§ 50.12. - Relocation of utility facilities.
The cost of relocating any and all utility facilities on easements or public rights-of-way shall be borne by the party requesting relocation. Payment shall be made in advance based on an estimate of the utility's engineers. If it is not feasible for the utility to relocate facilities on public rights-of-way, it is not obligated to do so. The utility's electric T & D engineering department will provide, at no cost, the initial estimate for the relocation. A non-refundable deposit in the amount of $50 may be required for the preparation of multiple engineering estimates. The deposit will be applied to the final payment. Customers requested to relocate existing overhead residential services underground are eligible for a $150 rebate to be applied to their current electric bill. An approved request for underground service rebate must be on file in the electric T & D engineering department to receive a rebate.
(Ord. No. 935-12-93, § 3, 12-7-93; Ord. No. 543-10-00, § 1(Exh. A), 10-3-00)
Ask a question about Springfield law
Corpus searches the Springfield sections it holds and shows the ones that match, with their citations. Free, no sign-in.