Sec. 27-35. - Installation of underground electrical facilities.
When underground electrical facilities are to be installed, whether required by governmental authority, or at the request of a customer (or developer), the city will, at its expense and in the exercise of its engineering judgment, design the facilities. The cost of including that design in the construction plans and documents of the customer (or developer) shall be borne by the customer (or developer). The customer (or developer), shall then provide and install (or cause to have installed), at their sole expense, all conduit, concrete equipment foundations, and related civil infrastructure required for the installation of the electrical facilities including, but not limited to: primary and secondary voltage electrical systems, services, and lighting systems in accordance with the Energy Delivery Service Guide referenced in section 27-36. Ownership of all customer or developer installed facilities shall be transferred to the city upon acceptance by the city. In addition, the customer (or developer) will pay any "Contribution in Aid of Construction" which the city may require pursuant to section 27-34. Except as provided for by ordinance, the costs associated with utility initiated underground electrical system construction or reconstruction shall be borne exclusively by the utility.
(Ord. No. 3665, § 5, 9-24-90; Ord. No. 3754, § 80, 1-27-92; Ord. No. 980557, § 3, 11-23-98)