§ 20.255.090 — Duties and Responsibilities of the Floodplain Administrator
Municipal Code of the City of San Marcos, California (Codified through Ordinance No. 2026-1582, enacted September 22, 2026. (Supp. No. 14)) · San Marcos Municipal Code § 20.255.090
Corpus is an independent public-information project, not the official City of San Marcos website. Stable reference: corpuslaw.us/code/b419e107-9e98-4ace-ae53-1d9b49ae62b4
Section 20.255.090 - Duties and Responsibilities of the Floodplain Administrator
The Floodplain Administrator (i.e., City Engineer) shall have the duties and responsibilities to do the following: A. Permit Review. 1. Review all development permits to determine that the permit requirements of this chapter have been satisfied, including determination of substantial improvement and substantial damage of existing structures. 2. Ensure that all other required state and federal permits have been obtained. 3. Ensure that the site is reasonably safe from flooding. 4. Ensure that the proposed development does not adversely affect the carrying capacity of areas where base flood elevations have been determined but a floodway has not been designated. For purposes of this chapter, "adversely affect" means that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than one (1) foot at any point within the City or adjacent communities. 5. Ensure that all Letters of Map Revision (LOMRs) for flood control projects are approved prior to the issuance of building permits. Building permits must not be issued based on Conditional Letters of Map Revision (CLOMRs). Approved CLOMRs allow construction of the proposed flood-control project and land preparation, as specified in the "start of construction" definition, found below. B. Development of Substantial Improvement and Substantial Damage Procedures. 1. The cost of replacement of a damaged structure shall be based on a square-foot cost factor determined by reference to a building-cost estimating guide recognized by the building construction industry. 2. The amount of depreciation shall be determined by taking into account the age and physical deterioration of the structure, and functional obsolescence as approved by the Floodplain Administrator, but shall not include economic or other external ways to determine obsolescence. Use of replacement costs or accrued depreciation factors different from those contained in recognized building cost estimating guides may be considered only if such factors are included in a report prepared by an independent professional appraiser and supported by a written explanation of the differences. C. Review, Use, and Development of other Base Flood Data. When base flood elevation data has not been provided in accordance with this chapter, the Floodplain Administrator will obtain, review, and reasonably use any base flood elevation and floodway data available from a federal or state agency, or other source, to administer the regulations in this chapter. A base flood elevation shall be obtained using one (1) of two (2) methods from the FEMA publication, FEMA 265, "Managing Floodplain Development in Approximate Zone A Areas - A Guide for Obtaining and Developing Base (100-year) Flood Elevations," dated July 1995. D. Notification of Other Agencies. When any of the following occur, the described actions shall be carried out. 1. Alteration or relocation of a watercourse: a. Notify adjacent communities and the California Department of Water Resources prior to any alteration or relocation of a watercourse. b. Submit evidence of such notification to the Federal Insurance Administration. c. Ensure that the flood carrying capacity within the altered or relocated portion of said watercourse is not diminished. 2. Base flood elevation changes due to physical alterations: a. Within six (6) months of information becoming available or project completion, whichever comes first, the Floodplain Administrator shall submit or ensure that the permit applicant submits technical or scientific data to FEMA for an LOMR. b. All LOMRs for flood control projects shall be approved prior to the issuance of building permits. Building permits must not be issued based on CLOMRs. Approved CLOMRs allow construction of the proposed flood control project and land preparation as specified in the "start of construction" definition, found below. Such submissions are necessary so that, upon confirmation of those physical changes affecting flooding conditions, risk premium rates and floodplain management requirements are based on current data. 3. Changes in corporate boundaries: Notify FEMA in writing whenever the corporate boundaries have been modified by annexation or other means, and include a copy of a map of the community that clearly delineates the new corporate limits. E. Documentation of Floodplain Development. Obtain and maintain for public inspection and make available as needed the following: 1. Certification required by Sections 20.255.110.C.1 (Elevation and Floodproofing) and 20.255.140 (Standards for Manufactured Homes within Manufactured Home Parks or Subdivisions) 2. Certification required by Section 20.255.110.C.2 (Elevation and Floodproofing) 3. Certification required by Section 20.255.110.C.3 (Elevation and Floodproofing) 4. Certification of elevation required by Section 20.255.130.A.3 (Standards for Subdivisions and Other Proposed Development) 5. Certification required by Section 20.255.160.B (Floodway) 6. Maintain a record of all variance actions, including justification for their issuance, and report such variances in the biennial report submitted to FEMA F. Map Determination. Make interpretations, where needed, concerning the exact location of the boundaries of the areas of special flood hazards or areas of mudslide (i.e., mudflow) where there appears to be a conflict between a mapped boundary and actual field conditions. The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation, as provided in Chapter 20.500 (Permits and Applications Process). G. Remedial Action. Take action to remedy violations of this chapter as specified in Section 20.255.040 (Compliance). H. Biennial Report. Complete and submit a biennial report to FEMA. I. Planning. Ensure that the City's General Plan is consistent with the floodplain management objectives herein.
Ask a question about San Marcos law
Corpus searches the San Marcos sections it holds and shows the ones that match, with their citations. Free, no sign-in.