§129.0205 Deferred Submittals of Required Building Permit Application Materials

Before issuing a Building Permit, the Building Official may allow deferral of submittal documents relating to a specific portion of the design. (a) The Building Official shall specify a maximum time period for submittal of the deferred documents. The Building Permit for the non-deferred portions may be issued and construction may start on the non-deferred portions of the work, before the deferred submittals are submitted. (b) The registered and responsible design professional shall list the deferred submittals on the construction documents for review by the Building Official. (c) The registered and responsible design professional shall review the deferred submittal documents and submit them to the Building Official, with annotation indicating that the deferred submittal documents have been reviewed and found to be in general conformance to the design of the building. (d) The deferred submittal items shall not be installed until their design and submittal documents have been approved by the Building Official.

(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.) (Amended 4-6-2016 by O-20624 N.S.; effective 5-6-2016.)