9.32.03 - Materials and methods for constructing excavations and fills, pipe culverts and storm sewers, catch basins, drop inlets and junction boxes and other structures.
A. Materials. 1. Fills. Materials used in the construction of compacted fills for storm sewers and other drainage facilities shall be composed of earth, sand, gravel, or other suitable material meeting the approval of the city engineer. 2. Pipe. Pipe used in the construction of culverts and storm sewers, shall be reinforced concrete or bituminous coated corrugated metal pipe or pipe arch with paved invert. a. Reinforced Concrete Pipe. Reinforced concrete pipe shall conform to ASTM Designation C76. b. Bituminous Coated Corrugated Metal Pipe or Pipe Arch with Paved Invert. Bituminous coated corrugated metal pipe or pipe arch with paved invert shall be Armco Standard or equal, and shall meet requirements for H-15 truck loading plus impact. 3. Rings and Covers and Grates and Frames. Cast iron shall be of good quality and of such character that it shall make the metal of the castings strong, tough, and of even grain. All castings shall be smooth, free from scale and cracks and other defects that might render them unsuitable for the use for which they are intended. a. Rings and Covers. Rings and covers shall be of two (2) main types: sidewalk and street type. The combined weight of the standard sidewalk type shall be approximately one hundred twenty-five (125) pounds, total, and the standard combined weight of the street type shall be approximately two hundred fifty (250) pounds total. 4. Portland Cement Concrete for Appurtenances. Portland Cement concrete for appurtenances shall have a minimum compressive strength of not less than two thousand (2,000) pounds per square inch in twenty-eight (28) days. Its maximum slump in place shall not exceed four (4) inches. Concrete shall be mixed in accordance with current ASTM requirements. B. Methods. 1. Excavation and Fills; Pipe Culverts and Storm Sewers. All excavation shall be carried to an elevation where foundation materials are satisfactory to the engineer, regardless of elevations shown on the plans. Pipe culverts and storm sewers shall be placed either by hand or by mechanical means, and shall be laid and backfilled as specified herein. a. Forming Bed for Pipe. Where pipe is laid below the ground line, the trench shall be excavated to the required depth and the minimum width practicable for the existing working conditions. The bottom of the trench shall be shaped to conform to the bottom of the pipe, and to afford a uniform bearing throughout its entire length. Recesses shall be excavated to receive the bells where bell and spigot pipe is used. When rock is encountered in the trench, it shall be removed to a minimum depth of six (6) inches below the pipe, and this excess depth shall be refilled with suitable material and stabilized. Where pipe is not laid in a trench, a uniform, firm bed shall be made as specified above. b. Laying the Pipe. Pipe culverts and storm sewers shall be laid to the lines and grades established by the engineer, with the hubs and bells upgrade. Spigot ends shall be fully entered into the adjacent hubs or bells. All joints shall be cemented with a ratio of 1:3 Portland cement mortar. The insides of all joints shall be wiped and finished smooth. When corrugated metal pipe or pipe arch sections are used, they shall be joined with a band made of the same material as the pipe. Any pipe which is not in true alignment or which shows settlement after laying shall be taken up and re-laid by the contractor. c. Backfilling. The material used for backfilling pipe culverts and storm sewers under any improvement shall be at optimum moisture, and shall be free from large lumps, clods or rocks, and it shall be placed alongside the pipe culverts or storm sewers in layers of approximately eight (8) inches and thoroughly compacted to an elevation equal to the spring line of the pipe. Subsequent layers of backfill material shall be placed uniformly over the contour of the pipe in layers not to exceed eight (8) inches, and shall be compacted for the entire depth of the trench. Backfill compaction by puddling or jetting with water shall not be permitted unless it is non-plastic materials. 2. Catch Basins, Drop Inlets, and Junction Boxes. Concrete floors for catch basins, drop inlets and junction boxes shall be poured at least twenty-four (24) hours prior to beginning construction on the walls. Floors shall be constructed to the full outside dimensions indicated in the plans. Walls shall be so constructed as to form a tight joint with the floor and around all inlets and the outlet pipes. Walls may be constructed of reinforced concrete meeting current ASTM requirements or concrete blocks laid and filled with concrete, as required by the engineer.
(Ord. No. A-584, Sec. 3)