§ 90-137 — Requirements for streets and other rights-of-way
Code of Ordinances of the City of Dothan, Alabama (Codified through Ordinance No. 2026-96, enacted April 21, 2026. (Supp. No. 67)) · Dothan Code of Ordinances § 90-137
Corpus is an independent public-information project, not the official City of Dothan website. Stable reference: corpuslaw.us/code/4e629fde-3d64-4d98-9ba6-f3a1086b76dd
Sec. 90-137. - Requirements for streets and other rights-of-way.
(a) Continuation of existing streets. Existing streets shall be continued at the same or greater width, but in no case less than the required width as stated in section 90-223(d)(3). (b) Connections with future subdivisions. Streets shall be reserved at strategic locations to provide for future access to adjoining properties which may be subdivided in the future. Paved temporary turnarounds shall be required at the end of streets not exceeding 150 feet in length. Each street connection shall intersect property lines at not less than a 75-degree angle. (c) Street names. Street names shall require the approval of the public works department. Streets that are obviously in alignment with streets already in existence and already named shall be given the name of the existing street. Names of new streets shall not duplicate or closely approximate those of existing streets. (d) Street jogs. Street jogs with centerline offsets of less than 200 feet shall not be permitted. (e) Cul-de-sacs. Unless otherwise approved, all dead-end streets shall terminate in a cul-de-sac and shall meet the following requirements: (1) Cul-de-sacs on streets longer than 150 feet shall have an outside pavement radius of at least 48 feet and the property line radius shall be at least 58 feet. (2) In commercial and industrial developments, an outside pavement radius of at least 90 feet and a property line radius of at least 100 feet unless directed otherwise by the fire marshal. (3) A continuous ten foot utility and drainage easement is also required outside of the right-of-way for all cul-de-sacs. (4) Cul-de-sac length should generally not exceed 750 feet but may be longer with the concurrence of city staff. (5) In cul-de-sacs, minimum grade shall be determined by the length of the curb line rather than the length of the centerline. (f) Development along major street, limited access highway or railroad right-of-way. Where a subdivision abuts or contains an expressway, freeway, arterial or collector street, or a railroad right-of-way, the planning commission may require a street approximately parallel to and on each side of such right-of-way, either as a marginal access street, or at a distance suitable for an appropriate use of intervening land, with a non-access reservation suitably planted. Due regard should be given requirements for approach grades and future grade separations in determining distances. Lots shall have no access to expressways, freeways or arterial or collector streets, but only to an accessible street in which case the planning commission may require double frontage lots. (g) Access lanes. The requirements for providing access lanes within a subdivision are as follows: (1) They shall not be provided in residential developments unless the subdivider provides evidence satisfactory to the planning commission of their need. (2) They may be provided at the rear of all lots intended to be used for commercial purposes. (3) They shall be generally parallel to the streets, shall not be less than 20 feet wide and shall be paved according to city design standards. (4) Right-of-way shall not be dedicated to the public. (5) Where two access lanes intersect, a triangular flair of not less than 20 feet from the normal intersection of the property line shall be provided along each property line. (6) Dead-ends shall be prohibited. (h) Reserve strips and easements. (1) Reserve strips may be implemented to control vehicular access to and physical access to public or private utilities to all unplatted property or properties which abut onto a dedicated public or private street. Said reserve strip shall be five feet in width and contained within the public or private street right-of-way or easement and shall not be removed until such time as the adjacent unplatted property or properties are platted, approved by the Dothan Planning Commission and duly recorded in the office of the county probate judge of the appropriate county. (2) The planning commission may require easements for access, poles, wires, conduits, storm sewers, sanitary sewers, gas lines, water lines or other utility lines along all rear lot lines, and alongside lot lines as determined necessary by the public works director. The minimum width needed for easements shall be determined by the design engineer in accordance with the utility which is involved and shall be approved by the public works director for each specific subdivision. In no case, however, shall the width of a public easement be less than 20 feet and further, where multiple utilities are located within an easement, ten additional feet shall be added for each utility unless otherwise approved by the public works director. (3) Medians or islands located in the right-of-way may be permitted as part of the approved subdivision design. Maintenance shall be the responsibility of the developer or homeowners association. Fences or perimeter walls installed by the developer shall be the responsibility of the developer or a homeowners association. Underdrain pipe is required back of the curb on both sides of the median island for any island that is sprinkled or will be. Median islands shall be designed with pavement breaks to enable easy access all lots affected by said median islands. Turning radius for boats, RVs, trailers and other tow-behind vehicles shall be considered during design. (i) Auxiliary lane requirements. In order for the internal subdivision streets and the adjacent existing roadways to operate safely and efficiently, it is necessary to evaluate the need for channelization of traffic movements, especially at major un-signalized intersections. The warrants outlined here shall be followed for un-signalized intersections that provide access to new subdivisions or developments and for major un-signalized intersections internal to the subdivision or development. The warrants apply both to subdivisions and developments that require a Traffic Impact Study (TIS), and to those that do not. Please note that left and right turn lanes can be required by the public works director even if the proposed development generates a lower turning volume than shown below in Table 1 and Table 3. These turn lanes may be required to mitigate traffic concerns (i.e. roadway capacity or safety), or if there are other traffic specific problems aggravated by the proposed development. If a turn lane is required by the traffic engineer over 500 feet away from the development's entrance, the developer can submit a traffic impact study providing information showing otherwise, approved by the traffic engineer and/or public works director, to remove this requirement. (1) Left turn lane warrants. The methodology presented here applies to all subdivision or development access points where a left turn must be executed from a two-lane roadway to enter the subdivision. The intent is to identify locations where lack of left turn lanes presents a potential safety concern. The need for an exclusive left turn lane can be determined from Table 1 if the following parameters are known: • ADT: The bi-directional average daily traffic on the roadway from which the left turn is executed. If a TIS for the subdivision is not available, ADT can be obtained from the City of Dothan Traffic Engineering Division if traffic counts exist for the roadway. • LT: Number of left turns in the peak hour ( PH ). If a TIS for the subdivision is not available, the number of left turns can be estimated based on the number of trips generated by the subdivision or development in the peak hour (using the trip generation rate from the current edition of the Trip Generation Manual) divided by the number of access points where left turns are (or will be) permitted, as shown in the following equation: LT = 0.5 Trip Generation PH. /Access Pts For residential subdivisions the equation simplifies to: LT = 0.5 Dwelling Units/Access Pts • Posted Speed: The posted speed limit on the roadway from which the left turn is executed. Table 1 shows the maximum number of left turn movements allowed in the peak hour without a dedicated left turn lane. If those values are exceeded for any ADT and speed combination, a left turn lane shall be provided. Table 2 shows the minimum left-turn approach and bay taper lengths. An exclusive left turn lane will also be required regardless of the size of the subdivision or development, if an access point to the subdivision is located in an area where sufficient stopping sight distance is not provided on the major roadway. If the roadway shoulders or any pedestrian or bicycle facilities are affected by the addition of a left turn lane they must be replaced. The minimum storage length required for the lane must comply with the requirements in the City of Dothan turn lane specifications. Table 1. Maximum left turn volume in the peak hour without a left turn lane ADT (2-way) Posted Speed (mph) | <2,500 | 2,500—5,000 | 5,000—10,000 | >10,000 ≤35 | 75 | 50 | 30 | 15 40—50 | 75 | 40 | 20 | 10 ≥55 | 75 | 30 | 10 | 5 Table 2. Minimum Left-Turn Approach and Bay Tapers Design Speed (mph) | Approach 1 (in feet) | Approach 2 (in feet) 25 | 125 | 100 30 | 180 | 120 35 | 245 | 140 40 | 320 | 160 45 | 405 | 180 50 | 500 | 200 55 | 605 | 220 60 | 720 | 240 (2) Right turn lane warrants. The methodology presented here applies to all subdivision or development access points where a right turn must be executed from a roadway to enter the subdivision. The intent is to identify locations where the lack of right turn lanes presents a potential safety concern. The need for an exclusive right turn lane can be determined from Table 3 if the following parameters are known: • ADT: The bi-directional average daily traffic on the roadway from which the right turn is executed. If a TIS for the subdivision is not available, ADT can be obtained from the City of Dothan Traffic Engineering Division if traffic counts exist for the roadway. • RT: Number of right turns in the peak hour. If a TIS for the subdivision is not available, the number of right turns can be estimated based on the number of trips generated by the subdivision or development in the peak hour (using the trip generation rate from the current edition of the Trip Generation 4 Manual) divided by the number of access points where right turns are (or will be) permitted, as shown in the equation below: RT = 0.5 Trip Generation PH /Access Pts For residential subdivisions the equation simplifies to: RT = 0.5 Dwelling Units/Access Pts Table 3 shows the maximum number of right turn movements allowed in the peak hour without a dedicated right turn lane. If those values are exceeded, a right turn lane shall be provided. Table 4 shows the length of lanes and tapers for right-turn lanes. Table 3. Peak Hour Volume Warrant for Right Turn Lanes ADT (2-way) | Max. Peak Hour Right Turn Volume (w/o RT Lane) 2,500—5,000 | 100 5,000—10,000 | 70 >10,000 | 40 Table 4. Speed Change Lane Lengths for Right-Turn Lanes Stop Condition | 15 mph Turn Design or Posted Speed (mph) | Accel | Decel | Accel | Decel | Minimum Acceleration Lane Taper Ratio | Minimum Deceleration Lane Taper Ratio 25 | 100 | 200 | 90 | 150 | 7.5:1 | 7.5:1 30 | 190 | 235 | 190 | 185 | 10:1 | 8:1 35 | 270 | 275 | 240 | 235 | 12.5:1 | 10:1 40 | 380 | 315 | 320 | 295 | 15:1 | 11.5:1 45 | 550 | 375 | 480 | 350 | 17.5:1 | 13:1 50 | 760 | 435 | 700 | 405 | 20:1 | 15:1 55 | 960 | 485 | 910 | 450 | 22.5:1 | 18.5:1 (3) Auxiliary lanes sample calculation. • Given the following information, determine the need for dedicated left turn and right turn lanes: • Turns made from a two lane collector roadway. • Posted speed: 40 mph. • ADT on collector roadway: 8,000 vehicles/day. • 150 single-family residences. • Two access points. To calculate LT and RT: LT = RT = (0.5×150)/2 = 38 To evaluate need for left turn lane: Reading in Table 3 for ADT between 5,000 and 10,000 and posted speed of 40, the maximum number of left turns allowed in the peak hour is 20. Since LT (38) > 20, a left turn lane IS warranted (at each access point). To evaluate need for right turn lane: Reading in Table 3 for ADT between 5,000 and 10,000 and posted speed of 40, the maximum number of right turns allowed in the peak hour is 70. Since RT (38) < 70, a right turn lane IS NOT warranted.
(Res. of 7-19-17; Res. of 6-20-18)
Ask a question about Dothan law
Corpus searches the Dothan sections it holds and shows the ones that match, with their citations. Free, no sign-in.