrolled there. In addition, the student must appear in person at the CAOE and present her/his current student identification card and a valid driver's license. Where the student does not have a driver's license, s/he may present a different form of identification that includes her/his photo.
(2) When more than one application is received for filming at substantially the same place and time, and the director reasonably determines that the filmings cannot logistically and/or safely occur together, the earlier or earliest of the applications that is received by the CAOE in a substantially completed form, which includes submission of the requisite application fee, shall be given priority as to the time and place requested. The CAOE shall make reasonable efforts to consult with the other applicant(s) in an attempt to find alternative times and/or locations that are acceptable.
(3) There is no deadline by which a filming permit application must be submitted to the CAOE; however, where a filming permit application includes a request for a street closure, the street closure portion of the application will not be approved unless it is received at least five business days prior to the closure.
(4) The CAOE and the departments of purview shall compile and maintain rules and guidelines applicable to the use of public property for filming, including the elements that are part of the filming, and shall apply those rules and guidelines equally regardless of the subject matter of the filming and/or the content of the speech therein.
(5) In the event that permission to perform an element is denied pursuant to subsection 46-105(2) above, the CAOE will process the remainder of the permit and grant all other aspects of the filming for which the requirements have been met.
(6) The CAOE may deny an application only if the director reasonably determines that one or more of the below-listed conditions exists. Prior to denial, the CAOE shall make reasonable efforts to consult with the producer in an attempt to resolve issues of concern and/or find alternative ways to accommodate the producer's filming needs, as described in subsections 46-106(7), (8), (9) and (10) below.
a. The filming poses an unreasonable risk of personal injury or property damage to people or property not associated with the filming;
b. The filming poses an unreasonable risk of damage to public property that could not be quickly and/or fully remediated;
c. The date and time requested for a particular filming location conflicts with previously-issued permits or permissions for filming, outdoor events, or other activities;
d. Use of the filming location, or use of the location during the date or time requested, would unreasonably interfere with the operation of city functions;
e. Use of the filming location or the proposed activity at the location would violate a law, ordinance, statute or regulation, regardless of whether the illegal activity is part of the message or content of the filming. A permit shall not be denied based upon simulation of an illegal activity where the actual illegal activity is not being performed;
f. The producer owes an outstanding debt to the city;
g. The producer previously caused significant damage to public property and, at the time of submitting the application under consideration, failed to adequately repair the damage or pay in full the city's invoice for damage repair and restoration services;
h. The producer previously violated this entertainment filming ordinance on two or more occasions, including without limitation by violating a material condition and/or restriction of a permit;
i. On two or more occasions, the producer's entertainment industry work in the city violated a city ordinance or other applicable law; and
j. The applicant made a material misrepresentation or gave incorrect material information on the application.
(7) Prior to denying an application, if the CAOE determines that the requested filming includes one or more of the conditions described in subsections 46-106(6)a., b., c., or d. above, the CAOE shall employ reasonable efforts to identify alternative filming locations, times and/or dates that eliminate the unacceptable condition(s) and that are mutually acceptable to the producer and the city. The producer shall modify the application to incorporate any agreed-upon alternatives.
(8) Prior to denying an application, if the CAOE determines that the requested filming or related activity creates a violation as described in subsection 46-106(6)c. above, the CAOE shall allow the producer to revise the application so that the filming activities comply with applicable law.
(9) Prior to denying an application pursuant to subsections 46-106(6)f. or g. above, the CAOE shall notify the producer of the potential denial and allow her/him to remedy the conditions described in those subsections. The CAOE shall process the application after such repair, restoration or payment is complete, and may require the producer to obtain a refundable sanitation bond for the filming permit in an amount equivalent to the cost of the repair, restoration or debt.
(10) Prior to denying an application pursuant to subsections 46-106(6)h., i. or j. above, the CAOE shall provide the applicant an opportunity to present documents or other evidence that refutes the director's finding of previous permit violations, of previous violations of the law, or of misrepresentation or misinformation on the application, as applicable.
(11) Where the director has complied with subsections 46-106(7), (8), (9) and/or (10) above and reasonably determines that one or more of the conditions set forth in subsection 46-106(6) continues to exist and that the application should therefore be denied, the director shall issue a written communication to the applicant that includes a detailed explanation for the denial. Nothing in this subsection shall preclude the director from also notifying the applicant orally.
(12) If the director denies an application, the applicant shall have the right to appeal the decision to the chief of staff or her/his designee, provided that a written request for such appeal is made to the chief of staff within three business days after the applicant's receipt of the director's determination. The person considering the appeal must be impartial, and must have had no involvement in the director's decision. The appeal shall be heard or considered within three business days after the city receives the applicant's request, and shall be decided de novo. The person considering the appeal shall evaluate the application and the director's decision in accordance with the criteria of this article IV.
(13) The person considering the appeal may issue her/his decision verbally, and shall issue a written decision within three business days of receiving written evidence from the applicant and/or meeting with the applicant, whichever is later. The written decision shall be the final decision of the city regarding the application. The applicant or producer may appeal the decision by writ of certiorari to the Superior Court of Fulton County pursuant to the procedures set forth by Georgia law.
(14) In no event shall the director's or any city employee's evaluation of whether to grant or deny the application, including any of the elements, include consideration of: a) the race, color, creed, religion, gender, age, disability, domestic relationship status, parental status, familial status, sexual orientation, national origin, gender identity, political affiliation or associational relationships of the applicant, producer or any person associated with the filming; or b) the message or content of the filming.
(Ord. No. 2013-33(13-O-0641), § 3, 7-3-13)