Dayton City Code § 151.80 Bond for installation of improvements.
Sec. 151.80. - Bond for installation of improvements.
(A) General. In order that the city has the assurance that the construction and installation of such improvements as street surfacing, curbs, gutters, sidewalks, public sanitary sewers, public water supply, and street signs will be constructed, and lot grading completed the subdivider shall enter into one of the following agreements:
(1) To construct all improvements directly affecting the subdivision, as required by the Plan Board, prior to the final approval of the plat; or
(2) In lieu of the completion of the improvements, furnish bond executed by a surety company or certified check equal to the cost of construction of such improvements as shows on plans, and based on an estimate approved by the Supervisor of Plats.
(B) Conditions.
(1) Before the final plan is given final approval the developer shall have executed a subdivider's contract and a performance bond or certified check with the Supervisor of Plats covering the estimated cost of required improvements.
(2) The performance bond or cash deposit shall run to the city or applicable government entity for a period of two years from date of execution, and shall provide that the subdivider, his heirs, successors, and assigns, their agent or servants, will comply with all applicable terms, conditions, provisions, and requirements of these regulations, and will faithfully perform and complete the work of constructing and installing such facilities or improvements in accordance with such laws and regulations.
(3) Before this bond is accepted it shall be approved by the proper administrative officials.
(4) Whenever a cash deposit is made, it shall be made to the city.
(C) Extension of time.
(1) If the construction or installation of any improvement or facility, for which guarantee has been made by the developer in the form of bond or cash deposit, is not completed within two years from the date of final approval of the record map, the developer may request the Supervisor of Plats to grant an extension of 12 months, provided he can show reasonable cause for inability to complete the improvements within the required two years. The extension shall not exceed 12 months. At the expiration of the 12-month extension the city will use as much of the bond or cash deposit as necessary to complete the construction of the improvements.
(2) The same shall apply whenever construction of improvements is not performed in accordance with applicable standards and specifications.
(D) Completion of work. As required improvements are completed, approved and accepted, the Supervisor of Plats may reduce the amount of the performance bond or cash deposit.
(E) Inspections.
(1) Periodic inspection during the installation of improvements shall be made by the city to insure conformity with the approved plans and specifications as required by these regulations. The subdivider shall notify proper administrative officials at least 24 hours before each phase of the improvements is ready for inspections.
(2) The absence of an inspector from a plat during construction shall not relieve the subdivider from full responsibility under this agreement. Upon acceptable completion of installation of the required improvements, the city engineer shall issue a letter to the subdivider or his agent and such letter shall be sufficient evidence for the release of bond by the city.
(F) Failure to comply. Whenever public improvements have not been constructed in accordance with the agreement and with specifications as established, the city may exercise its rights of foreclosure under the bond.
(Ord. 24655, passed 2-20-74)