Design and protection requirements for new developments or re-developments requiring a post-construction stormwater management plan.
Gulfport Code of Ordinances, App. C, § 6
in effectSection 6. - Design and protection requirements for new developments or re-developments requiring a post-construction stormwater management plan.
6.1 Grading, erosion control practices, sediment control practices and waterway crossings shall meet the design criteria set forth in the most recent version of the Stormwater Design Manual. All sites shall establish stormwater management practices to control the peak flow rates of stormwater discharge associated with specified design storms and reduce the generation of stormwater for the site to provide treatment for both water quality and quantity.
6.1.1 Fill slopes shall be no greater than 3:1, except as approved by the building code services division or engineering department to meet other community or environmental objectives.
6.2 Clearing and grading of natural resources, such as forests and wetlands, shall be permitted only when in compliance with all other sections of this Code. Clearing techniques that retain natural vegetation and drainage patterns, as described in the Stormwater Design Manual, shall be used to the satisfaction of the building code services division or engineering department.
6.3 No clearing shall begin until approved sediment control devices are in place and operable according to Stormwater Design Manual.
6.4 Phasing is the preferred method and will be encouraged to be adopted on larger sites. A plan and drawing showing such practices shall be submitted.
6.5 Erosion control requirements shall include the following:
6.5.1 Soil stabilization shall be completed as soon as practical but not later than five (5) days after clearing or inactivity in construction. The city engineer, public works director, or building official may shorten this time frame based on projected weather conditions.
6.5.2 If seeding or another vegetative erosion control method is used, it shall become established within two (2) weeks and the building official or city engineer may require the site have another method in place until the soil is stabilized.
6.5.3 Special techniques that meet the design criteria outline in the Stormwater Design Manual on steep slopes or in drainage ways shall be used to ensure stabilization.
6.5.4 Soil stockpiles or similar materials shall be stabilized or covered at the end of each workday.
6.5.5 The entire site shall be stabilized to control erosion at the close of construction for any prolonged periods in excess of forty-eight (48) hours.
6.5.6 Techniques shall be employed to prevent blowing of dust or sediment from the site.
6.5.7 Techniques that divert upland runoff past disturbed slopes shall be employed.
6.5.8 The use of techniques to prevent erosion and sedimentation from entering public roads or other areas including ditches, storm drains, and other drainage facilities.
6.6 Sediment control requirements include any of, or a combination of the following:
6.6.1 Settling basins, sediment traps, or tanks and perimeter controls.
6.6.2 Settling basins that are designed in a manner that allows adaptation to provide long-term stormwater management, when necessary or required by building code services division or the engineering department.
6.6.3 Protection for adjacent properties by the use of a vegetated buffer strip where practical and the use of perimeter controls.
6.7 Waterway and watercourse protection when required shall include:
6.7.1 A temporary stream crossing installed by the contractor and approved by the engineering department.
6.7.2 Stabilization of the watercourse channel before, during and after any in-channel work.
6.7.3 All on-site stormwater conveyance channels designed according to the criteria outlined in the Stormwater Design Manual.
6.7.4 Stabilization adequate to prevent erosion located at the outlets of all pipes and paved channels.
6.8 Construction site access requirements shall include a temporary access road and other measures required by building code services division or the engineering department in order to ensure that sediment is not tracked onto public rights-of-way by construction vehicles or washed into storm drains.
6.9 Work in or around natural wetlands should be consistent with the requirements outlined in the Coastal Wetlands Protection Act, The Clean Water Act, and all other federal and state requirements regarding wetlands. For new development or re-development, structural and non-structural stormwater treatment practices shall be designed to treat runoff, where required by MDEQ regulations.
6.9.1 To protect stream channels from degradation, appropriate channel protection shall be utilized.
6.9.2 Stormwater discharges to critical areas with sensitive resources (including shellfish beds, recreational areas, water supply reservoirs and groundwater recharge areas) are subject to additional performance criteria, or may need to utilize or restrict certain stormwater management practices.
6.9.3 Stormwater discharges from land uses or activities with higher potential pollutant loadings, known as "hotspots," may require the use of specific structural and pollution prevention practices. Such sites shall be identified on plans upon submission of a construction, grading or building permit application.
6.10 Stormwater maintenance agreements.
6.10.1 A legally binding covenant specifying the parties responsible for the proper operation and maintenance for all stormwater management facilities after construction is complete shall be included in the post-construction stormwater management plan and secured prior to issuance for any permits for land disturbance activities.
6.10.2 Enforceable operations and maintenance agreements are required to ensure the system will function as designed during and after construction. The maintenance agreements will include any and all maintenance easements required to access and inspect the stormwater treatment practices, and to perform routine maintenance as necessary to ensure proper functioning of the stormwater treatment practices. The parties responsible for the documented SWPPP BMPs shall make records of the installation, maintenance and repairs on the facility and shall retain these records for at least five (5) years. These records shall be provided to the city engineer annually by January 15 of each calendar year and during inspection of the facility or upon request.
6.10.3 Failure of the owner or operator to maintain the premises as required by the executed and recorded covenant shall be cause for the city to take action to inspect the property and request the owner to make any and all necessary repairs to the stormwater management facilities on the property. If the owner fails to perform the necessary maintenance and/or repairs, the City of Gulfport shall assess against the owner of the property a civil penalty in the amount of the estimated cost of the necessary repairs, as certified by the city engineer. The city may undertake any and all means available to it to collect this civil penalty from the appropriate party/ies.
(Ord. No. 2419, § 1, 1-19-05; Ord. No. 3031, § 3, 5-5-20)