§ 12.10.130 — Construction, inspection and completion of street improvement requirement

Fremont Municipal Code (Fremont Municipal Code current through Ordinance 02-2026 passed May 5, 2026 (Code Publishing Company, codepublishing.com, scraped 2026-11-18)) · Fremont Municipal Code § 12.10.130

Corpus is an independent public-information project, not the official City of Fremont website. Stable reference: corpuslaw.us/code/d82fdacf-5d82-4616-88ab-dc9668afd4f0

12.10.130 Construction, inspection and completion of street improvement requirement.

(a) Prerequisites to Commencement of Construction. Prior to the commencement of construction of street improvements required pursuant to an agreement executed pursuant to the provisions of this chapter, the lot user shall obtain or cause to be obtained by his/her contractor or other agent, from the public works director, any encroachment or other permit required pursuant to this code as a condition to the occupation and construction within rights-of-way and streets. If construction plans for the street improvements have been deferred in whole or in part pursuant to Section 12.10.110(d), such construction plans shall be submitted for approval of the public works director prior to the issuance of any such permit and before commencement of construction. (b) Inspection by City During Construction. The construction of street improvements required pursuant to this chapter shall be subject to inspection by the public works director during the progress of such construction in accordance with policies and practices established by the director in connection with any such work. Certification of partial completion during the progress of construction for the purposes of partial release of improvement security shall be subject to the provisions of Section 12.10.120(c). (c) Final Inspection and Certification of Completion. When the lot user or his/her contractor or other agent has determined that the street improvements required to be constructed pursuant to an agreement executed pursuant to this chapter have been completed, the lot user or agent shall inform the public works director of such determination and request a final inspection of the completed street improvements. Upon such request, or upon his/her own determination, the public works director shall make a final inspection and, if he/she finds that the full extent of the required street improvements have been completed pursuant to the agreement and the approved construction plans therefor, he/she shall promptly transmit to the lot user and to the city clerk a certification of such completion. If the public works director finds, upon such inspection, that the full extent of the required street improvements have not been completed, he/she shall inform the lot user of the findings of such inspection. (d) “As Built” Improvement Plans. Unless waived in whole or in part by the public works director, a complete improvement plan “as built,” in a form complying with the requirement for such plan required pursuant to the subdivision ordinance, shall be filed with and subject to the approval of the city engineer or public works director upon completion of street improvements required pursuant to an agreement executed pursuant to this chapter. The filing and approval of such “as built” improvement plan shall be a condition to the certification of completion of the street improvements by the public works director and acceptance thereof by the city council. (Ord. 924 § 1, 9-12-72; amended during 2012 reformat. 1990 Code § 8-3112.)

Prior legislation: Ords. 189, 313, 702 and 832.