§ 10-12.09 — CERTIFICATE OF COMPLETION

Hayward Municipal Code (Supp. No. 28, Update 2: codified through Ordinance No. 26-08, adopted August 18, 2026) · Hayward Municipal Code § 10-12.09

Corpus is an independent public-information project, not the official City of Hayward website. Stable reference: corpuslaw.us/code/d12c1cc3-b6eb-4bc1-8374-d4767cd9af2d

SEC. 10-12.09 - CERTIFICATE OF COMPLETION.

(a) The Certificate of Completion (see Appendix C) shall include the following seven (7) elements: (1) project information sheet that contains: (A) date; (B) project name; (C) project applicant name, telephone, and mailing address; (D) project address and location; and (E) property owner name, telephone, and mailing address; (2) certification by either the signer of the landscape design plan, the signer of the irrigation design plan, or the licensed landscape contractor that the landscape project has been installed per the approved Landscape Documentation Package; (A) where there have been significant changes made in the field during construction, these "as-built" or record drawings shall be included with the certification; (B) a diagram of the irrigation plan showing hydrozones shall be kept with the irrigation controller for subsequent management purposes. (C) irrigation scheduling parameters used to set the controller; (D) landscape and irrigation maintenance schedule (see Section 10-12.10); (E) irrigation audit report (see Section 10-12.11); and (F) soil analysis report, if not submitted with Landscape Documentation Package, and documentation verifying implementation of soil report recommendations (see Section 10-12.06); and (G) landfill diversion verification statement (see Appendix C. Part 7) (b) The project applicant shall: (1) submit the signed Appendix C - Certificate of Completion to the City for review; (2) ensure that copies of the approved Certificate of Completion are submitted to the property owner or his or her designee. (c) The City shall: (1) receive the signed Appendix C - Certificate of Completion from the project applicant; (2) perform a verification field inspection by City Landscape Architect upon receipt of the Certificate of Completion prior to issuance of Certificate of Occupancy. If the inspection fails, City Landscape Architect shall provide a correction list to the project applicant.

Ask a question about Hayward law

Corpus searches the Hayward sections it holds and shows the ones that match, with their citations. Free, no sign-in.