Indianapolis-Marion County Revised Code § 565-501 Floodplain status standards.
Sec. 565-501. - Floodplain status standards.
(a) Floodways (riverine). Located within SFHAs, established in section 565-302, are areas designated as floodways. The floodway is an extremely hazardous area due to the velocity of floodwaters, which carry debris, potential projectiles, and has erosion potential. Under the provisions of the Flood Control Act (IC 14-28-1). The purpose of the floodway designation is to guide development in areas identified as a floodway. IDNR, under the authority of the INRC, exercises primary jurisdiction in the floodway area. A permit for construction in a floodway from the Indiana Department of Natural Resources is required prior to the issuance of a local building permit for any excavation, deposit, construction, or obstruction activity located in the floodway. This includes land preparation activities such as filling, grading, clearing, and paving undertaken before the actual start of construction of the structure. General licenses and exemptions to the requirements of the Flood Control Act (IC 14-28-1 and 312 IAC 10) may apply to qualified additions/improvements to existing lawful residential structures, rural bridges, logjam removals, wetland restoration, utility line crossings, outfall projects, creek rock removal, and prospecting. The Consolidated City of Indianapolis and Marion County may impose terms and conditions on any floodplain development permit it issues in a floodway that are more restrictive than those imposed by IDNR regulations. The following regulations shall apply to all land within the floodway. These regulations shall be in addition to all other primary and secondary zoning district regulations applicable to such land, and in case of conflict, the more restrictive regulations shall apply.
(1) If the site is in a regulatory floodway as established in section 565-302, the floodplain administrator and/or designee shall require the applicant to apply to IDNR for a state permit for construction in a floodway and forward the application, along with all pertinent plans and specifications, to the Indiana Department of Natural Resources and apply for approval for construction in a floodway, provided the activity does not qualify for a general license or exemption (IC 14-28-1 or 312 IAC 10). A floodplain development permit shall not be issued by the floodplain administrator and/or designee for the proposed activity until the IDNR has issued a certificate of approval of construction in a floodway or a letter stating that IDNR approval is not required, and the floodplain administrator and/or designee determines that the application complies with all other applicable requirements of this article.
(2) No action shall be taken by the floodplain administrator and/or designee until approval has been granted by the Indiana Department of Natural Resources for construction in the floodway, or evidence provided by an applicant that the development meets specified criteria to qualify for a general license or exemption to the requirement of the Flood Control Act. The floodplain development permit shall meet the provisions contained in this article.
(3) The floodplain development permit cannot be less restrictive than an approval issued for construction in a floodway issued by the Indiana Department of Natural Resources, or the specified criteria used to qualify for a general license or exemption to the Flood Control Act for a specific site/project. However, a community's more restrictive regulations (if any) shall take precedence.
(4) In floodway areas identified on the FIRM, development shall cause no increase in flood levels during the occurrence of the base flood discharge without first obtaining a conditional letter of map revision and meeting requirements of section 565-405(a). A conditional letter of map revision cannot be issued for development that would cause an increase in flood levels affecting a structure and such development should not be permitted.
(5) In floodway areas identified by the Indiana Department of Natural Resources through detailed or approximate studies but not yet identified on the effective FIRM as floodway areas, the total cumulative effect of the proposed development, when combined with all other existing and anticipated development, shall not adversely affect the efficiency of, or unduly restrict the capacity of the floodway. This adverse effect is defined as an increase in the elevation of the regulatory flood of at least fifteen-hundredths (0.15) of a foot as determined by comparing the regulatory flood elevation under the project condition to that under the natural or pre-floodway condition as proven with hydraulic analyses.
(6) For all projects involving channel modifications or fill (including levees) the Consolidated City of Indianapolis and Marion County shall submit the data and request that the Federal Emergency Management Agency revise the regulatory flood data per mapping standard regulations found at 44 CFR § 65.12.
(7) Permitted uses. The following uses shall be permitted in the floodway subject to the development standards of this section.
a. Open land uses;
b. Land alterations and watercourse alterations;
c. Nonbuilding structures;
d. Accessory structures; and
e. Improvements, additions, and restoration of damage to legally established nonconforming uses.
(8) Development standards in the floodway.
a. Open land use. An open land use shall be allowed without a floodplain development permit provided that the open land use does not constitute or involve any structure, obstruction, deposit, construction, excavation, or filling in a floodway in accordance with IDNR regulations. Otherwise, proposed open land uses shall require a floodplain development permit in accordance with this chapter.
b. Land and watercourse alterations. Land alterations and watercourse alterations as defined in this article shall not result in any new or additional public or private expense for flood protection; shall assure that the flood carrying capacity is maintained and shall not increase flood elevations, velocities, or erosion upstream, downstream or across the stream from the proposed site; and shall not result in unreasonable degradation of water quality or the floodplain environment. In addition, no floodplain development permit shall be issued for land alterations or watercourse alterations in a floodway unless a certificate of approval for construction in a floodway is first issued by IDNR for the proposed activity, if required pursuant to IC 14-28-1.
c. Prohibition of garbage, trash, and junk. No use shall involve the storage, accumulation, spreading, dismantling or processing of garbage, trash, junk, or any other similar discarded or waste material.
(b) Fringe (riverine). The purpose of the floodway fringe is to guide development in areas subject to potential flood damage, but outside a floodway. If the site is in the fringe (either identified on the FIRM or identified by the Indiana Department of Natural Resources through detailed or approximate studies and not identified on a FIRM), the floodplain administrator and/or designee may issue the local floodplain development permit provided the provisions contained in this article have been met. The following regulations shall apply to all land within the floodway fringe. These regulations shall be in addition to all other primary and secondary zoning district regulations applicable to such land, and in case of conflict, the more restrictive regulations shall apply.
Permitted uses. All uses permitted in the applicable primary zoning district shall be those uses permitted in the floodway fringe, unless otherwise prohibited (prohibited uses), and provided no other secondary zoning district prohibits the use.
(1) Prohibited uses. The following critical facilities are prohibited from newly locating in the floodway fringe:
a. Jails;
b. Hospitals;
c. Assisted living facilities;
d. Nursing homes;
e. Laboratories;
f. Elementary, Middle or High Schools;
g. Daycare facilities;
h. Fire stations;
i. Emergency operation centers;
j. Police facilities;
k. Truck, train, or bus terminal, storage or maintenance facility;
l. Wrecking or salvage facility;
m. Gas, oil or propane storage facility;
n. Industrial laundry;
o. Hazardous waste handling or storage facility; and
p. Other public equipment storage facilities.
(2) Development standards in the floodway fringe.
a. Flood protection grade required. Except as specifically provided in this section, no building shall be erected, reconstructed, expanded, structurally altered, converted, used, relocated, restored, or improved unless the lowest floor elevation including any basement is provided and maintained at a flood protection grade of at least two (2) feet above the base flood elevation.
b. Flood-proofing. This flood protection grade may be achieved for nonresidential structures by structural flood-proofing. The design and construction shall be certified on a flood-proofing certificate by a professional engineer or professional architect registered in the State of Indiana as being adequate to withstand the flood depths, pressures, velocities, impact and uplift forces and other factors associated with the base flood.
c. Open land use. All open land uses as defined in this article shall be allowed in a floodway fringe without a floodplain development permit.
d. Land and watercourse alterations. Land alterations and watercourse alterations in a floodway fringe shall not result in any new or additional public or private expense for flood protection; shall not increase flood elevations or reduce flood carrying capacity; shall not increase velocities or erosion upstream, downstream, or across the stream from the proposed site; and shall not result in unreasonable degradation of water quality or the floodplain environment.
(3) Draining of land; altering of watercourses; construction of ponds, lakes, levee, dams. No draining or reclamation of land; altering, widening, deepening or filling of watercourses or drainage channels or ways; construction of ponds, lakes, levees, or dams; or any other changes or improvements of watercourses or drainage channels or ways shall be undertaken in the floodway fringe unless first approved by the IDNR, if applicable, and any other local, state or federal agencies having jurisdiction over such activity.
(4) Construction of new access roads. If the proposed activity includes the construction of a new access road between proposed buildings to be located in the floodway fringe and a public road, and the public road at the intersection with the proposed access road is at or above the base flood elevation, then the proposed access road must also be at or above the base flood elevation along the entire length between any proposed building and the public road. If there is more than one access road between the public road and any proposed building, only one must provide access at or above the base flood elevation.
(5) Compensatory storage required.
a. Whenever any portion of the SFHA is authorized for use, the volume of space that will be occupied by the authorized fill or structure below the base flood elevation shall be compensated for and balanced by an equivalent volume of excavation taken below the base flood elevation. The excavation volume shall be at least equal to the volume of storage lost (replacement ratio of 1 to 1) due to the fill or structure.
b. The excavation shall take place in the floodplain and on the same property that the authorized fill or structure is located.
c. Under certain circumstances, the excavation may be allowed to take place outside of but adjacent to the floodplain provided that the excavated volume will be below the base flood elevation, will be in the same property that the authorized fill or structure is located, will be accessible to the base flood water, will not be subject to ponding when not inundated by flood water, and that it shall not be refilled.
d. The excavation shall provide for true storage of floodwater but shall not be subject to ponding when not inundated by flood water.
e. The fill or structure shall not obstruct a drainage way leading to the floodplain.
f. The grading around the excavation shall be such that the excavated area is accessible to the base flood water.
g. The fill or structure shall be of a material deemed stable enough to remain firm and in place during periods of flooding and shall include provisions to protect adjacent property owners against any increased runoff or drainage resulting from its placement.
h. The compensatory storage area shall be outside the stream protection corridor (section 744-205).
i. The compensatory storage requirement excludes interior drainage behind accredited floodplain protection structures.
j. Plans depicting the areas to be excavated and filled shall be submitted prior to the actual start of construction or any site work; once site work is complete, but before the actual start of construction, the applicant shall provide to the floodplain administrator and/or designee a certified survey of the excavation and fill sites demonstrating the fill and excavation comply with this article.
(c) SFHAs without established base flood elevation and/or floodways/fringes (riverine).
(1) Drainage area upstream of the site is greater than one (1) square mile: If the site is in an identified floodplain where the limits of the floodway and fringe have not yet been determined, and the drainage area upstream of the site is greater than one square mile, the floodplain administrator and/or designee shall require the applicant to forward the application, along with all pertinent plans and specifications, to the Indiana Department of Natural Resources for review and comment.
No action shall be taken by the floodplain administrator and/or designee until written approval from the Indiana Department of Natural Resources (approval for construction in a floodway, letter of authorization, or evidence of general license qualification) or a floodplain analysis/regulatory assessment citing the one-percent annual chance flood elevation and the recommended flood protection grade has been received from the Indiana Department of Natural Resources.
Once the floodplain administrator and/or designee has received the proper written approval, evidence of general license qualification, or floodplain analysis/regulatory assessment approving the proposed development from the Indiana Department of Natural Resources, a Floodplain Development Permit may be issued, provided the conditions of the floodplain development permit are not less restrictive than the conditions received from the Indiana Department of Natural Resources and the provisions contained in this section have been met.
(2) Drainage area upstream of the site is less than one square mile: If the site is in an identified floodplain where the limits of the floodway and fringe have not yet been determined and the drainage area upstream of the site is less than one square mile, the floodplain administrator and/or designee shall require the applicant to provide an engineering analysis showing the limits of the floodplain and one-percent annual chance flood elevation for the site.
Upon receipt, the floodplain administrator and/or designee may issue the local floodplain development permit, provided the provisions contained in this article have been met.
(d) SFHAs not identified on a map.
(1) If a proposed development site is near a waterway with no SFHA identified on a map, the floodplain administrator and/or designee shall verify the drainage area upstream of the site. If the drainage area upstream of the site is verified as being greater than one square mile, the floodplain administrator and/or designee shall require the applicant to forward the application, along with all pertinent plans and specifications, to the Indiana Department of Natural Resources for review and comment.
(2) No action shall be taken by the floodplain administrator and/or designee until written approval from the Indiana Department of Natural Resources (approval for construction in a floodway, letter of authorization, or evidence of general license qualification) or a floodplain analysis/regulatory assessment citing the one-percent annual chance flood elevation and the recommended flood protection grade has been received from the Indiana Department of Natural Resources.
(3) Once the floodplain administrator and/or designee has received the proper written approval, evidence of general license qualification, or floodplain analysis/regulatory assessment approving the proposed development from the Indiana Department of Natural Resources, a floodplain development permit may be issued, provided the conditions of the floodplain development permit are not less restrictive than the conditions received from the Indiana Department of Natural Resources and the provisions contained in this article have been met.
(G.O. 22, 2024, § 1)