Seattle Mun. Code § 22.900D.010 Development permit fees
22.900D.010 - Development permit fees
A. General. The development fee shall cover the application, review and inspection process associated with new construction, additions, alterations, and repairs to existing buildings and establishment of use. The development fee shall consist of a permit fee and, where plans are reviewed, a separate plan review fee. The permit fee and plan review fee shall be determined based on valuation, except as provided below.
B. Time of payment of fees
1. Amount due prior to application. Fees for building pre-application conference and any additional fees accrued after the conference shall be due prior to permit application. See subsection 22.900D.010.I for building pre-application conference fees.
2. Amounts due at time of application. The following amounts are due at the time of application:
a. Applications for subject-to-field inspection (STFI) permits shall pay a fee equal to the permit fee specified in Table D-2 for 22.900D.010.
b. Applications for building and/or mechanical permits with plan review shall pay the plan review fees plus 1/2 the permit fee as specified in Table D-2 for 22.900D.010.
c. For development permits approved to be issued in phases, the plan review fee plus 1/2 the permit fee due at the time of application of the first phased submittal shall be calculated based on the value calculated in accordance with subsection 22.900D.010.C for the entire scope of the development permit. The remaining portion of the permit fee will not be collected until issuance of the final phase of the development permit that completes the scope of the proposed building project.
d. For other applications, the minimum fee specified in Table D-2 for 22.900D.010 shall be collected at the time of application.
3. Fees collected at the time of application will be based on Department estimates of the total fees due at the time of permit issuance. The final Department fees will be recalculated during review, and any additional amount due shall be collected prior to the issuance of the permit, approval, denial, decision, or recommendation, provided that hourly fees may be collected earlier, as described in subsection 22.900B.030.A. Any fee in excess of the final calculated fee shall be refunded pursuant to Section 22.900B.050 and subsection 22.900D.010.K.
4. If, when determining the project value and fees during initial review, the previously collected application fee is determined to be less than 90 percent of the revised application fee, review work after the initial review will not proceed until the balance is paid to the Department.
C. Determination of value
1. The Director shall determine the value of construction for which the permit is issued (the estimated current value of all labor and materials, whether actually paid or not, as well as all finish work, painting, roofing, electrical, plumbing, heating, air-conditioning, elevators, fire-extinguishing systems, automatic sprinkler systems, other mechanical systems, retaining walls, rockeries, and any other permanent work or permanent equipment, but not including furnishings). The building valuation data from the International Code Council and other valuation criteria approved by the Director will be used to determine the value of construction.
2. Dish or panel antennae. The fee for processing applications for installation of a dish or panel antenna shall be charged on the value of the foundation and supports constructed for the installation. The value of the dish or panel antenna shall not be included in the determination of value.
3. The development fee for parks and playgrounds shall be based on the project value, including the value of improvements for structures incidental to the park or playground such as retaining walls, rockeries, and restrooms, but shall not include the value of playground equipment.
4. The valuation shall be based on the highest type of construction to which a proposed structure most nearly conforms, as determined by the Director.
D. Phased permits
1. a.
If a new building project is proposed to be built in phases and the Director determines that separate development permits may be issued for approved portions of the project, the development fee for the entire permit shall be based on the value of work according to Table D-2 for 22.900D.010.
b. If the shoring and/or excavating work is included with the complete foundation (below grade) phase of the building project, the fees for such work shall be included in the fees described above.
c. If the proposed building project includes a separate shoring and/or excavation phase that is not combined with the complete foundation (below grade) phase, the shoring and/or excavation work will be reviewed and issued as a separate permit. The fees for the excavation portion of that permit shall be based on Section 22.900D.145, and the fees for the shoring portion of that permit shall be based on the value of that structural portion of the work according to Table D-2 for 22.900D.010. No credit will be given for any of these fees toward the phased building permit.
2. In addition to the fee specified in subsection 22.900D.010.D.1, if an applicant requests division of an already-submitted permit application a fee shall be charged for each separate application as specified in Table D-2 for 22.900D.010, and the fee to process this request shall be charged at the SDCI hourly rate.
E. Calculation of development fees. The development fee for a permit shall be calculated as described in this Section 22.900D.010.
1. Table D-1 for 22.900D.010 establishes the Development Fee Index for value-based development fees. Except as specified in Section 22.900D.010.F, Table D-2 for 22.900D.010 establishes the permit fee and plan review fee, calculated as a percentage of the development fee index where determined by value.
2. For the calculation of the Development Fee Index, as specified in Table D-1 for 22.900D.010, if a building is more than three stories high using construction Types 1A and 1B, the total building valuation may be modified for structure height depending on the building occupancy as described in the current Director's Rule clarification on "Implementation of the Fee Subtitle, Building Valuation," which is incorporated by reference.
3. If two or more buildings are allowed under one permit, they shall be assessed fees as separate buildings under Table D-2 for 22.900D.010. The individual fees shall then be added to determine the total development fee for the permit.
Table D-1 for 22.900D.010 - CALCULATION OF THE DEVELOPMENT FEE INDEX
Total Valuation | Development Fee Index
$0 to $1,000 | $325 for the first $1,000 of value or fraction thereof
$1,001 to $25,000 | $325 for the first $1,000 of value plus $1.60 for each additional $100 of value or fraction thereof
$25,001 to $50,000 | $709 for the first $25,000 of value plus $1.55 for each additional $100 of value or fraction thereof
$50,001 to $75,000 | $1,096.50 for the first $50,000 of value plus $1.50 for each additional $100 of value or fraction thereof
$75,001 to $100,000 | $1,471.50 for the first $75,000 of value plus $1.40 for each additional $100 of value or fraction thereof
$100,001 to $175,000 | $1,821.50 for the first $100,000 of value plus $7.75 for each additional $1,000 of value or fraction thereof
$175,001 to $250,000 | $2,402.75 for the first $175,000 of value plus $7.75 for each additional $1,000 of value or fraction thereof
$250,001 to $500,000 | $2,984 for the first $250,000 of value plus $7.50 for each additional $1,000 of value or fraction thereof
$500,001 to $750,000 | $4,859 for the first $500,000 of value plus $7 for each additional $1,000 of value or fraction thereof
$750,001 to $1,000,000 | $6,609 for the first $750,000 of value plus $7 for each additional $1,000 of value or fraction thereof
$1,000,001 to $1,500,000 | $8,359 for first $1,000,000 of value plus $6.75 for each additional $1,000 of value or fraction thereof
$1,500,001 to $2,000,000 | $11,734 for the first $1,500,000 of value plus $6.50 for each additional $1,000 of value or fraction thereof
$2,000,001 to $2,500,000 | $14,984 for first $2,000,000 of value plus $6 for each additional $1,000 of value or fraction thereof
$2,500,001 to $3,000,000 | $17,984 for the first $2,500,000 of value plus $6 for each additional $1,000 of value or fraction thereof
$3,000,001 to $3,500,000 | $20,984 for first $3,000,000 of value plus $5.25 for each additional $1,000 of value or fraction thereof
$3,500,001 to $4,000,000 | $23,609 for first $3,500,000 of value plus $5 for each additional $1,000 of value or fraction thereof
$4,000,001 to $4,500,000 | $26,109 for first $4,000,000 of value plus $4.50 for each additional $1,000 of value or fraction thereof
$4,500,001 to $5,000,000 | $28,359 for the first $4,500,000 of value plus $4.50 for each additional $1,000 of value or fraction thereof
$5,000,001 to $10,000,000 | $30,609 for the first $5,000,000 of value plus $4 for each additional $1,000 of value or fraction thereof
$10,000,001 to $25,000,000 | $50,609 for the first $10,000,000 of value plus $4 for each additional $1,000 of value or fraction thereof
$25,000,001 to $50,000,000 | $110,609 for the first $25,000,000 of value plus $3.25 for each additional $1,000 of value or fraction thereof
$50,000,001 to $75,000,000 | $191,859 for the first $50,000,000 of value plus $2.75 for each additional $1,000 of value or fraction thereof
$75,000,001 to $100,000,000 | $260,609 for the first $75,000,000 of value plus $2.75 for each additional $1,000 of value or fraction thereof
$100,000,001 to $150,000,000 | $329,359 for the first $100,000,000 of value plus $2.25 for each additional $1,000 of value or fraction thereof
$150,000,001 to $200,000,000 | $441,859 for the first $150,000,000 of value plus $2.25 for each additional $1,000 of value or fraction thereof
$200,000,001 and up | $554,359 for the first $200,000,000 of value plus $2 for each additional $1,000 of value or fraction thereof
Table D-2 for 22.900D.010 - CALCULATION OF DEVELOPMENT FEES DETERMINED BY VALUE
Type of Development | Percent of Development Fee Index (DFI) Calculated from Project Value as Specified in Table D-1 1 for 22.900D.010
Permit Fee | Plan Review Fee
1. Building, with or without mechanical, with or without use | 100% of DFI | 100% of DFI
2. STFI (Subject to field inspection - building and/or mechanical 2 ) | 100% of DFI | 40% of DFI
3. Energy code compliance review using Total UA Alternative and/or Simulated Performance Alternative | (included in subsection 1 of this Table D-2 for 22.900D.010) | SDCI hourly rate, 1 hour minimum
4. Mechanical permit:
a. Submitted as part of a building permit application (if associated with other work) | (included in subsection 1 of this Table D-2 for 22.900D.010) | Mechanical review at the SDCI hourly rate, 1 hour minimum
b. If submitted separately from a building permit application (if associated with other work) or if applied for as a mechanical only permit; also see Section 22.900D.090 for mechanical equipment fees | 100% of DFI | SDCI hourly rate, 1 hour minimum
5. Blanket permit review fees:
a. Tenant alterations applied for within 18 months of the date of issuance of the first certificate of occupancy within a building where the area of work is more than 50,000 sq. ft. | $3.70 per 100 square feet 1 | $4.25 per 100 square feet 1
b. Tenant alterations applied for after 18 months of the date of issuance of the first certificate of occupancy | 100% of DFI | 100% of DFI
6. Initial tenant alterations applied for within 18 months of the date of issuance of the first certificate of occupancy (nonblanket permit initial tenant improvements to shell and core) 3 | 50% of DFI based on new building value of shell and core | 50% of DFI based on new building value of shell and core
7. Standard plans:
a. Establishment of standard plan, including temporary structures. (For swimming pools, see subsection 16 of this Table D-2 for 22.900D.010.) | 100% of DFI | 200% of DFI, plus SDCI hourly rate for review/approval of "options"
b. Establishment of already permitted plan as standard plan | 100% of DFI | 100% of DFI, plus SDCI hourly rate for review/approval of "options"
c. Subsequent reviews of standard plan, other than temporary structures | 100% of DFI | 60% of DFI, plus SDCI hourly rate for review/approval of "revisions"
d. Subsequent reviews of standard plans for temporary structures | See subsection 18 of this Table D-2 for 22.900D.010 | See subsection 18 of this Table D-2 for 22.900D.010
8. Factory-built housing and commercial structures:
a. Modular construction, 3 or fewer stories | Base fee × 1 | Base fee × 1 for each module
b. Modular construction, more than 3 stories | Base fee × 1 | Base fee × 1 for each module, plus SDCI Hourly Rate for structural review
Special Development Fees
9. Establishing use for the record:
a. Applications with no construction | Base Fee × 1.5 | None
b. Applications with construction: Refer to subsection 17 of Table C-1 for 22.900C.010, for additional Land Use Fees that apply to this permit type | 100% of DFI | 100% of DFI
10. Building review associated with platting actions and/or LBAs | None | SDCI hourly rate; .25 hour minimum
11. Noise survey reviews | None | See Table F-2 for 22.900F.020 Noise Fees
12. Parking facilities:
a. Outside a building | See Section 22.900D.060
b. Within or on a building | See subsection 22.900D.010.C
13. Renewal (or Reestablishment) of development permits and/or separate mechanical permits See subsection 22.900D.010.G and subsection 22.900D.010.L for exceptions and modifications to fee | Base fee × 1.5 | SDCI hourly rate
14. Single-family seismic retrofit:
a. Permit for work in full compliance with prescriptive earthquake home retrofit (EHR) plan set | Base fee × 1 | None
b. Permit for work in partial compliance with prescriptive earthquake home retrofit (EHR) plan set with additional engineering design of those portions not in compliance | Base fee × 1 | SDCI hourly rate with 1 hour minimum
c. Voluntary seismic upgrades requiring full engineering/design and not per prescriptive earthquake home retrofit (EHR) plan set | 100% of DFI | 100% of DFI
15. Unreinforced Masonry Building (URM) designation or seismic retrofit:
a. Review to appeal unreinforced masonry bearing wall building designation | N/A | Base fee × 1 (waived if appeal approved)
b. Permits for work associated with any earthquake retrofit of an unreinforced masonry building contributing to a code compliant retrofitted URM | 50% DFI | 50% DFI
16. Special inspection | Base fee × 1
17. Swimming pools: 4
a. Unenclosed pools accessory to Group R-3 occupancy | Base fee × 4
b. Unenclosed pools accessory to occupancies other than Group R-3 | Base fee × 6
c. Principal use unenclosed pools | Base fee × 6
d. Future construction of an unenclosed swimming pool | Base fee × 1
e. Initial approval of standard plan for swimming pool accessory to Group R-3 occupancy | Base fee × 5
f. Subsequent review of application based on approved swimming pool standard plan | Base fee × 1.5
18. Temporary structures, such as commercial coaches 5 | Base fee × 2 per structure
19. Temporary use permits:
a. For 4 weeks or less 6 | Base fee × 1.5
b. For more than 4 weeks 6 | Base fee × 2
20. Phased Permits:
a. Value ≤ $5,000,000 | Base fee × 1
b. Value > $5,000,000 | Base fee × 2
21. ECA Small Project Waiver on a building permit | None | SDCI hourly rate; 0.25 hour minimum
22. Street Improvement Exceptions on a building permit | SDCI Land Use Hourly × 2 | Land Use Hourly rate for each review hour spent beyond 2 hour minimum fee
23. Building Permit Shop Drawings | None | SDCI hourly rate: 1.75 hour minimum
24. Sprinkler Shop Drawings | None | SDCI hourly rate: 0.75 hour minimum
25. Sprinkler Only Permit Submittals (New and/or Add/Alt) | Base fee × 0.75 | See Chapter 22.900G; this fee is determined by the Seattle Fire Department
26. Code Alternate Request | None | SDCI hourly rate, 2 hour minimum
27. Commercial Re-Roofing Permit | Base fee × .5
Footnotes to Table D-2 for 22.900D.010 1 The minimum permit fee or plan review fee for value-based fees is $292. 2 The minimum plan review fee for subject-to-field-inspection (STFI) value-based plan review is $116.75. 3 This fee is applicable only to those initial tenants that reflect the use and occupancy established in the shell and core permit. The value used shall be the new construction value used in calculating value for the shell and core permit. 4 If a swimming pool is located within an enclosed building and is included in the building plans for that building, a separate fee shall not be charged for the swimming pool. The swimming pool area will be considered as floor area of the principal occupancy of the building. 5 This fee shall not apply to any on-site, temporary construction office where a valid building permit is in force. 6 Master use permit fees for such temporary uses shall be charged according to Table C-1 for 22.900C.010.
F. Blanket permits
1. The application fee for a blanket permit to cover nonstructural tenant alterations is one times the base fee. A deposit based on the estimated value of the proposed work within 18 months shall be collected at the time of application. As individual tenant spaces are reviewed, the fee for the work to be done shall be calculated according to Table D-2 for 22.900D.010 and deducted from the deposit.
2. If the estimated blanket fee deposit is used up in less time than the life of the permit and work remains to be done, an additional deposit shall be paid based on the estimated floor area remaining to be improved during the remaining life of the permit. If a portion of the deposit is unused at the end of the life of the permit and work remains to be done, credit for the balance of the deposit may be transferred from the expiring permit to a new blanket permit. To minimize additional accounting costs associated with blanket permits, if more than two deposits are made during the life of the blanket permit, the minimum amount of each subsequent deposit shall be $2,000.
G. Revisions to issued permits. Fees for revisions to issued permits shall be charged according to standards promulgated by the Director that approximate the additional cost of reviewing the revisions. A nonrefundable fee of one times the base fee shall be paid at the time the revisions are submitted.
H. Certificate of Occupancy. The issuance of a Certificate of Occupancy for existing buildings, either if no Certificate of Occupancy has previously been issued or if a change of occupancy is requested, requires a building permit. If there is no construction valuation (there is no work that would require a building permit), the minimum building permit fee shall be assessed. In addition to the minimum building permit fee, if records research, plan examination, or inspection is required, charges shall be assessed at the SDCI hourly rate. If work is being done as authorized by a permit, the permanent Certificate of Occupancy fee is not assessed in addition to the building permit fee. The fee for a temporary Certificate of Occupancy shall be charged at the rate of 1/2 the base fee. The fee for the duplication of a Certificate of Occupancy is $48.85 unless records research, plan examination, or inspection is required, in which case charges shall be assessed at the SDCI hourly rate.
I. Building pre-application conferences
1. Required building pre-application conferences. If there is a requirement for a pre-application or pre-design conference, such as buildings subject to the Seattle Building Code special provision for atriums (Section 404), or high-rise buildings (Section 403), 35 percent of the estimated plan review fee for the structure shall be charged and paid as specified in subsection 22.900D.010.B, and applied toward the development permit fee provided the permit application is made within six months of the date of the pre-application conference. (See Table C-1 for 22.900C.010 for land use pre-application conference fees.)
2. Other building pre-application conferences. If a pre-application conference is requested by the applicant but is not required by Code, a fee equal to 1.5 times the base fee shall be paid no later than the time of the conference. Such fee is required for each meeting held on a project. In addition to the minimum building pre-application conference fee, if additional staff, research, preliminary plan examination or inspection is required, charges shall be assessed at the SDCI hourly rate and shall be charged and paid as specified in subsection 22.900D.010.B.
J. Correction Fee. After written notice to the applicant, a Correction Fee of two times the SDCI base fee may be charged for each additional correction cycle required due to insufficient response from the applicant.
K. Renew or reestablish a permit
1. Fees to renew or reestablish a permit shall be charged according to Table D-2 for 22.900D.010. If the fee for a new permit would be less than 1.5 times the base fee, then the fee to renew or reestablish the permit shall be the same as for a new permit.
2. Fees to renew or reestablish a fire sprinkler permit shall be 1/2 the base fee.
3. If changes are made to the original approved plans, an additional fee shall be charged for plans examination and inspections at the SDCI hourly rate.
(Ord. 127360, § 3, 2025; Ord. 127134, § 5, 2024; Ord. 127133, § 5, 2024; Ord. 126935, § 8, 2023; Ord. 126709, § 5, 2022; Ord. 125982, § 6, 2019; Ord. 125704, § 4, 2018; Ord. 125451, § 4, 2017; Ord. 125184, § 8, 2016; Ord. 124919, § 103, 2015 [department name change and other cleanup]; Ord. 124636, § 6, 2014; Ord. 124047, § 7, 2012; Ord. 123755, § 8, 2011; Ord. 123453, § 12, 2010; Ord. 123246, § 2, 2010; Ord. 122855, § 5, 2008; Ord. 122297, § 7, 2006; Ord. 121851, § 1, 2005; Ord. 121664, § 7, 2004; Ord. 120997, § 5, 2002; Ord. 120818, § 8, 2002; Ord. 120448, §§ 3, 4, 5, 2001; Ord. 119766, § 5, 1999; Ord. 119255, § 2, 1998.)