Sec. 27-313. - Affirmative defenses to discharge violations.
(a) Upset. (1) An upset does not constitute noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation. An upset shall constitute an affirmative defense to an action brought for noncompliance with pretreatment standards if the requirements of subsection (a)(2) of this section, are met. (2) An industrial user who wishes to establish the affirmative defense of an upset shall demonstrate, through properly signed, contemporaneous logs, or other relevant evidence that: a. An upset occurred and the industrial user can identify the causes of the upset; b. The industrial user's facility was at the time being operated in a prudent and workman-like manner and in compliance with applicable operation and maintenance procedures; and c. The industrial user has orally submitted the following information to the POD within 24 hours of becoming aware of the upset, with a written submission to be provided within five days, including the following information: 1. A description of the indirect discharge and cause of noncompliance; 2. The period of noncompliance, including exact dates and times or, if not corrected, the anticipated time the noncompliance is expected to continue; and 3. Steps being taken and/or planned to reduce, eliminate, and prevent recurrence of the noncompliance. (3) In any enforcement proceeding, the industrial user seeking to establish the occurrence of an upset shall have the burden of proof. (4) The industrial user shall control production or all discharges to the extent necessary to maintain compliance with pretreatment standards upon reduction, loss, or failure of its treatment facility until the facility is restored or an alternative method of treatment is provided. This requirement applies in the situation where, among other things, the primary source of power of the treatment facility is reduced, lost, or fails. (b) Prohibited discharge standards. A user shall have an affirmative defense to an enforcement action brought against it for noncompliance with the prohibitions in section 27-307 if it can prove that it did not know, or have reason to know, that its discharge, alone or in conjunction with discharges from other sources, would cause pass through or interference and that either: (1) A local limit exists for each pollutant discharged and the user was in compliance with each limit directly prior to, and during, the pass through or interference; or (2) No local limit exists, but the discharge did not change substantially in nature or constituents from the user's prior discharge when the City was regularly in compliance with its NPDES permit, and in the case of interference, was in compliance with applicable sludge use or disposal requirements. (c) Bypass. (1) Notice. a. If an industrial user knows in advance of the need for a bypass, it shall submit prior notice to the POD, at least ten days before the date of the bypass. If the industrial user does not know of the need for a bypass ten days prior to the bypass then the industrial user shall notify the POD immediately upon knowledge of the need for the bypass. b. An industrial user shall submit oral notice of an unanticipated bypass that exceeds applicable pretreatment standards to the POD within 24 hours from the time the industrial user becomes aware of the bypass. A written submission shall also be provided within five days of the time the industrial user becomes aware of the bypass. The written submission shall contain a description of the bypass and its cause; the duration of the bypass, including exact dates and times, and, if the bypass has not been corrected, the anticipated time it is expected to continue; and steps being taken or planned to reduce, eliminate, and prevent reoccurrence of the bypass. (2) Exceptions. a. Bypass is prohibited, and the POD may take an enforcement action against a user for a bypass, unless: 1. Bypass was unavoidable to prevent loss of life, personal injury, or severe property damage as defined herein; 2. There were no technically feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate backup equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance; and 3. The user submitted notices as required under subsection (c)(1) of this section. b. The POD may approve an anticipated bypass, after considering its adverse effects, if the POD determines that it will meet the three conditions listed in subsection (c)(2)a. of this section. (3) Allowable bypasses. A user may allow any bypass to occur which does not cause pretreatment standards or requirements to be violated, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to the provision of paragraphs (c)(1) and (2) of this section. (4) User liable for damage. In the event of an unavoidable bypass, the industrial user shall not be relieved of any liability for damage to the POTW.
(Code 1992, § 27-217; Ord. No. 296-G, § 1, 10-7-1997; Ord. No. 345-G, § 8, 9-24-1998; Ord. No. 67-H, §§ 13, 14, 2-21-2013)