§ 12.1.8 — Tree Protection During Construction
Code of Ordinances of the City of Roswell, Georgia (Codified through Ordinance No. 2025-11-10, adopted November 10, 2025. (Supp. No. 17)) · Roswell Unified Development Code § 12.1.8
Corpus is an independent public-information project, not the official City of Roswell website. Stable reference: corpuslaw.us/code/bf7cae62-e847-4430-8a7e-da4fd8442f7e
12.1.8. - Tree Protection During Construction
A. Materials Prohibited in Tree Save Areas. No structure, improvement, or any activity including solvents, material, construction machinery, portable toilets, construction trailers, or temporary soil deposits may encroach or be placed within a drip line or within 6 feet of the area immediately outside the drip line of any specimen tree or any tree within a tree save area unless authorized by the City Arborist in writing. [image omitted; see the official code] B. Tree Protection Devices. Before development, land clearing, filling, or any land alteration, the developer is required to erect suitable protective barriers required by the City Arborist pursuant to an approved tree protection plan, including tree fences, tree protection signs, and erosion barriers. City inspection of tree protection barriers is required prior to the commencement of any land disturbance or development. Tree protection measures must remain in functioning condition until completion of site landscaping, completion of the project, or until the certificate of occupancy is issued. Authorization to remove the protective devices must be evidenced by approval in writing by the City Arborist or issuance of a final certificate of occupancy. C. Active Tree Protection Devices. Materials for active tree protection must consist of chain link, orange laminated plastic, wooden post and rail fencing or other equivalent restraining material. In addition to fencing, where active tree protection is required, each tree to be saved must be marked at the base of the trunk with blue colored water-based paint. D. Passive Tree Protection. Passive tree protection fencing is to be used only for areas remote from construction activity. Materials for passive tree protection must consist of heavy mil. plastic flagging, a minimum of 4 inches wide with dark letters reading "Tree Protection Area - Do Not Enter" or equivalent signage on a continuous, durable restraint. E. Additional Measures. The developer must take measures to ensure the health of protected trees during construction, including, but not limited to: 1. Water, fertilize and treat the trees for pests or disease as needed, in accordance with standards of the International Society of Arboriculture. 2. Where grading covers the trees with dust, hose them off. 3. Do not prune branches so that equipment or structures "fit" within the tree's protected zone. 4. Do not strip the topsoil or remove the natural leaf mulch or material from beneath a protected tree. 5. Trees should be felled away from, rather than into, tree save areas. 6. Provide adequate mulching and water for trees that will be retained. F. Tree Damage. Any tree designated on a tree protection plan to be saved damaged during construction or as a result of construction, as determined by the City Arborist, must be treated according to accepted standards of the National Arborists Association, or replaced with trees equal to the tree density unit value of the tree removed or damaged. However, any specimen tree damaged must be replaced with trees equal to 2 times the tree density unit value of the tree removed or damaged. Where a damaged specimen tree must be removed, the area occupied by its drip line must remain in a pervious state. A replacement plan must be approved by the City Arborist.
Ask a question about Roswell law
Corpus searches the Roswell sections it holds and shows the ones that match, with their citations. Free, no sign-in.