Sec. 6.2. - Bond and surety: amount and release.
A. In the event it is decided by the subdivision committee that the requirements set out in section 6.1A of this article need not be immediately met by the subdivider, the requirements may be deferred by temporary waiver, upon the execution of a subdivision improvement agreement with the subdivider, as approved by the city attorney, to run with the land, binding any future owners. That instrument shall require that all such improvements be installed and constructed within the length of time specified in section 6.3 of these regulations, and the subdivider shall maintain said improvements and shall guarantee the work to be free from defect of materials or workmanship for a period of one year following the acceptance of dedication by the city council. A performance bond shall be required by the city engineer to insure the fulfillment of such agreement, and shall be in cash, by certified or cashier's check, acceptable certificates of deposit, irrevocable letters of credit, or made by a surety company authorized to do business in the State of Alabama. Upon submission of satisfactory bond or surety to the city engineer, said surety and the subdivision improvement agreement, and the final plat can be recorded in probate court. B. Such bond shall be in an amount equal to 115 percent of the estimated cost of the improvements. Bond amounts shall be reviewed annually and may be adjusted to ensure adequate funds are available for the completion of the remaining required improvements. C. The surety shall not be released from said bond except by a release in writing from the city engineer. D. In the event the developer does not cause to be installed the infrastructure improvements required by these regulations within two-years, of the approval of the final plat and a time extension is not granted by resolution of the subdivision committee, the city shall cause the improvements to be installed and shall pay for said improvements by redeeming the bond submitted by the developer as required by these regulations for the purpose of ensuring the installation of the required infrastructure improvements.
Ask a question about Birmingham law
Corpus searches the Birmingham sections it holds and shows the ones that match, with their citations. Free, no sign-in.