§ 112-107 — Floodplain development permit
Code of Ordinances of the City of Jonesboro, Arkansas (Codified through Ordinance No. 25:028, enacted September 2, 2025. (Supp. No. 16)) · Jonesboro City Code § 112-107
Corpus is an independent public-information project, not the official City of Jonesboro website. Stable reference: corpuslaw.us/code/950976ed-8fdf-44f4-900b-c0755c2b1a8b
Sec. 112-107. - Floodplain development permit.
(a) Preparation. Application for a floodplain development permit shall be made by the developer on forms prescribed by the city engineer and made available through the city planning office. (b) Submission. The developer shall submit two copies of the application and all supporting documentation to the city planning office along with the review fee as established by the city council. Upon receipt, the planning office will forward the submittals to the city engineer for review. (c) Plan review. (1) The city engineer or his designated representative shall review the submittals for conformance to the city minimum design standards as established in these regulations and in the Stormwater Drainage Design Manual. (2) The city engineer will review and comment or approve the project submittals within 15 business days upon receipt. Failure of the city engineer to meet this timeline shall not be considered approval of the proposed work. (d) Rejection. (1) If it is determined that the proposed development is not in accordance with these regulations, a comment letter listing the deficiencies shall be issued to the developer for response. Re-submittals shall be made to the city planning office. (2) If needed, an informal meeting between the developer and the city engineer or his designee may be scheduled by either party to review the overall concepts included in the plan. The purpose of this meeting may vary, but generally shall be to jointly agree upon an overall stormwater management concept for the proposed development and to review criteria and design parameters which shall apply to the project. (e) Acceptance. (1) If it is determined that the proposed development is in accordance with these regulations, a compliance letter shall be issued to the developer stipulating the conditions of approval which are: a. The engineering department relied upon statements and representations made in the floodplain development application. In case any statement or representation in the aforementioned documents is found to be incorrect, then the approval may be revoked; b. There shall be no deviations from the approved plans and specifications unless revised plans and specifications have been first submitted for review and written consent given amending the compliance letter; c. The review of the plans and specifications are for conformance to city minimum design standards and in no way constitute an analysis of the hydraulic or structural design; and d. If construction of this project is not started within one year from the date of approval, then the approval is terminated. (2) Other conditions of approval may be added by the city engineer as needed, as long as the added conditions are consistent with these regulations.
(Ord. No. 08:099, § 2(3.5), 12-18-2008)
Ask a question about Jonesboro law
Corpus searches the Jonesboro sections it holds and shows the ones that match, with their citations. Free, no sign-in.