Sec. 26-475. - Nonresidential electric development fees and charges.

(a) An Electric Capacity Fee ("ECF"), calculated as set forth in this Section and representing the cost to construct the electric distribution system infrastructure for a new or modified nonresidential service shall be paid prior to the scheduling of any construction work required to provide such service. The ECF shall be determined based on the amps for each proposed meter, calculated individually then aggregated, and the ECF charges in effect at the time of full payment. The customer shall also be responsible for secondary service installation from the point of delivery to the service panel. In the event of a customer request for revision to the system requirements for a new or modified service, construction of infrastructure improvements will cease until the customer has made payment in full of an updated ECF, including any increased construction costs associated with the revised system requirements; such increased amount, if any, shall be paid at the ECF rates in effect at the time it is paid in full. (b) The ECF shall be the total of the kVA service charge and systems modification charge, to be determined as follows: (1) The kVA service charge shall be determined as follows. a. For customer electric loads served by the utility, the kVA service charge shall be calculated as follows: ECF shall be calculated as follows: secondary metered services | $/kW = $465.52 + $29.76 x ln(kW) primary metered services | $/kW = $309.69 + $8.09 x ln(kW) Where ln is the natural logarithm kW is calculated as follows: three phase services | kW = A x V x SQRT(3) x PF x 0.3/1000 single phase services | kW = A x V x PF x 0.3/1000 Where A is the requested amperage, calculated individually and aggregated under subsection (a) above. V is requested line to line voltage. PF is the power factor, which is assumed to be 0.9. (2) A system modifications charge will apply when a new or modified service will require infrastructure in addition to or different from the standard base electrical system model. The differential costs associated with such system modifications will be included in the calculated ECF. (c) The utility will schedule and commence construction of a new or modified electric service upon receipt of payment in full of the associated electric development fees, and per the Utility Installation Sequence as defined in the Electric Service Standards. If the utility is unable to commence construction when requested due to utility workload backlogs, the utility will schedule and commence the construction of new or modified electric service projects in the same order in which full payments are received. (d) A Building Site Charge ("BSC") for extending primary circuitry to the transformer for any new or modified nonresidential service shall be invoiced and paid in the same manner and at the same time as the ECF is invoiced and paid pursuant to § 26-475(a). The BSC shall be the total of the primary circuit charge, transformer installation charge and any additional charges, based on the actual cost of construction, labor, materials, and equipment reasonably related to and required in providing electric services to the nonresidential site. The BSC shall be reviewed and adjusted as provided in Section 26-473(b). Actual special costs to the utility of installation of service resulting rom site conditions shall be included in the BSC as additional charges. Such conditions may include, but are not limited to, frozen or rocky soil, concrete cutting and asphalt replacement. (e) In lieu of the ECF and BSC based on Subsections (a), (b), and (d), the ECF and BSC for any new nonresidential service exceeding five thousand (5,000) kilowatts in size will be determined on a case-by-case basis so as to recover the direct and indirect costs associated with extending primary circuitry to the user's point of delivery.

(Ord. No. 154, 2003, § 12, 11-18-03; Ord. No. 135, 2005, § 3, 11-15-05; Ord. No. 175, 2006, § 2, 11-7-06; Ord. No. 123, 2007, § 2, 11-20-07; Ord. No. 113, 2008, § 2, 10-21-08; Ord. No. 118, 2009, § 2, 11-3-09; Ord. No. 115, 2010, § 2, 11-16-10; Ord. No. 080, 2011, § 1, 9-6-11; Ord. No. 142, 2011, § 7, 11-1-11; Ord. 143, 2011, § 3, 11-1-11; Ord. No. 114, 2012, § 7, 11-6-12; Ord. 115, 2012, § 2, 11-6-12; Ord. No. 147, 2013, § 2, 11-5-13; Ord. No. 155, 2014, § 2, 11-4-14; Ord. No. 136, 2014, §§ 5—7, 12-2-14; Ord. No. 141, 2015, § 4, 11-17-15; Ord. No. 068, 2017, §§ 4, 5, 6-6-17; Ord. No. 168, 2017, § 2, 12-19-17; Ord. No. 131, 2019, § 4, 11-19-19; Ord. No. 130, 2020, § 3, 11-17-20; Ord. No. 147, 2021, § 3, 11-16-21; Ord. No. 131, 2022, § 3, 11-15-22; Ord. No. 021, 2024, § 2, 2-20-24; Ord. No. 173, 2024, § 2, 12-3-24)