Sec. 86-137. - Non-communications facility permit review criteria.

The following review criteria apply to all applications for an NCF permit: (1) No NCF permit shall be issued to any person who has existing equipment or facilities within the right-of-way requiring city commission approval pursuant to section 6.3.I.2.b. of the Land Development Code, until commission approval is obtained or such equipment or facilities have been removed in compliance with this article. (2) No NCF permit shall be issued where the city manager determines that there is a reasonable likelihood that the activity proposed, or the location of the proposed equipment or facilities within the right-of-way, would create an undue risk to the health, safety, and welfare of the public, such as where the proposed activity may conflict with safe and efficient vehicular or pedestrian use of the travel portions of the right-of-way, including by interfering with sight lines; the existing or planned city or other governmentally-owned structures, including signs and utility infrastructure; or existing utility infrastructure owned by any other public utility provider. (3) No NCF permit required by shall be issued where the city manager determines that there is a reasonable likelihood that the proposed activity would damage public or private property or injure persons. (4) Except in cases of public emergency, no NCF permit shall be issued to any person with an outstanding debt which is due and payable to the city without offset or dispute; or to any person who has existing unpermitted equipment or facilities within the right-of-way, where a permit is required, until such equipment or facilities have been removed in compliance with this article. (5) No NCF permit shall be issued authorizing the construction of equipment or facilities unless: a. The applicant is a public utility provider authorized by state or federal law to locate its facilities in public right-of-way; provided, however, that the public utility provider must have a franchise or license from the city except where prohibited by law; or b. The city commission has approved the encroachment of the facilities or equipment into the right-of-way; or c. The equipment or facilities are limited to at- or below-grade encroachments unassociated with a change of use of the abutting property, where the provisions of this article are adequate to protect the public interest.