For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 18-29-306.2.1 — Overexcavation

Municipal Code of Chicago (2026 S-74, current through Council Journal of June 17, 2026) · Municipal Code of Chicago § 18-29-306.2.1

Corpus is an independent public-information project, not the official City of Chicago website. Stable reference: corpuslaw.us/code/fe95e5e3-bf6b-4404-b919-6734878a28cb

18-29-306.2.1 Overexcavation.

Where trenches are excavated below the installation level of the pipe such that the bottom of the trench does not form the bed for the pipe, the trench shall be backfilled to the installation level of the bottom of the pipe with sand or fine gravel placed in layers of 6 inches (150 mm) maximum depth and such backfill shall be compacted after each placement.

Ask a question about Chicago law

Corpus searches the Chicago sections it holds and shows the ones that match, with their citations. Free, no sign-in.