§ 14.5-154 — Construction reporting requirements
Code of Ordinances, City of Gainesville, Florida (Supp. No. 64, Update 1: codified through Ordinance No. 2024-740, adopted November 6, 2025) · Gainesville City Code § 14.5-154
Corpus is an independent public-information project, not the official City of Gainesville website. Stable reference: corpuslaw.us/code/31e19791-1776-4047-a999-eee3deb10ca3
Sec. 14.5-154. - Construction reporting requirements.
(a) Schedule of construction. For a major construction or rebuild of its cable system, a grantee shall provide the city with a written progress report detailing work to be done and a schedule for completion of construction. Such report shall include a description of any necessary agreements, licenses, or certifications and any other information the city manager or his designee may reasonably deem necessary. (b) Progress reports. Upon commencement of such major construction or rebuild of a cable system, written progress reports shall be submitted to the city on a monthly basis, unless otherwise agreed by the parties, throughout the entire construction or rebuild process. The reports will designate work completed to date and any changes in the implementation or in the previously submitted proposed construction schedule. (c) Notice of construction to residents. Prior to the commencement of any major construction or rebuild of a cable system, a Grantee shall produce an informational document to be distributed to all residents of the area of the proposed construction, which shall describe the activity that will be taking place. The informational document shall be reviewed and approved by the city manager or designee prior to its distribution. In an upgrade situation, if a customer will be materially impacted, notice will be given.
(Ord. No. 040116, § 2, 7-26-04)
Ask a question about Gainesville law
Corpus searches the Gainesville sections it holds and shows the ones that match, with their citations. Free, no sign-in.