§ 14.12.100 — Timely Commencement and Prosecution of the Work
Municipal Code of the City of San Marcos, California (Codified through Ordinance No. 2026-1582, enacted September 22, 2026. (Supp. No. 14)) · San Marcos Municipal Code § 14.12.100
Corpus is an independent public-information project, not the official City of San Marcos website. Stable reference: corpuslaw.us/code/0001ee4e-7df7-4445-9465-2b0e5ea2de31
14.12.100 - Timely Commencement and Prosecution of the Work.
(a) The Director may cancel a Permit unless the work is commenced within 60 days of the issuance thereof and thereafter, in the opinion of the Director, is diligently prosecuted to completion. (b) Any Permit is automatically rendered null and void if work is not started six months after date of issuance. (c) The Applicant shall prosecute with diligence and to the satisfaction of the Director all work covered by the Permit. (d) The Applicant shall promptly complete such work restoring the street or Public Place as near as possible to its original condition not later than 48 hours after the original cut, unless extended by the Director. (e) The permanent completion of the Excavation work shall be completed not later than 30 calendar days after the original street cut.
(Ord. No. 2003-1196, 8-26-03; Ord. No. 2022-1521, § 2, 9-13-2022)
Ask a question about San Marcos law
Corpus searches the San Marcos sections it holds and shows the ones that match, with their citations. Free, no sign-in.