9-14-28. - Facade Materials.

(a) Intent. The intent of the facade materials standards of this section is to: (1) Provide minimum material standards to ensure use of well-tested, high quality, durable, weather-resistant, exterior grade, preferably natural materials on the majority of finished surfaces, while permitting a wider range of materials for details. High quality materials can improve quality of buildings in that they weather well, have a low failure rate, require a low level of maintenance, and create buildings with a longer life cycle and a sense of permanence; (2) Limit the number of facade materials to promote simpler, clearly articulated facades; and (3) Encourage a high level of detail from smaller scaled, less monolithic materials in order to relate facades to pedestrians, especially at the ground level. (b) Major Materials. The major material requirements of this section may be met only with materials listed as allowed major facade materials in Table 14-8, "Allowed Major Facade Materials," for the relevant form-based code area. See Figure 14-59. Examples of Allowed Facade Materials. (1) Type A Frontages. A minimum of eighty percent of each Type A frontage facade, not including window and door areas, shall be composed of major materials, as specified in this section. (2) Type B and C Frontages. A minimum of sixty percent of each Type B and C frontage facades, not including window and door areas, shall be composed of major materials, as specified in this section. (3) Simplicity of Surface Materials. To meet the major façade materials requirements of this section, a minimum of sixty percent of each Type A, B, and C facade, not including window and door areas, shall be faced of a single major material. In Boulder Junction I and Alpine-Balsam, architectural metal panel systems shall not be used to meet this standard. (4) Corners of Buildings. Where Type A, B, or C facades are located perpendicular to a rear, interior side, or rail corridor facade, the major materials on the Type A, B, or C facade shall be continued around the corner along the perpendicular facade for a minimum of thirty feet. (c) Prohibited Materials. The materials listed in Table 14-11, "Prohibited Materials," are prohibited on any building facade. See Figure 14-60. Examples of Prohibited Facade Materials. (d) Minor Materials. Minor materials may be installed on the remaining facade areas of the building not required to meet major material requirements. Minor materials are materials listed as allowed minor facade materials in Table 14-9, "Allowed Minor Facade Materials," for the relevant form-based code area. (e) Details and Accents. Detail and accent materials listed in Table 14-10 may be installed as a detail or accent on any facade. The approving authority may allow other details and accent materials that are similar in quality and durability to those listed in Table 14-10, "Allowed Detail & Accent Materials." (f) Solar Panels. Where solar panels are mounted on any facade, any major or minor facade material may be used on that facade, provided the material is not visible through the panels.

![Source table](https://figures.74-208-44-221.nip.io/boulder/496676/c4885b5386c9da3ca9f817efc879865c213da837649ff76cd13e237e48f324ba.png)

![Source table](https://figures.74-208-44-221.nip.io/boulder/496676/0cb4ef78859db5661c0c6b0884b87ca94ab0193a00fd0d80f7870faabac92902.png)

| | | --- | | TABLE 14-10. ALLOWED DETAIL & ACCENT MATERIALS | | All allowed major and minor facade materials may be used for details, trim, and accents. | | Concrete Details precast stone ornamentation, lintels, sills, banding, columns, beams | | Fiber Cement Details trim, soffits | | Metal Details trim, ornamentation, lintels, beams, columns | | Wood and Wood Composite Details painted/treated trim, soffits, other approved details | | Vinyl Details limited to soffits, window trim; minimum .04 inches thick | | Fiberglass and Acrylic Panels all | | Plastic Panels all, including high-density polyethylene, polyvinyl chloride (PVC), and polycarbonate panels | | Stucco or Synthetic Stucco Moldings & Assemblies trim, sills, cornices, banding, columns, pilasters or other 3-dimensional decorative details | | Synthetic Stucco Surfaces all | | Vinyl & PVC Siding all | | Wood unfinished, untreated plywood siding or panels |

![Figure 14-59. Acceptable Materials](https://figures.74-208-44-221.nip.io/boulder/496676/db563dbbeff67ae1b65997d753d5fc9beadc291d989e04b7b30ad27a0b2ccf5f.png)

Figure 14-59. Acceptable Materials

![Figure 14-60. Unacceptable Major Materials](https://figures.74-208-44-221.nip.io/boulder/496676/79e592563ab1af7b5e68bb2ab1b149b6ff9b89f3c61c329776ee005a67625f7b.png)

Figure 14-60. Unacceptable Major Materials (g) Other Materials with Approval. Materials that are not listed in this section for its proposed application as an allowed major material or allowed minor material may not be installed on any facade unless approved by the approving authority pursuant to this subsection (d). (1) The approving authority may approve facade materials that are not listed in this section for its proposed application if the applicant demonstrates the material in its proposed application meets the intent of the facade material standards described in subsection (a) of this section. Samples and examples of successful high quality local installation shall be provided by the applicant. Ordinance No. 8669 (2025)