13.20.300. - Compliance schedules for meeting applicable pretreatment standards.
A. The schedule must contain increments of progress in the form of dates for the commencement and completion of milestones leading to the construction and operation of additional Pretreatment required for the Industrial User to meet the Applicable Pretreatment Standards (e.g., hiring an engineer, completing preliminary plans, completing final plans, executing contract for major components, commencing construction, completing construction, etc.). B. No increment referred to in paragraph A. of this section shall exceed nine (9) months unless an alternate schedule has been approved in writing by the Director. C. Not later than fourteen (14) days following each date in the schedule and the final date for compliance, the Industrial User must submit a progress report to the city including, at a minimum, whether or not it complied with the increment of progress to be met on such date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay, and the steps being taken by the Industrial User to return the construction to the schedule established. In no event shall more than one hundred eighty (180) days elapse between such progress reports.
(Ord. 1460 § 1, 2022)