SEC. 6-306. - REIMBURSEMENTS.

(a) Oversize Sewer Mains (Non-UGM). Reimbursements for Oversize Sewer Charges paid pursuant to subdivision 6-304(a)(2), as the result of development in areas other than an UGM sewer service area, shall be made as follows: (1) When a city sewer main installed by a person is required by the Director to be constructed to a size larger than eight inches in diameter, the city shall reimburse such person in an amount designated in the Master Fee Resolution. The amount to be reimbursed shall be credited against the Oversize Sewer Charge to be paid on behalf of all property contributing to the cost thereof, in proportion to the amount of such contribution. If the credit for any such property exceeds the Oversize Sewer Charge, then a sum equal to the difference shall be paid from the sewer connection account upon city acceptance of the main. (2) When a city oversize sewer main installed by a person is required by the Director to be constructed at a depth greater than eight feet, the city shall reimburse such person in an amount designated in the Master Fee Resolution. The amount to be reimbursed shall be credited against the Oversize Sewer Charge to be paid on behalf of all property contributing to the cost thereof in proportion to the amount of such contribution. If the credit for any such property exceeds the Oversize Sewer Charge, then a sum equal to the difference shall be paid from the sewer connection account upon city acceptance of the main. (b) City Sewer Mains. (1) This subdivision shall be applicable to city sewer mains installed after July 1, 1975, except when constructed by special assessments, (2) Any person installing a city sewer main shall, prior to construction of the city sewer main, file with the Director a legal description of the properties on behalf of which contributions have been made to the cost of the construction, and a statement of the proportions of the cost borne by each property. Within ninety days following city acceptance of the city sewer main, such person shall file with the Director a project accounting, in a form as specified by the Director, stating the cost (excluding any city reimbursement) of the construction of the main. In the event a project accounting has not been filed with the Director within such period, then a reimbursement under subdivision (b)(3), below, shall not be made in the event additional property is connected to the sewer main constructed. If an ownership statement is not filed prior to construction, only the property served by the city sewer main and owned by the person who installed the city sewer main on the date of commencement of installation will be deemed to have paid for the installation; provided, that if within seven years after the date of commencement of installation such person acquires in fee property served by the city sewer main which would otherwise be subject to payment of Lateral Sewer Charges, such person shall also be deemed to have paid the Lateral Sewer Charges for such property. (3) For the initial reimbursement period, or, if applicable, the extended reimbursement period, as such terms are defined in Section 12-4.501.5-F of this Code, after city acceptance of a city sewer main referred to in subdivision (b)(1) above, the person or persons bearing the cost of such city sewer main construction may be reimbursed pursuant to this subdivision (b). The Lateral Sewer Charges collected by the city pursuant to this article for connection to such city sewer main shall be paid by the city proportionately to the owner or owners of property on behalf of which contributions were made to the cost of construction of such city sewer main. When a person is entitled to an UGM fee reimbursement under this subsection, the city shall make semiannual payments, in amounts determined by the Director, in the manner and for the period prescribed by Section 12-4.504-C of this Code. However, neither shall reimbursement exceed the sum of (1) one hundred percent of the cost of constructing city sewer mains which do not front on any contributing property, and (2) fifty per cent of the cost of constructing city sewer mains fronting on properties on behalf of which such contributions were made; nor shall the total reimbursement exceed the total amount of the Lateral Sewer Charges which would have been payable by property on behalf of which no contribution was made to the cost of installation as of the date of city acceptance of the city sewer main. Such reimbursements shall be paid from the applicable sewer connection account. (4) If the total amount of the Lateral Sewer Charges (based on fees in effect on the date of city acceptance of the city sewer main) which would be collectible from property on behalf of which no contribution has been made to the cost of installation is less than one thousand dollars, the Director may elect to proportionately reimburse from the applicable sewer connection account, after completion of the city sewer main, to the person or persons contributing to the cost of constructing the city sewer main, the amount of said Lateral Sewer Charges which would be collectible from non-contributing property. If the Director elects to reimburse in this manner, such person or persons will be eligible neither for the exemption provided in subdivision (b)(2) above nor for further reimbursement provided in subdivision (b)(3) above. (5) For purposes of reimbursements, where a property has more than one frontage, the actual Lateral Sewer Charge paid shall be apportioned between the frontages on which the calculation of charges was based in the ratio of the total length of each frontage. (c) UGM Oversize Sewer Mains. Oversize Sewer Service Areas shall be established for all land located within the Urban Growth Management Area, the boundaries of which areas shall reflect that territory which the Director determines will receive primary service from existing or projected oversized facilities or other trunk sewer mains identified by the Director. (1) The maximum reimbursement for oversize sewer cost, which may be paid from the sewer connection account upon city acceptance of an oversize sewer main, shall be an amount designated in the Master Fee Resolution. (2) All subsequent reimbursements, in amounts designated in the Master Fee Resolution, shall be determined semiannually on or about each April first and October first following city acceptance of the city sewer main, and shall occur only to the extent Oversize Sewer Charges are paid on behalf of non-contributing properties located within the service area of the oversize sewer main for the duration of the appropriate reimbursement period, as defined in Section 12-4.501-F of this Code. The order of reimbursements shall be based on the dates of submittal of project accountings to the Director. Reimbursements shall not be initiated for an oversize sewer main until reimbursements are complete for oversize sewer mains covered by previously submitted project accountings. Project accountings must be filed with the Director within ninety days of city acceptance of the oversize sewer main. Reimbursements shall not be made if project accountings are not so filed within such period. (3) In the event all construction which would be subject to payment of the Oversize Sewer Charge which would be used for reimbursement purposes within an UGM service area is effectively barred or prohibited by any governmental agency having superior jurisdiction to the city, or by any legal action initiated by or on behalf of any such agency, the applicable reimbursement period as defined in Section 12-4.501.5-F of this Code, shall be extended on a day-to-day basis for the duration of any such moratorium, but not exceeding the appropriate cumulative reimbursement period. (4) Reimbursements in excess of the maximum reimbursement amount may be paid only after such amount has been repaid through the collection of Oversize Sewer Charges within the service area of the subject oversize sewer main. A credit shall be given against the Oversize Sewer Charge on those properties required to construct an oversize sewer main whenever the estimated cost of construction exceeds the fee obligation. (d) When reimbursements are made pursuant to subdivision (b) or (c) of this Section 6-306, the city shall retain an administrative charge pursuant to Section 12-4.504-C. Reimbursement of the fees shall be made in the manner and for the period prescribed by Section 12-4.504-C of this Code. (e) Trunk Sewer Mains Reimbursement Provisions. (1) Where a developer installs a trunk sewer main or portion thereof, he shall file with the Director, within ninety days following city acceptance of the trunk sewer main, a project accounting stating the cost of construction of the trunk sewer main. The project accounting shall include a legal description of all properties on behalf of which contributions have been made to such costs, and a statement of the proportion of the costs borne by each property. (2) Following the receipt of the project accounting, the Director shall make semiannual determinations on or about each April first and October first, in the manner prescribed in Section 12-4.504-C of this Code, of the amounts to be reimbursed to the persons who constructed the trunk sewer main as shown in the project accounting, subject to the following: (i) Each determination shall calculate the Trunk Sewer Charges which have been collected during the preceding six months for land developed within the Trunk Sewer Service Area in which the trunk sewer main is located. (ii) No reimbursements shall be made if the project accounting was not filed within the time specified in subdivision (1) of this subsection. (iii) In no event shall reimbursement payments be made which total in excess of the cost of the trunk sewer main as shown on the project accounting. (3) The Trunk Sewer Charge on the property contributing to the cost of the trunk sewer main shall be either increased or decreased by an amount equal to the difference between the actual cost of construction and the fee obligation established at the time of the granting of the entitlement. (4) Reimbursement payments shall be made neither after the end of the appropriate reimbursement period, as defined in Section 12-4.501-F of this Code, nor shall reimbursement be made which would reduce the balance in the Trunk Sewer Service Area account to an amount less than the bond debt payments due during the next twelve months. (5) The priority of reimbursements shall be according to dates the project accounting statements are accepted by the Director. (6) Reimbursements shall not be made until reimbursements are complete for the trunk sewer main, which is covered by previously submitted project accounting statements.

(Added Ord. 75-69, § 6, eff. 7-27-75; Am. Ord. 76-8, § 1, eff. 2-22-76; Am. Ord. 80-115, § 101, eff. 8-8-80; Am. Ord. 80-164, § 7, eff. 12-5-80; Am. Ord. 83-163, § 1, eff. 1-20-84; Am. Ord. 89-85, §§ 1, 2, eff. 7-28-89; Added Ord. 90-84, § 7, eff. 8-31-90; Am. Ord. 98-97, §§ 10, 11, 1-9-99)