Sec. 33-32.6. - Opening, backfilling and paving trenches.
(a) No trench shall be opened in any street for the purpose of laying pipes, conduits or ducts more than four hundred (400) feet in advance of the pipe, conduit or ducts being placed in the trench, except when the prior written consent of the director has been obtained. (b) Each permittee shall cover open excavation with non-skid surface steel plates ramped to the elevation of the contiguous street, pavement or other public right-of-way or otherwise protected in accordance with guidelines prescribed by the department. (c) All excavations shall comply with the standards and requirements established by the director for compaction, backfill and pavement restoration. The standards and requirements may impose different requirements for different excavations, taking into consideration relevant factors, such as (i) the location, type and extent of excavation performed (ii) the condition of the surface being excavated, (iii) the period of time elapsed since the construction or most recent resurfacing of the surface being excavated, and (iv) the average daily traffic volume and truck volume. Permanent pavement restoration shall be completed no later than two (2) weeks after the trench is backfilled; provided, however, that the director may grant an extension depending on the complexity of the work and testing which is demonstrated to be necessary to get the utility in service. (d) The old torn up pavements and other rubble shall be removed, together with any surplus excavated material, within one (1) working day from the time such material is placed upon the street, provided that exceptions to this requirement may be approved by the director. After backfilling is completed, and prior to repaving the cut, the contractor or permittee shall remove all loose paving material and trim the edges of the excavation at the street surface to the satisfaction of the director. (e) Whenever any caving in the sidewalls of any excavation, the pavements above such caving shall be cut away. In no case shall any void under a pavement be filled by any side or lateral tamping.
(Ord. No. 2447, § 6, 10-2-00)
Ask a question about Santa Ana law
Corpus searches the Santa Ana sections it holds and shows the ones that match, with their citations. Free, no sign-in.