Sec. 33-32. - Same—Requirements.

(a) Before issuing an excavation permit, the director shall require a written application on a form furnished by the director, setting forth: (1) The name and residence or business address of the applicant; (2) The location and approximate area of the excavation, including its approximate length and width, and, if the excavation is in a street, whether it is parallel or transverse to the direction of the travel lanes; (3) The purpose of the excavation; (4) The proposed start date of excavation and duration of the excavation; (5) A current business license issued by the City of Santa Ana. (6) Evidence of insurance as required by section 33-32.19. (7) A traffic control plan to be approved by the city traffic engineer. (8) The applicant shall attach to the application form a scaled plan per director's requirement showing the location of the proposed excavation, the method of excavation, the facilities to be installed, to be maintained or repaired in connection with excavation, the dimensions thereof, and any other details the director may require. The director may establish different requirements for blanket permits issued under section 33-32.13 of this chapter. (b) At the time the permit is issued, the applicant shall pay a nonrefundable fee in an amount established by resolution of the city council to defray the city's costs to process the application and to inspect the excavation. (c) Except for requirements subject to the exclusive jurisdiction of another regulatory agency, the location, depth and other physical characteristics of any facilities for which an excavation permit is issued shall be subject to approval of the director, and all backfilling, compaction and pavement restoration performed for any excavation shall comply with the requirements of the director. (d) In the event that relocation is required by the city to accommodate a proper governmental use of the street, alley, sidewalk or other public place, no fee or requirement authorized or imposed pursuant to this chapter shall be construed to affect or alter in any way any obligation of the public and private utilities with facilities installed in any street, alley, sidewalk or other public place to relocate the facilities at no cost to the city.

Ask a question about Santa Ana law

Corpus searches the Santa Ana sections it holds and shows the ones that match, with their citations. Free, no sign-in.